Thu 16 Aug 2007, 14:00 GBG - Great Basin Gold - Reports good progress on
GBG
 GBG                                                                             
GBG - Great Basin Gold - Reports good progress on both its development projects 
GREAT BASIN GOLD LIMITED                                                        
(Incorporated in Canada and registered as an External Company in South Africa)  
(Registration No. 2006/021304/10)                                               
Share Code: GBG      ISIN Number: CA3901241057                                  
("Great Basin" or "the Company")                                                
GREAT BASIN GOLD REPORTS GOOD PROGRESS ON BOTH ITS DEVELOPMENT PROJECTS         
August 16, 2007, Vancouver, BC - Great Basin Gold Ltd. ("Great Basin" or the    
"Company") (TSX: GBG; AMEX: GBN; JSE: GBGOLD) announces results for the second  
quarter of fiscal 2007.                                                         
The company continues to make good progress on both its development projects and
released a Feasibility Study for its Hollister Project and an updated           
Feasibility Study for its Burnstone Project, both indicating robust returns.  In
addition our BEE agreement was finalised for the Burnstone Project and the mine 
was officially inaugurated by the Hon. Minister of Minerals, Minister Buyelwa   
Sonjica on 10 July 2007.                                                        
Great Basin Gold does not yet produce gold and, therefore, expenditure is mainly
of a capital nature and directed at the construction of its growth projects. The
Company incurred a loss of CAD$13.8 million (March `07 - CAD$6.7 million) before
tax for the quarter ending June 30, 2007. Expenditures were mainly related to   
development activities at the Burnstone and Hollister projects, with operational
and exploration costs of CAD$9.9 million. CAD$2.7 million was spent at Burnstone
and CAD$7.0 million at Hollister.                                               
The increase in expenditure at Hollister is in line with plan.  At the time of  
acquiring Hecla`s earned-in interest in February 2007, Hecla had completed all  
activities related to Phase I of the original schedule.  As part of Phase II,   
GBG would have had to contribute 50% of all ongoing capital and operational     
expenditure.  Following the acquisition of the Hecla portion, GBG incurs 100% of
the expenditure for 100% of the benefit.                                        
Burnstone Project                                                               
The Company continues to make good progress on the development of the decline at
its Burnstone project in South Africa.  As at 13 August 2007 the decline being  
developed to extract a 26 000 ton bulk sample has achieved 965 metres in linear 
length from the portal entrance with progress on schedule. Approximately 2 400  
metres of development is required before a cross-cut to reef is to be developed.
All inclusive metres developed to date which include muck bays and cubbies,     
amount to 1 240 metres.                                                         
Preparation with the ventilation system requirements for mining the bulk sample 
are on schedule.  From surface the project to raise bore a 3.0m diameter        
ventilation shaft has commenced with curtain grouting being complete.  The      
ventilation switchover is planned for mid-November.                             
The first borehole of the new Area 4 exploration programme has intersected      
Kimberley Reef at a depth of 1 163 metres below surface, and deflection holes   
are currently underway.  This borehole is testing for depth and continuity of   
historic information. Results obtained will update the resource model.  Area 4  
is the depth extension of Area 1 and the plan is to mine any additional ounces  
through the planned established infrastructure.                                 
Hollister Project                                                               
At Hollister, the increased expenditures were made related to the Stage II      
development of the project, the main areas of expenditure being once off costs  
associated with the purchase of underground mining equipment and a Mine Arc     
refuge chamber, as well as the continuation of the underground drilling program 
and trial mining to extract a bulk sample.                                      
The second batch of 3,000 tons of underground ore is being stockpiled on surface
and will be transported to Queenstake Resources for milling once the necessary  
transportation permits have been received.                                      
The Company continued to enhance its management team at both Hollister and      
Burnstone with the appointment of Steve Konieczki (formerly with Newmont) as    
Chief Engineer and Dan Anderson (formerly with Barrick) as Environmental Manager
at Hollister and Derick Botha as Engineering Manager (formerly with Gold Fields)
at Burnstone.                                                                   
For the period 1 April to 30 July 2007, approximately 19,192 feet of underground
drilling had been completed. Excellent results have been achieved so far (News  
Release of July 9, 2007), and assays will continue to be made available on an   
ongoing basis.                                                                  
During the past quarter 37 holes were completed and a summary table of these    
results will be posted on the Great Basin Gold web page (Table of Assay Results 
- Underground Drilling) within the next 2 days.                                 
Highlights include:                                                             
Hole HDB-140 intersected 2.6 ft (0.79 m) grading 0.54 oz/t (18.62 g/t) Au and   
2.69 oz/t (92.40 g/t) Ag from 134.9-137.9 ft (41.1-42.0 m), and 8.5 ft (2.59 m) 
grading 0.32 oz/t (10.96 g/t) Au and 1.52 oz/t (52.04 g/t) Ag from 148.0-158.0  
ft (45.1-48.2 m), and 1.2 ft (0.37 m) grading 1.59 oz/t (54.56 g/t) Au and 6.63 
oz/t (227.12 g/t) Ag from 295.4-296.8 ft (90.0-90.5 m).                         
Hole HDB-141 intersected 1.6 ft (0.49 m) grading 1.18 oz/t (40.49 g/t) Au and   
0.80 oz/t (27.26 g/t) Ag from 151.2-153.0 ft (46.1-46.6 m), and 1.6 ft (0.49 m) 
grading 1.67 oz/t (57.26 g/t) Au and 15.53 oz/t (532.32 g/t) Ag from 255.6-257.7
ft (77.9-78.5m).                                                                
Hole HDB-151 intersected 1.2 ft (0.37 m) grading 3.56 oz/t (121.91 g/t) Au and  
10.27 oz/t (352.21 g/t) Ag from 252.0-253.5 ft (76.8-77.3 m).                   
Hole HDB-157 intersected 3.0 ft (0.91 m) grading 0.98 oz/t (33.44 g/t) Au and   
4.43 oz/t (152.05 g/t) Ag from 199.6-202.9 ft (60.8-61.8 m).                    
Hole HDB-158 intersected 5.4 ft (1.65 m) grading 1.26 oz/t (43.14 g/t) Au and   
25.08 oz/t (859.82 g/t) Ag from 192.8-198.2 ft (58.8-60.4 m), including 3.0 ft  
(0.91 m) grading 1.99 oz/t (68.16 g/t) Au and 44.40 oz/t (1,522.18 g/t) Ag from 
192.8-195.8 ft (58.8-59.7 m).  In addition, this hole intersected 6.4 ft (1.95  
m) grading 2.44 oz/t (83.73 g/t) Au and 1.60 oz/t (54.76 g/t) Ag from 267.0-    
273.4 ft (81.4-83.3m), including 0.6 ft (0.18 m) grading 25.55 oz/t (875.97 g/t)
Au and 10.24 oz/t (351.04 g/t) Ag from 272.8-273.4 ft (83.2-83.3m)). A third    
high grade interval was intersected: 8.6 ft (2.62 m) grading 1.21 oz/t (41.62   
g/t) Au and 0.72 oz/t (24.79 g/t) Ag from 301.0-309.6 ft (91.7-94.4 m),         
including an interval of 2.0 ft (0.61 m) grading 4.68 oz/t (160.42 g/t) Au and  
3.11 oz/t (106.48 g/t) Ag from 307.6-309.6 ft (93.8-94.4 m).                    
Hole HDB-163 intersected 1.9 ft (0.58 m) grading 0.44 oz/t (15.2 g/t) Au from   
197.5 ft - 199.8 ft 0.70m) and 7.4 ft (2.26 m)  grading  0.91 oz/t (31.1 g/t) Au
from 238.8 ft  - 247.8 ft, including an intersection of 1.6 ft grading 2.20 oz/t
(74.79 g/t) Au from 242.4 to 244.3 ft ( 0.58 m).  A third vein includes 0.7 ft  
grading 0.36 oz/t (12.39 g/t) Au from 291.4 - 292.2 ft (0.24 m)                 
Hole HDB-168 intersected 1.0 ft (0.3m) grading 1.24 oz/t (43.35 g/t) Au and 6.73
oz/t (230.8 g/t) Ag from 263.1 - 264.8 ft (0.52 m)                              
Hole HDB-171 intersected 1.0 ft (0.3) grading 13.54 oz/t (464.11 g/t)Au and     
74.73 oz/t (2562.3 g/t) Ag from 237 - 238 ft (0.31 m)                           
Hole HDB-182 intersected 2.4 ft (0.73 m) grading 1.11 oz/t (38.17 g/t) Au and   
2.60 oz/t (89.16 g/t) Ag from 219.7 - 222.3 ft (0.79 m)                         
Hole HDB-175 intersected 0.8 ft (0.24 m) grading 1.31 oz/t (44.91 g/t) Au and   
6.16 oz/t (211.35 g/t) Ag from 27.2-28.0 ft (8.3-8.5 m), and 4.0 ft (1.22 m)    
grading 2.95 oz/t (101.16 g/t) Au and 1.57 oz/t (53.77 g/t) Ag from 230.4-234.4 
ft (70.2-71.5 m), and 4.0 ft (1.22 m) grading 9.22 oz/t (315.98 g/t) Au and     
140.41 oz/t (4,814.02 g/t) Ag from 240.0-244.0 ft (73.2-74.4 m).  This last     
interval contains 1.6 ft (0.49 m) grading 22.92 oz/t (785.74 g/t) Au and 310.94 
oz/t (10,661.05 g/t) Ag from 242.4-244.0 ft (73.9-74.4m).                       
The surface drilling program at Hollister has also progressed substantially and 
has been enhanced by the addition and commissioning of the Great Basin Gold`s   
own diamond drill.  Results and assays will be made available as they are       
received.                                                                       
Ferdi Dippenaar, Great Basin Gold President and CEO commented "The past quarter 
has been one of many milestones both at our Hollister and Burnstone Projects,   
with good progress being made in both areas of development and exploration.     
With Feasibility Studies for both projects being completed, the teams are now   
focussing on delivering what we believe are two quality growth projects. With   
the increased level of activity, we expect the following six months to be just  
as exciting as the first half of the fiscal year."                              
Gernot Wober, P.Geo, a qualified person and V.P. Exploration of Great Basin     
Gold, is monitoring the program on behalf of Great Basin Gold and has reviewed  
this news release.                                                              
Great Basin Gold has two advanced stage gold projects in two of the world`s best
gold environments: the Hollister property on the Carlin Trend of Nevada, USA,   
and the Burnstone Gold Project in the Witwatersrand Goldfield of South Africa.  
For more information on Great Basin and its projects, please visit Great Basin  
Gold`s website at www.grtbasin.com or call Investor Services in South Africa at 
+27 (0) 11 884 1610 or within North America at +1-800-667-2114.                 
Samples collected from the Hollister Development Block Project are stored in a  
secure facility until picked up by Inspectorate America Corporation             
(Inspectorate) of Sparks, Nevada.  Vein samples are analyzed by either metallic 
screen or standard fire assay procedures.  For metallic screen analyses, vein   
sample preparation consists of drying and jaw-crushing the entire sample to 90% 
passing 10-mesh, taking a 500 g sub-sample using a rotary splitter, and then    
pulverizing the 500 g sub-sample to 90% passing 150-mesh using a large capacity 
ring and puck pulverizer.  Gold and silver determinations are by metallic screen
analysis, with two 1 assay-ton (30 g) fire assays completed on the fine         
fraction; the coarse fraction is fire assayed in its entirety.  For standard    
fire assay, vein sample preparation consists of drying and jaw-crushing the     
entire sample to 90% passing 10-mesh, taking a 300 g sub-sample using a Jones   
splitter, and then pulverizing the 300 g sub-sample to 90% passing 150-mesh     
using a large capacity ring and puck pulverizer.  A 30 g charge is fire assayed.
All metal determinations are by gravimetric finish.  Vein samples analyzed by   
standard fire assay will be re-assayed using metallic screen procedures.        
Laboratory Quality Assurance/Quality Control (QA/QC) is monitored using coarse  
reject blanks and assay standards, duplicate fire assays, and Inspectorate`s    
internal standards and blanks.  Coarse blanks (barren rhyolite or landscape     
marble) and assay standards are inserted into the sample sequence as blind      
samples prior to submitting the samples to the laboratory.  Inspectorate also   
inserts assay standards and blanks into the sample stream.   QA/QC results are  
within acceptable limits.                                                       
For additional details on Great Basin and its gold properties, please visit the 
Company`s website at www.grtbasin.com or contact Investor Services at (604) 684-
6365 or within North America at 1-800-667-2114.                                 
Ferdi Dippenaar                                                                 
President and CEO                                                               
No regulatory authority has approved or disapproved the information contained in
this news release.                                                              
Cautionary and Forward Looking Statement Information                            
This release includes certain statements that may be deemed "forward-looking    
statements". All statements in this release, other than statements of historical
facts, that address possible future commercial  production, reserve potential,  
exploration drilling results, development, feasibility or exploitation          
activities and events or developments that Great Basin expects to occur  are    
forward-looking statements. Although the Company believes the expectations      
expressed in such forward-looking statements are based on reasonable            
assumptions, such statements are not guarantees of future performance and actual
results or developments may differ materially from those in the forward-looking 
statements. Factors that could cause actual results to differ materially from   
those in forward-looking statements include market prices, exploitation and     
exploration successes, effect of and changes to government policies regarding   
mining and natural resource exploration and exploitation, availability of       
capital and financing, geopolitical uncertainty and political and economic      
instability, and general economic, market or business conditions. Investors are 
cautioned that any such statements are not guarantees of future performance and 
those actual results or developments may differ materially from those projected 
in the forward-looking statements. For more information on the Company,         
Investors should review the Company`s annual Form 20-F filing with the United   
States Securities and Exchange Commission and its home jurisdiction filings that
are available at www.sedar.com.                                                 
Date: 16/08/2007 14:00:04 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: