Thu 19 Apr 2007, 8:59 PAM - Palabora Mining Company Limited - Production
PAM
 PAM                                                                             
PAM - Palabora Mining Company Limited - Production overview and statistics      
PALABORA MINING COMPANY LIMITED                                                 
(Incorporated in the Republic of South Africa)                                  
Registration number - 1956/002134/06                                            
JSE Code: PAM & ISIN: ZAE000005245                                              
("Palabora" or "the Company")                                                   
FIRST QUARTER 2007 - OPERATIONS OVERVIEW AND PRODUCTION STATISTICS              

                     1Q     2Q     3Q      4Q     1Q     FULL                   
                     2006  2006   2006    2006   2007   YEAR                    
                                                   2006                         
Palabora mine                                                                   
Tonnes hoisted (`000        2,672  2,771   2,832  2,917  11,018                 
tonnes)               2,743                                                     
Ore treated (`000    2,646  2,633  2,668   2,783  2,886  10,730                 
tonnes)                                                                         
Average ore grade:   0.71   0.70   0.72    0.72   0.71   0.71                   
copper (%)                                                                      
Copper concentrates  51.5   43.0   53.4    61.0   82.1   208.9                  
produced                                                                        
(`000 tonnes)                                                                   
Average concentrate  29.9   30.5   29.4    28.5   27.4   29.4                   
grade:                                                                          
copper (%)                                                                      
Copper in             15.4   13.1   15.7    17.4   22.5   61.5                  
concentrates (`000                                                              
tonnes)                                                                         
Palabora                                                                        
smelter/refinery                                                                
New concentrate       42.0   83.3   87.7    75.5   73.6   288.5                 
smelted on site (`000                                                           
tonnes)                                                                         
New copper anodes     10.0   24.0   22.4    22.2   21.2   78.6                  
produced                                                                        
(`000 tonnes)                                                                   
Refined new copper    14.3   21.9   22.9    22.1   20.8   81.2                  
produced                                                                        
(`000 tonnes)                                                                   
By-products:                                                                    
Magnetite concentrate 251    296    299     281    262    1,127                 
(`000 tonnes)                                                                   
Refined nickel        35     28     25      32     21     120                   
sulphate (tonnes)                                                               
Copper sold as        5      6      -       5      9      16                    
concentrate (`000                                                               
tonnes)                                                                         
Vermiculite plant                                                               
Vermiculite produced  48     48     52      50     50     198                   
(`000 tonnes)                                                                   
Palabora, situated in the Ba-Phalaborwa area of Limpopo, operates South Africa`s
largest copper mine. After 40 years of mining from a large, open-pit operation, 
the ore is now extracted in an underground operation located immediately below  
the open pit. Overall copper production is supplemented by imported copper      
concentrates from Zambia.                                                       
Daily production from the underground mine averaged 32,416 tonnes. The          
production was 3% higher than the prior quarter and 6% higher than the          
corresponding period in 2006. In total, 2,917,430 tonnes of ore were hoisted    
with a copper grade of 0.71%, marginally lower than the previous quarter.       
The ore treated increased by 9% year on year and by 4% compared with the fourth 
quarter of 2006 in line with improved mine output.                              
Copper concentrate tonnage was 35% higher in the quarter compared with the      
previous quarter due to a 4% higher milled tonnage and the transfer of 24,863   
tonnes of low-grade stock from the concentrator to the smelter for sale.        
There was an increase of 6% in concentrate grade during the quarter from        
flotation compared with the fourth quarter of 2006. This was offset by the      
reclaimed low grade concentrate from the 2006 pond inventory which resulted in a
net decrease of 3.6% in copper concentrate delivered to the smelter.            
Smelting capacity was affected during the quarter as a result of the Eskom power
outage for several hours in January 2007 which continued to impact on copper    
recovery for a few days. The reverb furnace was also shutdown for 3 days in     
February for a planned maintenance.                                             
Vermiculite Operations                                                          
Vermiculite production in the first quarter was 4% above the corresponding      
quarter in 2006.  The main contributing factor for higher production was the    
increase in recovery of the finer material.  Along with this, the quality of    
superfine and micron grade improved. Overall plant recovery for the quarter was 
at 68.7%, which was slightly lower than the previous quarter.                   
Magnetite                                                                       
The magnetite production during the quarter was in line with rail logistic      
capacity to both ports of Richards Bay and Maputo with a seasonal reduction in  
deliveries of heavy medium fines to coal washeries due to wet season mining     
conditions.                                                                     
Phalaborwa                                                                      
19 April 2007                                                                   
Sponsor:                                                                        
Barnard Jacobs Mellet Corporate Finance (Pty) Limited                           
Date: 19/04/2007 08:59:45 Produced by the JSE SENS Department.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: