Not logged in
  Home   Markets   Shares   Funds   Portfolio   Toolbox   Charting   Alerts   Directory   
 Admin   

Fri 1 Feb 2008, 15:27 AEA - African Eagle Resources Plc - Positive Pre-Feasibility Study From
AEA
 AEA                                                                             
AEA - African Eagle Resources Plc - Positive Pre-Feasibility Study From         
    Mkushi Copper Project, Zambia And Latest Drill Results (Correction)         
AFRICAN EAGLE RESOURCES PLC                                                     
(INCORPORATED IN ENGLAND AND WALES, REGISTERED NUMBER 3912362)                  
AIM SHARE CODE: AFE      AIM ISIN: GB0003394813                                 
JSE SHARE CODE: AEA      JSE ISIN: GB0003394813                                 
CORRECT VERSION OF ANNOUNCEMENT RELEASED EARLIER TODAY AT 13:32 ON SENS         
POSITIVE PRE-FEASIBILITY STUDY FROM MKUSHI COPPER PROJECT, ZAMBIA               
AND LATEST DRILL RESULTS                                                        
Highlights                                                                      
-    Pre-feasibility Study demonstrates viability of project                    
-    Definitive Feasibility Study to be completed in Q4 this year               
-    Interim resource estimate of 10.7Mt at 1.11% copper                        
-    Projected total net pre-tax cash flow 
US$215M                             
-    Estimated NPV US$ 60-70M and IRR 35-40%                                    
-    Capital requirement of US$65-70M                                           
-    Minimum mine life of 6 years at 1.6 Mt per annum                           
-    Open pit contract mining                                                   
-    Mill and float plant delivering 96% recovery to a 28% copper               
concentrate                                                                 
-    New drill results include 1.75% copper over 26m and 2.71% over 9m          
-    Upside potential along strike, at depth and in surrounding area            
African Eagle`s Managing Director Mark Parker said: "The results of this        
study are very positive. We look forward to completion of the definitive        
feasibility study leading to a final production decision later this year.       
Development of Mkushi will be a turning point in African Eagle`s history".      
African Eagle Resources plc ("African Eagle", "AFE"  or "the Company",          
ticker AIM: AFE, AltX: AEA) today announces that its 49% owned Mkushi Copper    
Joint Venture, has completed a study to assess the viability of developing      
an open pit copper mine, processing facility and associated infrastructure      
at the Mkushi Copper Project in Zambia (the "Study").  The Study was            
undertaken by the Joint Venture technical team supported by independent         
technical consultants when required.                                            
The study addressed the geological, mining engineering, metallurgy, mineral     
processing, tailings disposal, environmental impact, infrastructure,            
utilities and manpower aspects of the project in some detail, and conducted     
a financial analysis including tests of the sensitivity of the project to       
such variables as copper price, input costs, ore grade, ore/waste ratio and     
mine life.                                                                      
Because the drilling programme is still underway, an interim resource           
estimate of 10.7Mt at 1.11% copper was used for the Study, based on the         
drill results to Q3 2007.  This estimate was made internally by the Joint       
Venture technical team and although not yet independently reviewed, provides    
confidence that sufficient resources exist to make the project payable.         
The Study concluded that the project is economically viable at current          
prices and the Joint Venture is now committed to prepare a definitive           
feasibility study, which will include an independently audited resource         
report fully compliant to Canadian NI 43-101.                                   
The premise of the Study was an open pit mine operated by contractors,          
feeding 1.6Mt of ore per annum to a flotation plant delivering a 28% copper     
concentrate.  The estimated capital cost of the plant and infrastructure is     
US$61M.  On the basis of the interim resource estimate, the mine would have     
a minimum life of 6 years.  At the 2007 average copper price of US$3/lb, the    
total net pre-tax cash flow would be around US$215M and the estimated NPV       
and IRR, US$60-70M and 35-40% respectively, at 10% discount rate.               
In addition to the Study, the Joint Venture has reported new results from       
its continuing drilling programme, which is directed towards defining the       
copper reserves and resources for the definitive feasibility study due for      
completion in late 2008.  The new results include:                              
-    1.75% copper over 26m and 2.71% over 9m from the Munshiwemba Zone          
-    2.05% over 9m from G-Zone                                                  
-    1.93% over 9m and 0.6% over 33m from H-Zone                                
Geological resource                                                             
Prior to establishment of the JV, AFE`s wholly owned Zambian operating          
Company, Katanga Resources Limited, carried out almost 10,000m of               
exploration drilling.  Subsequently, the JV has carried out an additional       
16,000m of diamond drilling and 6,100m of reverse circulation ("RC")            
drilling, and combined all the drilling and sampling data into a digital        
database.                                                                       
Based on the results to mid-Q3 2007, the JV commissioned a geological           
interpretation and  evaluation of the orebody by an experienced geologist       
with appropriate expertise in copper sulphide mineralisation and resources      
modelling.  The interim resource estimate made on this basis was 10.7Mt at      
1.11% copper.  Although this estimate was made internally by the JV and has     
not yet been independently reviewed, it provides confidence that sufficient     
resources exist to make the project economically viable. Drilling will          
continue into Q2 2008 and as part of the definitive feasibility study, the      
partners will prepare audited resource and reserve statements in accordance     
with Canadian NI 43-101.                                                        
Financial Analysis                                                              
The preliminary financial analysis from the Study indicates that the project    
is likely to be economically viable and the Joint Venture now intends to        
prepare a detailed feasibility study.                                           
The estimated capital requirements determined by the Study (based primarily     
on work carried out by Metplant Engineering Services Pty Ltd) is US$61M,        
including a contingency of U$5M. The breakdown of the capital cost estimate     
is set out below.                                                               
US$M                      
             Mine                                     3.3                       
             Infrastructure, buildings and Utilities  15.7                      
             Process Plant                            33.1                      
EPCM                                     8.8                       
                                                                                
             TOTAL                                    60.9                      
Based on these capital requirements, current standard industry costs and        
productivity, the resource estimated from results of drilling to mid-Q3 2007    
and assuming a copper price of US$3.0/lb, the indicative analysis set out in    
the Study suggests that the net pre-tax cash flow from the project will be      
of the order of US$215M over an estimated mine life of 6 years. On this         
basis, at a discount rate of 10% and taking royalties and taxes into            
account, the NPV would be US$ 60-70M and the IRR 35-40%.                        
Tenure and Ownership                                                            
The copper deposits at Mkushi which form the basis of the Study lie within      
Exploration Licence No. PL114. This is surrounded by a larger Exploration       
Licence, No. PL290. Both licences are held by Mkushi Copper Joint Venture       
Company ("MCJV") which is a joint venture owned 51% by Seringa Mining           
Company ("Seringa", a wholly owned subsidiary of CGA) and 49% by Katanga        
Resources Company ("Katanga", African Eagle`s wholly-owned Zambian              
subsidiary).                                                                    
Location                                                                        
The project is located in north central Zambia, some 220 km northeast of the    
capital city of Lusaka and 35 km east of the regional township of Kapiri        
Mposhi. The site is easily accessible via a 20km gravel road leading from       
the sealed highway from Lusaka through Kapiri Mposhi towards Tanzania.          
Plentiful water and electrical power is available nearby. The site lies at      
an altitude of 1100m ASL.                                                       
Geology and history                                                             
The main Mkushi copper deposit is a shear hosted sub-vertical suite of          
mineralisation extending over a distance of 2km, a length of 800m of which      
is exposed in an existing open pit. The deposit is part of a broader            
mineralized belt extending over more than 12km within the tenements. The        
deposit, hosted by metamorphic gneissic rocks and associated with a suite of    
felsic intrusive rocks, is structurally complex, with evidence of several       
generations of faulting. The mineralisation pinches and swells along strike     
and to depth. Copper mineralisation has been intersected to 300m vertical       
depth.                                                                          
The project is located close to the southern end of the Zambian Copperbelt,     
but the style of mineralisation is quite different to that of the               
stratabound deposits for which the copper belt is well known.                   
The deposit was developed by an Italian mining company in the 1970s and in      
its 5 years of operation, produced 2.2 million tonnes of ore at a grade of      
about 0.98% copper. The ore was processed in a small concentration facility     
(part of which still exists on site), to produce 78,000 tonne of copper         
concentrate at a grade of 24% copper. The concentrate was sold to smelters      
within Zambia.                                                                  
Exploration                                                                     
Katanga as the manager and operator of the exploration activities outside       
the area of the known resources at Mkushi, has identified a number of           
prospective zones with potential for discovery of additional copper             
deposits. These will be investigated using either diamond drilling or RC        
drilling during the project development phase.                                  
Mining                                                                          
The JV appointed Zambia-based African Mining Consultants (AMC) to review the    
geotechnical conditions within the existing pit on site and develop design      
parameters on which to base the preliminary open pit design. The Australian     
Company AMC Consultants (AMCC), with involvement from the JV, carried out an    
optimization of the in-house geological model and developed a preliminary       
open pit proposal.                                                              
AMC advise that the pit slopes could be designed with a final overall angle     
of up to 70 degrees, based on tests on drill core.                              
Review of hydrogeological records and recent observations made since the        
existing pit was dewatered, suggests that the mine will not make significant    
water.                                                                          
The study has assumed an annual production rate of 1.6Mt per annum with an      
18 month pre-production period. Mining would probably progress from the         
north to the south along the strike of the deposit.                             
The study contemplates the use of a mining contractor, operating 60t haul       
trucks and 100t excavators, on a two shift per day basis, six days a week.      
Local labour would be used extensively, with the mining contractors training    
local operators. Indicative costs, based on the preliminary pit designs,        
have been obtained from Zambian South African and Australian contractors.       
Metallurgy                                                                      
The JV commissioned AMMTEC Laboratories in Perth to conduct a metallurgical     
test programme on 196kg of sample, which was made up by quartering core from    
a total of 12 diamond drill holes, representing three depth zones and           
covering the entire mineralized zone.  A consultant metallurgist with 40        
years experience in Australia and overseas oversaw the collection of            
appropriate drill core samples and supervised the test programme.               
The results of the programme indicate a potential 96% recovery of copper        
using conventional copper sulphide flotation technology, yielding a             
concentrate containing 28% copper. The samples tested, which are believed to    
be representative, do not have significant levels of any onerous minerals       
and the concentrate is therefore unlikely to be liable to any smelter           
penalties.                                                                      
Ore Processing                                                                  
Metplant Engineering Pty Ltd, which has relevant experience in sulphide         
developments, was commissioned to design and cost the process plant. The        
facility proposed by Metplant will comprise primary crushing followed by        
single stage autogenous milling and a standard flotation circuit followed by    
pressure filter drying, to recover a concentrate from the run-of-mine ore.      
The concentrate will be trucked about 200km to nearby smelters in Zambia for    
sale.                                                                           
Tailings Disposal                                                               
D. Cooper and Associates planned and supervised the tailings disposal           
investigation and testwork. Process plant tailings would be sent to an          
appropriately designed and constructed impoundment located nearby to the        
processing facility.                                                            
The proposed tailings dam is designed to allow surplus water to be recovered    
and returned for use in the process plant.                                      
Environmental Impact Assessment                                                 
The JV commissioned AMC to carry out a baseline study and to produce an         
environmental brief setting out the guidelines for a full environmental         
impact assessment to be conducted as part of the feasibility study. The         
investigation did not discover any significant issues that may affect any       
development at the project area. The existing tailings dump is eroding and      
requires remedial action, but the JV has received confirmation from the         
regulatory body that the previous operators, not the current Joint Venture,     
are responsible for any remediation. The JV is considering enclosing the        
existing tailings within a new development so as to mitigate any possible       
remedial action.                                                                
Infrastructure and Utilities                                                    
Process water can be abstracted either directly from the nearby Lumsemfwa       
River or from a dam to be constructed on the Lumsemfwa or one of its            
tributaries. A final decision will be made as part of the feasibility study.    
Potable water could be sourced from the nearby river and treated to an          
acceptable standard.                                                            
Electrical power can be sourced from either an existing National Grid power     
line, located 300m north of the planned open pit or from the nearby             
Lumsemfwa hydrostation. Power in Zambia is presently charged at US$0.34 per     
kW.                                                                             
It is proposed to upgrade the existing gravel road to allow for all year        
round access of people and materials.                                           
Domestic suppliers of consumables, presently supplying the requirements of      
the Zambian Copperbelt, would likely be contracted to deliver into              
appropriately designed and constructed buildings established onsite at          
Mkushi.                                                                         
Zambian Taxation                                                                
The Finance Minister of Zambia recently announced his intention to introduce    
a new windfall tax regime for copper mines, scaled on the incremental copper    
price from 25% for prices between $2.5 and $3/lb to 75% for prices above        
$3.50/lb.  He also announced a reduction in the depreciation allowance.  The    
proposed new tax regime will be included in the financial analysis for the      
definitive feasibility study.                                                   
New Drill Results                                                               
Prior to the JV`s involvement in the project, Katanga carried out almost        
10,000m of exploration drilling. Subsequently, CGA carried out an additional    
16,000m of diamond drilling and 6,100m of reverse circulation ("RC")            
drilling.                                                                       
Significant assay results from the final quarter of 2007 are indicated in       
the following table. The results are encouraging and have extended the          
resource potential of the three principal mineralisation zones H, L and G       
Zones. The promising results from L Zone, including 14m at 1.23%Cu and 9m at    
1.93m from MH080, highlight the potential of L zone at depth and are the        
target of ongoing drilling. Additional copper mineralisation has been           
located in the hanging wall to both L and H Zones and this will be further      
targeted in the ongoing drilling programmes.  The results from the Mtuga        
Prospect, 3km southwest of the main deposit, are of low order but warrant       
further geological assessment to assist in planning of follow up                
exploration.                                                                    
SIGNIFICANT DIAMOND DRILL RESULTS                                               
HOLE     PROSPECT    FROM   WIDTH  Cu %                                         
NO                                                                              
MH078    L ZONE      126    3      1.31                                         
MH078    L ZONE      138    5      1.49                                         
MH080    L ZONE      111    22     0.46                                         
MH080    L ZONE      153    14     0.95                                         
MH080    L ZONE      229    14     1.23                                         
MH080    L ZONE      247    9      1.93                                         
MH081    L ZONE      109    10     1.07                                         
MH081A   L ZONE      113    9      0.96                                         
MH081A   L ZONE      249    9      1.08                                         
MH082    L ZONE      117    2      2.75                                         
MH083    H ZONE      28     3      2.95                                         
MH083    H ZONE      47     6      0.88                                         
MH083    H ZONE      64     2      2.1                                          
MH083    H ZONE      85     1      1.61                                         
MH084    L ZONE      137    7      1.26                                         
MH084    L ZONE      206    1      3.95                                         
MH085    H ZONE      25     5      1.03                                         
MH086    H ZONE      72     33     0.6                                          
MH086    H ZONE      109    9      0.9                                          
MH086    H ZONE      219    8      0.85                                         
MMT005   MTUGA       62     10     0.74                                         
MMU046   G ZONE      7      5      1.45                                         
MMU047   G ZONE      87     9      2.05                                         
MMU047   G ZONE      103    6      0.98                                         
MMU049   MUNSHIWEMBA 34     4      0.98                                         
MMU050   MUNSHIWEMBA 17     3      1.99                                         
MMU050   MUNSHIWEMBA 31     26     1.75                                         
MMU051   MUNSHIWEMBA 48     9      2.71                                         
John Park                                                                       
Chairman                                                                        
African Eagle Resources plc                                                     
4thFebruary 2008                                                                
Qualified Person                                                                
The Study from which much of this report was abstracted was prepared under      
the supervision of Mr Geoff.G.Jones, F.Aus.I.M.M.CP Mng, who is acting as       
the Qualified Person for the JV  Mr Jones is a fellow of the Australasian       
Institute of Mining and Metallurgy (AusIMM), and a consultant to the JV         
technical team.                                                                 
Information of a technical nature in this report is based on information        
compiled by, or under the supervision of, and approved by Mr Geoff G Jones      
and Mr Simon Plunkett. Mr Plunkett is a Professional member of the              
Australian Institute of Geoscientists and is the on site manager of the         
project The drilling results were assayed by Genalysis Laboratory Services      
Pty Ltd in Perth, Western Australia.                                            
Both Mr Jones and Mr Plunkett have sufficient experience relevant to the        
style of mineralisation and type of deposit under consideration to be           
recognised as Competent Persons as defined in the 2004 Edition of the           
`Australasian Code for Reporting of Exploration Results, Mineral Resources      
and Ore Resources`. Mr Jones and Mr Plunkett consent to the inclusion in the    
report of the matters based on their information in the form and context in     
which it appears.                                                               
Information in this report relating to exploration results is based on data     
reviewed by Mr Christopher Davies BSc, MSc, DIC, FSEG, FAusIMM, Operations      
Director for African Eagle, who is a Fellow of the Australasian Institute of    
Mining and Metallurgy, has more than 26 years relevant experience in mineral    
exploration and is a Qualified Person under AIM rules. Mr Davies consents to    
the inclusion of the information in the form and context in which it            
appears.                                                                        
For further information, see the Company`s web site www.africaneagle.co.uk      
or contact one of the following:                                                
Mark Parker                                                                     
Managing Director                                                               
+44 20 7248 6059                                                                
+44 77 5640 6899                                                                
Nicola Marrin                                                                   
Seymour Pierce                                                                  
+44 20 7107 8000                                                                
Ed Portman/ Leesa Peters                                                        
Conduit PR                                                                      
+44 20 7429 6607 / +44 (0) 7733 635 01                                          
James Duncan                                                                    
Russell & Associates, Johannesburg                                              
+ 27 11 8803924 / +27 82 8928052                                                
About African Eagle                                                             
African Eagle is a diversified mineral exploration and development company      
operating in eastern and central Africa.  The Company`s principal advanced      
projects are the Mkushi Copper Mines project in Zambia and the Miyabi gold      
project in Tanzania, which are being fast-tracked towards production. The       
Company also holds a large well-balanced portfolio of promising earlier         
stage gold and base metal projects, including the Ndola copper project and      
the Eagle Eye iron-oxide copper gold project.                                   
Zambia, Tanzania and Mozambique, the sites of African Eagle`s projects, are     
all countries which have highly prospective geology, relatively low             
aboveground risks and track records of successful major investments in the      
metals and minerals industries.                                                 
African Eagle specialises in project generation and exploration. To take its    
discoveries into production, it seeks to sign up industry partners with         
records of successful mine development. These joint ventures and, in time,      
the revenue from advanced projects, will finance future exploration and new     
discoveries.                                                                    
Technical terms                                                                 
A glossary of technical terms used by African Eagle in this announcement and    
other published material may be found at www.africaneagle.co.uk/african-        
eagle-projects-glossary.html                                                    
Date: 01/02/2008 15:27:06 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: