Tue 24 Apr 2007, 9:39 BIL - BHP Billiton Plc - Quarterly Report On Explo
BIL
 BIBLT                                                                           
BIL - BHP Billiton Plc - Quarterly Report On Exploration And Development        
                        Activities Quarter Ended 31 March 2007                  
BHP Billiton Plc                                                                
Share code:         BIL                                                         
ISIN:               BG0000566504                                                
24 April 2007                                                                   
Number 13/07                                                                    
BHP BILLITON QUARTERLY REPORT ON EXPLORATION AND DEVELOPMENT ACTIVITIES         
QUARTER ENDED 31 MARCH 2007                                                     
This report covers the company`s exploration and development activities for the 
quarter ended 31 March 2007.  Unless otherwise stated, BHP Billiton`s interest  
in the projects referred to in this report is 100 per cent and references to    
project schedules are based on calendar years.                                  
DEVELOPMENT                                                                     
During the quarter, the Company announced the sanctioning of the Rapid Growth   
Project 4 (RGP4) at its Western Australia Iron Ore operations.  RGP4`s progress 
will now be reported each quarter.                                              
Also during the quarter, the Company finalised the acquisition of the Genghis   
Khan oil and gas development in the Gulf of Mexico.  Genghis Khan`s progress    
will now be reported each quarter.                                              
PROJECT AND    SHARE OF    INITIAL     PRODUCTION QUARTERLY PROGRESS            
OWNERSHIP      APPROVED    PRODUCTION  CAPACITY                                 
              CAPEX US$M  TARGET      (100%)                                    
DATE                                                  
                                                                                
Petroleum                                                                       
Projects                                                                        
Genghis Khan   365         Mid CY07    55,000     Acquisition completed.        
44%                                    barrels of Rig to be mobilised by        
Oil/Gas                                oil per    May 2007 to complete the      
                                      day        existing well.                 
Atlantis       1,500       Under       200,000    Seven development wells       
South (US)                 review,     barrels of have been drilled with        
44%                        forecast    oil and    six of these wells having     
Oil/Gas                    2H CY07     180        been completed at the end     
million    of March.  The Balder          
                                      cubic feet installation vessel has        
                                      of gas per recommenced installing         
                                      day        flow lines.                    
Neptune (US)   300         End CY07    50,000     On schedule however           
35%                                    barrels of drilling and construction     
Oil/Gas                                oil and 50 costs are under review.       
                                      million    The subsea oil and gas         
cubic feet export and all well flow       
                                      gas per    lines have been                
                                      day        installed.  Four wells         
                                                 have been drilled and          
completions are                
                                                 commencing.                    
Stybarrow      300         Q1 CY08     80,000      On schedule however          
(Australia)                            barrels of  drilling and construction    
50%                                    oil per day costs are under review.      
Oil/Gas                                            Two producing wells and      
                                                  two injector wells have       
                                                  been drilled and              
completed.  Drilling of       
                                                  the fourth producing well     
                                                  has commenced.  The FPSO      
                                                  hull has been delivered       
and the integration of        
                                                  topside modules and the       
                                                  mooring turret are            
                                                  progressing.  Offshore        
installation activities       
                                                  are underway.                 
North West     200         End CY08    800 million On budget and schedule.      
Shelf Angel                            cubic feet  Topsides and jacket          
(Australia)                            gas per day fabrication progressing.     
16.67%                                                                          
Oil/Gas                                                                         
North West     300         Late CY08   LNG         On schedule and revised      
Shelf Train 5                          processing  budget as advised by the     
(Australia)                            capacity of Operator. 10 of 17 module    
16.67%                                 4.2 million shipments have been          
LNG                                    tpa         received.  Last module       
shipment is scheduled for     
                                                  May 2007.                     
Shenzi (US)    1,940       Mid CY09    100,000     On budget and schedule.      
44%                                    barrels of  Hull and topsides            
Oil/Gas                                oil and 50  fabrication continues.       
                                      million                                   
                                      cubic feet                                
                                      gas per day                               

Minerals                                                                        
Projects                                                                        
Alumar -       725         Q2 CY09     2 million   On revised budget and        
Refinery                               tpa         schedule.  Detailed          
Expansion                                          engineering is 60%           
(Brazil) 36%                                       complete, procurement is     
Alumina                                            35% complete and             
construction stands at        
                                                  10% complete.                 
Koala          200         End CY07    3,300       On schedule and budget.      
Underground                            tonnes per  During the quarter,          
(Canada)                               day ore     underground tunnelling       
80%                                    processed   continued and the mine       
Diamonds                                           ventilation facilities       
                                                  were completed.               
Procurement is well           
                                                  advanced and engineering      
                                                  is complete.                  
Ravensthorpe   2,200       Q1 CY08     Up to       On revised schedule and      
(Australia)                            50,000 tpa  budget.  Construction has    
100%                                   contained   passed 90% complete with     
Nickel                                 nickel in   activities now focused on    
                                      concentrate piping completion and         
electrical and                
                                                  instrumentation               
                                                  installation.  Pre-           
                                                  commissioning and             
commissioning of various      
                                                  areas including the           
                                                  Compressor Plant and Ore      
                                                  Preparation facilities is     
in progress.  First ore       
                                                  was delivered during the      
                                                  quarter.                      
Yabulu         556         Q1 CY08     45,000 tpa The Yabulu Expansion is       
(Australia)                            nickel     mechanically complete and     
100%                                              commissioning will start      
Nickel                                            ahead of delivery of feed     
                                                 from Ravensthorpe.             

Iron Ore       1,300       Q4 CY07     20 million On schedule and budget.       
(Western                               tpa        Engineering and               
Australia)                                        procurement activities        
RGP3                                              are essentially complete,     
85%                                               with construction             
Iron Ore                                          activities now 53%            
                                                 complete.                      
Iron Ore       1,850       1H CY10     26 million The project was approved      
(Western                               tpa        on 23 March 2007 and work     
Australia)                                        has commenced.                
RGP4                                                                            
86.2%                                                                           
Iron Ore                                                                        
Samarco Third  590         1H CY08     7.6        On schedule and budget.       
Pellet Plant                           million    The pipeline is 75%           
(Brazil)                               tpa        complete with total           
50%                                               project progress being        
Iron Ore                                          61% complete.                 
MINERALS EXPLORATION                                                            
BHP Billiton continued to pursue global exploration opportunities for key       
commodities of interest utilising both in-house capabilities and the Junior     
Alliance Programme.                                                             
Grassroots exploration continued on diamond targets in Angola, Canada and the   
Democratic Republic of Congo (DRC), on copper targets in Australia, Chile,      
Mongolia, the DRC and USA; and on nickel targets in Australia, Russia and       
Africa.  Exploration for iron ore, coal, potash and bauxite was undertaken in a 
number of regions including Australia, Brazil, Canada and West Africa.          
For the nine months ended 31 March 2007, BHP Billiton spent US$227 million on   
minerals exploration of which US$166 million was expensed.                      
PETROLEUM EXPLORATION                                                           
Exploration and appraisal wells drilled during the quarter or in the process of 
drilling as at 31 March 2007.                                                   
WELL            LOCATION          BHP BILLITON EQUITY STATUS                    
Shenzi-6        Gulf of Mexico    44% BHP Billiton    Hydrocarbons              
               Green Canyon      and operator        encountered.               
Block 609                             Additional appraisal       
                                                     required.  Plugged         
                                                     and abandoned.             
Shenzi-6 -      Gulf of Mexico    44% BHP Billiton    Drilling ahead.           
Side Track 1    Green Canyon      and operator                                  
               Block 610                                                        
Puma-2          Gulf of Mexico    29.805% BHP         Drilling suspended.       
               Green Canyon      Billiton (BP        Additional appraisal       
Block 821         operator)           required. Temporarily      
                                                     plugged and                
                                                     abandoned.                 
Puma-3          Gulf of Mexico    29.805% BHP         Drilling ahead.           
Green Canyon      Billiton (BP                                   
               Block 866         operator)                                      
Torosa-2        Browse Basin      8.33% BHP Billiton  Hydrocarbons              
               Western           (Woodside operator) encountered.  Under        
Australia                             evaluation.                
               WA-30-R                               Plugged and                
                                                     abandoned.                 
Sculptor-2      Dampier Basin     16.67% BHP Billiton Hydrocarbons              
Western           (Woodside operator) encountered.  Under        
               Australia                             evaluation.  Plugged       
               WA-24-R                               and abandoned.             
Sculptor-3      Dampier Basin     16.67% BHP Billiton Hydrocarbons              
Western           (Woodside operator) encountered.  Under        
               Australia                             evaluation.  Plugged       
               WA-24-R                               and abandoned.             
Calliance-2     Browse Basin      20% BHP Billiton    Drilling ahead.           
Western           (Woodside operator)                            
               Australia                                                        
               WA-28-R                                                          
Ruby-2          Trinidad and      25.5% BHP Billiton  Dry hole.  Plugged        
Tobago Block 3    and operator        and abandoned.             
               (a)                                                              
Petroleum exploration expenditure for the nine months ended 31 March 2007 was   
US$265 million.  The amount expensed was US$206 million which includes US$43    
million of exploration expenditure previously capitalised.                      
Further information on BHP Billiton can be found on our Internet site:          
www.bhpbilliton.com                                                             
Australia                                                                       
Samantha Evans, Media Relations                                                 
Tel: +61 3 9609 2898  Mobile: +61 400 693 915                                   
email: Samantha.Evans@bhpbilliton.com                                           
Jane Belcher, Investor Relations                                                
Tel: +61 3 9609 3952  Mobile: +61 417 031 653                                   
email: Jane.H.Belcher@bhpbilliton.com                                           
United Kingdom                                                                  
Mark Lidiard, Investor & Media Relations                                        
Tel: +44 20 7802 4156  Mobile: +44 7769 934 942                                 
email: Mark.Lidiard@bhpbilliton.com                                             
Illtud Harri, Media Relations                                                   
Tel: +44 20 7802 4195  Mobile: +44 7920 237 246                                 
email: Illtud.Harri@bhpbilliton.com                                             
United States                                                                   
Tracey Whitehead, Investor & Media Relations                                    
Tel: US +1 713 599 6100 or UK +44 20 7802 4031                                  
Mobile: +44 7917 648 093                                                        
email: Tracey.Whitehead@bhpbilliton.com                                         
South Africa                                                                    
Alison Gilbert, Investor Relations                                              
Tel: SA +27 11 376 2121 or UK +44 20 7802 4183                                  
Mobile: +44 7769 936 227                                                        
email: Alison.Gilbert@bhpbilliton.com                                           
Date: 24/04/2007 09:39:01 Produced by the JSE SENS Department.                  
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: