Not logged in
  Home   Markets   Shares   Funds   Portfolio   Toolbox   Charting   Alerts   Directory   
 Admin   

Tue 11 Sep 2007, 9:01 FUM - First Uranium Corporation - News Release
FUM
 FIU                                                                             
FUM - First Uranium Corporation - News Release                                  
First Uranium Corporation                                                       
(Continued under the laws of British Columbia, Canada)                          
(Registration number C0777384)                                                  
(South African registration number 2007/009016/10)                              
Share code: FUM & ISIN: CA33744R1029                                            
NEWS RELEASE - September 10, 2007                                               
FIRST URANIUM PROVIDED OPERATIONS UPDATE                                        
Toronto and Johannesburg - First Uranium Corporation (TSX:FIU, JSE:FUM)         
(ISIN:CA33744R1029) ("First Uranium" or "the Corporation") today announced      
that it is making significant progress to advance both of the Corporation`s     
uranium and gold projects.                                                      
Key milestones:                                                                 
Phase 1 of the rehabilitation of the shaft at the Ezulwini Mine ("Ezulwini"),   
has been completed and has begun to hoist ore                                   
the Ezulwini gold plant is on schedule to be commissioned in April 2008, and    
the uranium plant in June 2008                                                  
First Uranium`s Board of Directors has approved a US$11.7 million capital       
program to install the first reclamation station at the Buffelsfontein          
Tailings Recovery Project (the "Project") and increase the mining rate to       
630,000 tonnes per month the Corporation will proceed directly to a full        
feasibility report for the Project by November, by-passing a pre-feasibility    
report the Project is ahead of schedule to complete the flow of tailings from   
the Buffelsfontein Mine to the plant at Mine Waste Solutions ("MWS") in         
November First Uranium holds its funds in cash and guaranteed investment        
certificates and has no exposure to asset-backed commercial paper               
EZULWINI MINE                                                                   
The Ezulwini Mine is an underground mine that has two separate tabular ore      
bodies approximately 400 metres apart. The Upper Elsburg is gold bearing only,  
while the Middle Elsburg is a gold and uranium deposit.                         
The Mine produced gold from its opening in the 1960s until 2001, and uranium    
between 1982 and 1997. In 2001, commodity prices declined to the point where    
the mine wasn`t economical. At that point it was placed on care and             
maintenance. The project was acquired in 2006 and the Corporation began         
underground development in February this year, ahead of schedule.               
One of the key milestsones previously planned for October 2007 was to           
establish a new, low maintenance, rock hoisting system. The Corporation is      
pleased to announce that the 250,000-tonne per month double drum Koepe winder   
has been successfully re-commissioned and hoisting of low-grade gold bearing    
development rock, through the newly installed hanging tower, has commenced      
ahead of schedule. The underground transfer belts for the Upper Elsburg gold    
section are expected be commissioned next week, which will result in the mine   
having re-established more than sufficient hoisting capacity to meet its        
further production requirements.                                                
The first priority to re-opening the mine and establishing a safe and low       
maintenance shaft has been the rehabilitation of the main shaft through an      
overlying lava layer, called the Western Area Formation ("WAF"). Phase 1 of     
the shaft rehabilitation work-comprised of the planned rock consolidation,      
reinforcing and long-anchor support of the WAF where it occurs within the       
Ezulwini shaft barrel-has been successfully completed.                          
The six meter wide zone of weaker rock within the WAF, which has required       
constant maintenance for the past 46 years, has been successfully consolidated  
by injecting liquid resin into the fractured rock at very high pressure. Once   
injected, the resin solidifies at high compressive strengths, which then        
allows for the installation of tensioned, end-anchored high tensile steel       
supports. These anchor supports and the area ground support of the entire       
shaft barrel extends to 100 metres above and 75 metres below the WAF zone. All  
of this work has been executed by independent specialists in the field of       
shaft stabilization and inspected by an independent third party to ensure that  
the consolidation and support work conform to design specifications.            
To further reduce the impact of any work interruption from the WAF, the         
Corporation is installing a hanging steel tower through which the shaft cages   
will be transported through the WAF zone. This installation of the new tower    
steelwork to create the hanging tower has progressed well. Thirteen of the 25   
tower sets have been installed to date.                                         
Phase 2 of the shaft rehabilitation work to support the WAF zone is being       
undertaken from the access provided by the new tower steelwork. This support    
work entails the installation of high tensile mesh screens, which are anchored  
in position using five 370 kiloNewton strength tendons per screen as per the    
design criteria for this area of the shaft.                                     
The tower set installation and Phase 2 secondary support screen installation    
is scheduled for completion in December 2007. Upon completion, re-profiling of  
the shaft concrete and sidewall will commence and is scheduled for completion   
by February 2008.                                                               
Phase 1 of the Ezulwini de-stressing project, which entails the creation of a   
30-metre annulus excavation around the shaft barrel to remove rock stress from  
the WAF, is scheduled to commence in February 2008.                             
Phase 2 of the de-stressing project is intended to develop stopes that will     
intersect the annulus, where 450 metres of development has already been         
completed.                                                                      
Preparation for production stoping is going according to schedule and           
management anticipates that the production of ore from newly equipped stopes    
will commence in October 2007 as planned.                                       
Based on existing surface stockpiles and actual production rates, stockpiles    
will be tailored to ensure that sufficient surface inventory will exist for     
the commissioning of the gold plant in April 2008 and the uranium plant in      
June 2008.  Until the Ezulwini gold plant is commissioned, the Corporation      
will toll treat higher grade gold ore and expects to begin processing in        
October, as planned.                                                            
BUFFELSFONTEIN TAILINGS RECOVERY PROJECT                                        
Since the acquisition of the adjacent operation of Mine Waste Solutions         
("MWS") effective June 6, 2007, the Buffelsfontein Tailings Recovery Project    
(the "Project") has been producing gold from the MWS tailings dams. The         
acquired MWS gold plant will be the new site for the planned uranium plant and  
expanded gold plant for the Project. To allow the Corporation to move all 350   
million tonnes of tailings to the plant for processing will require the use of  
water cannons, pumps, a hydraulic monitoring station and pipelines.             
The construction of the hydraulic monitoring station and new production         
pipelines between the Buffelsfontein number two tailings dam and the MWS gold   
plant is progressing well and is scheduled for commissioning in November 2007   
as planned.                                                                     
The Corporation`s Board of Directors has approved a US$11.7 million capital     
program to install the first monitoring station and to increase the previously  
planned mining rate and throughput at the existing MWS gold plant from 500,000  
tonnes of tailings per month to 630,000 tonnes per month.                       
In addition, the Board has approved an upgrade of the Project`s pre-            
feasibility study to a full feasibility study due for completion in November    
2007. As part of this study, First Uranium will report the results of the       
final pressure leach testing and outline its tailings treatment strategy. The   
Corporation is on track with the accelerated schedule (which resulted from the  
MWS acquisition) to commission the Project`s uranium plant and an expansion of  
the gold plant by November 2008.                                                
"The progress we have made to date gives us greater confidence that the         
Ezulwini Mine and the Buffelsfontein Tailings Recovery Project will meet their  
production targets on schedule and on budget," said Gordon Miller, President    
and Chief Executive Officer of First Uranium.                                   
Cautionary Language Regarding Forward-Looking Information                       
This news release contains certain forward-looking statements. Forward-looking  
statements involve known and unknown risks, uncertainties and other factors     
which may cause the actual results, performance or achievements of First        
Uranium to be materially different from any future results, performance or      
achievement expressed or implied by the forward-looking statements. Risks and   
uncertainties include, among others, the actual results of the planned          
feasibility study for the Buffelsfontein Tailings Recovery Project, the actual  
results of additional exploration and development activities, the timing and    
amount of estimated future production and the cost thereof, the conclusions of  
economic evaluations, failure of plant, equipment or processes to operate as    
anticipated, accidents, labour disputes or other risks of the mining industry.  
Although First Uranium has attempted to identify important factors that could   
cause actual actions, events or results to differ materially from those         
described in forward-looking statements, there may be other factors that cause  
actions, events or results not to be as anticipated, estimated or intended. It  
is important to note, that: (i) unless otherwise indicated, forward-looking     
statements indicate the Corporation`s expectations as at the date hereof; (ii)  
actual results may differ materially from the Corporation`s expectations if     
known and unknown risks or uncertainties affect its business, or if estimates   
or assumptions prove inaccurate; (iii) the Corporation cannot guarantee that    
any forward-looking statement will materialize and, accordingly, readers are    
cautioned not to place undue reliance on these forward-looking statements; and  
(iv) the Corporation disclaims any intention and assumes no obligation to       
update or revise any forward-looking statement even if new information becomes  
available, as a result of future events or for any other reason. In addition,   
First Uranium is in the development stage and is subject to the risks and       
challenges similar to other companies in a comparable stage of development.     
The risks include, but are not limited to, certain business, operational and    
market risks. For a discussion of the Corporation`s risks please refer to the   
Corporation`s Annual MD&A, the 2007 Annual Information Form and other filings,  
which are available on the Corporation`s website www.firsturanium.com and on    
www.sedar.com or upon request from the Corporation.                             
About First Uranium Corporation                                                 
First Uranium Corporation is focused on the development of South African        
uranium and gold mines with the goal of becoming a significant producer         
through the re-opening and development of the Ezulwini Mine, and the            
construction of the Buffelsfontein Tailings Recovery Project. First Uranium     
also plans to grow production by pursuing acquisition and joint venture         
opportunities.                                                                  
First Uranium Corporation                                                       
1240-155 University Avenue, Toronto, ON Canada M5H 3B7                          
www.firsturanium.com                                                            
For further information, please contact:                                        
Bob Tait, VP Investor Relations at 416 558-3858 or bob@firsturanium.com         
Date: 11/09/2007 09:01:22 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: