Not logged in
  Home   Markets   Shares   Funds   Portfolio   Toolbox   Charting   Alerts   Directory   
 Admin   

Thu 14 Feb 2008, 9:25 FUM - First Uranium Corporation - First Uranium Reports Results For The
FUM
 FIU                                                                             
FUM - First Uranium Corporation - First Uranium Reports Results For The         
                             Three And Nine Months Ended December 31, 2007      
First Uranium Corporation                                                       
(Continued under the laws of British Columbia, Canada)                          
(Registration number C0777384)                                                  
(South African registration number 2007/009016/10)                              
ISIN: CA33744R1029                                                              
Share code:  FUM                                                                
("First Uranium")                                                               
NEWS RELEASE - February 13, 2008                                                
FIRST URANIUM REPORTS RESULTS FOR THE THREE AND NINE MONTHS ENDED DECEMBER      
31, 2007                                                                        
All amounts are in US dollars unless otherwise noted.                           
First Uranium commits to commissioning Uranium production despite electrical    
power supply issues                                                             
Toronto and Johannesburg - First Uranium Corporation (TSX:FIU, JSE:FUM)         
(ISIN:CA33744R1029) ("First Uranium" or "the Company") today announced that     
it recorded a net loss of $4.1 million for the three months ended December      
31, 2007 ("Q3 2008") (Q3 2007: $3.8 million), which was primarily the result    
of ongoing expenditures incurred in preparation of the uranium and gold         
projects for production, along with general and administrative expenses.        
Net income for the nine months ending December 31, 2008 ("2008 YTD") was $4.5   
million (2007 YTD: $5.2 million) primarily the result of foreign exchange       
gains on translation of net assets held in Canadian dollars and South African   
rand into US dollars offset by ongoing expenditures.   As the Ezulwini Mine     
is still in a ramp-up phase and has not yet achieved commercial levels of       
production, the revenue less cost of production from its mining operations of   
$2.4 million during both Q3 2008 and 2008 YTD has been capitalized against      
Mine infrastructure costs in Property, Plant and Equipment.                     
Recent Highlights                                                               
During Q3 2008, First Uranium:                                                  
*    toll-treated 27,951 tonnes of ore from the Ezulwini Mine (see              
    Definitions 2) at a recovered grade of 5.6 grams of gold per tonne,         
    producing 5,055 ounces of gold at a Cash Cost (see Definitions 1 ) of       
    $348 per ounce                                                              
*    started drilling specific targets related to the possible expansion of     
    the existing Ezulwini Mine (the "Ezulwini Expansion Program")               
*    completed construction of the pump station at MWS (see Definitions 2)      
    and the 10.5-kilometre pipeline to the MWS gold plant at a total cost of    
$11.7 million                                                               
*    completed the clean up and processing of the remaining tailings of the     
    MWS No.2 tailings dam and commenced hydraulic mining and pumping of         
    material from the Buffelsfontein No.2 dam to the MWS gold plant for         
processing during mid-December                                              
*    processed a total of 832,208 tonnes of tailings through the MWS gold       
    plant at a recovered grade of 0.275 grams of gold per tonne, producing a    
    total of 7,357 ounces of gold at a Cash Cost of $674 per ounce              
*    completed a pre-feasibility study of MWS incorporating higher average      
    uranium and gold price assumptions and increased capital investment,        
    which projected the project`s expected net present value ("NPV")            
    increasing by 71% to $505 million and its internal rate of return           
("IRR") increasing from 69% to 151%                                         
*    entered into an interim off-take agreement with a third party pursuant     
    to which the third party will purchase yellowcake from First Uranium        
    from June 2008 until January 2009 at rates based upon the then              
prevailing spot prices                                                      
*    issued 6.1 million First Uranium shares to Waterpan Mining Consortium      
    ("Waterpan") in connection with the acquisition of the remaining 10%        
    interest in Ezulwini Mining Company (Proprietary) Limited ("EMC") which     
owns and operates the Ezulwini Mine, resulting in EMC becoming wholly-      
    owned by First Uranium (the "Waterpan Transaction")                         
*    ended the period with $215.2 million in cash and cash equivalents          
Subsequent to the end of Q3 2008, First Uranium:                                
*    was granted an unconditional prospecting right for 6,843 hectares of       
    additional property adjacent to the Company`s Ezulwini Mine                 
*    filed the technical report for the pre-feasibility study of MWS, as        
    announced on December 19, 2007                                              
*    due to the significantly reduced supply of electrical power currently      
    available in South Africa, its national power utility ("Eskom")             
    developed concerns about its ability to supply power in the short and       
    medium term.  As a result, First Uranium has had to impose voluntary        
shut-downs of mine development and hoisting activity at the Ezulwini        
    Mine. Most recently, Eskom has implemented compulsory cut-backs of power    
    consumption on businesses and mining companies generally. The specific      
    effects of these measures mandated by Eskom on First Uranium`s              
operations and development projects and any modifications thereto (the      
    "Power Situation") have been and continue to be analyzed.  (see             
    `Preliminary Assessment of the Impact of the Power Situation`)              
During Q4 2008, and prior to the Power Situation, First Uranium had planned     
to:                                                                             
*    commence the upgrading of the MWS gold plant to increase the design        
    capacity from 500,000 tonnes per month to 630,000 tonnes per month, with    
    completion scheduled in Q4 2008                                             
*    upgrade MWS No.5 tailings dam to enable a deposition rate of 630,000       
    tonnes of material per month.   The upgrade is expected to be completed     
    during Q4 2008.                                                             
*    start on-site preparation for the construction of the additional gold      
plant module and the two uranium plant modules at MWS                       
Gordon Miller, President and Chief Executive Officer of First Uranium said,     
"We have, so far, been able to accomplish all the significant objectives we     
have set out to do.  While power supply reductions threaten our ability to      
continue to do that, we have several alternatives to adjust our uses and        
sources of power with the intent to start uranium production as close to plan   
as the Power Situation will allow."                                             
Preliminary Assessment of the Impact of the Power Situation                     
After a preliminary review of the feasibility of the Corporation generating     
its own power, First Uranium`s Board has concluded that the Corporation`s two   
projects are sufficiently robust to continue development as planned based on    
the addition of power generation capacity.                                      
The initial impact of this decision is as follows:                              
For the Ezulwini Mine:                                                          
*    given the uncertainty of power supply at a third-party gold plant to       
    toll-treat the Corporation`s ore, the Board has decided to postpone the     
ramp-up of the underground production and to accelerate the shaft           
    refurbishment program                                                       
*    the weekly operating plan to date has been to focus on mine development    
    and hoisting for three days and on shaft rehabilitation for four days;      
henceforth the intention is to focus entirely on shaft refurbishment        
    until the operation`s gold plant is commissioned in April 2008              
*    the first 50,000 tonne per month module of the gold plant is on schedule   
    for commissioning in April 2008 using existing generator capacity;          
should Eskom power not be forthcoming, the Ezulwini Mine has existing       
    generator capacity of 13 MVA ("1 Megavolt Ampere = 1 Mega Watt") which      
    will be utilized                                                            
*    the first 50,000 tonne per month module of the uranium plant remains on    
schedule for commissioning in June 2008;  a feasibility study of power      
    generation options is underway to reduce power reliance on Eskom            
*    commissioning of the remaining modules of the gold and uranium plant       
    will be deferred by approximately a year to January 2010 to coincide        
with the corresponding mine development plan                                
For MWS:                                                                        
*    the current MWS operation is at present unaffected by the Power            
    Situation as it has been drawing additional power from Buffelsfontein       
Gold Mines Limited ("BGM")                                                  
*    upgrading of the MWS gold plant to increase the design capacity to         
    630,000 tonnes per month remains on schedule for completion in Q4 2008      
*    the expansion of the current operations, however, will require             
additional power; a power generation feasibility study has been             
    initiated with the expected result that the expansion will be delayed by    
    approximately three months                                                  
The decision to invest in generating our own power is a temporary measure       
until the Power Situation has normalized which may take several years.  It is   
expected that the Corporation will be able to monetize a significant portion    
of its investment in owner generated power at that time.                        
Financial Highlights                                                            
(thousands of dollars)    Q3       Q3      2008        2007 YTD                 
                         2008     2007    YTD                                   
Revenue                   6,623    -       15,069      -                        
Operating loss            (4,484)  (1,575) (9,838)     (4,225)                  
Net income (loss) for     (3,998)  (3,787) 4,524       (5,239)                  
the period                                                                      
Revenue                                                                         
During Q3 2008, a total of 12,412 ounces of gold were produced and sold from    
the Ezulwini Mine and MWS, at an average price of $873 per ounce.  Combined     
production during 2008 YTD totaled 25,956 ounces of gold, which were sold at    
an average price of $742 per ounce.                                             
Revenue during Q3 2008 and 2008 YTD as presented above was generated from the   
processing of MWS tailings material and sale of the related gold.               
As the Ezulwini Mine is still in a ramp-up phase and has not yet achieved       
commercial levels of production, the revenue less cost of production from its   
mining operations of $2.4 million has been capitalized against Mine             
infrastructure costs in Property, Plant and Equipment.                          
Operating loss                                                                  
Operating loss includes the following:                                          
*    in Q3 2008, gold was produced at average Cash Costs of $348 and $674 per   
ounce at the Ezulwini Mine and MWS, respectively.  The relatively high      
    average cash costs at MWS can be attributed to the diminishing resources    
    taken from the MWS No. 2 tailings dam, which necessitated a low-volume,     
    high-cost mechanical load and placement operation.                          
*    for Q3 2007 and 2007 YTD, employee compensation costs, consulting and      
    professional fees were $0.6 million and $2.6 million, respectively          
*    higher general, consulting and administrative expenses in Q3 2008 and      
    2008 YTD primarily reflect the higher project development activities,       
the costs of corporate offices in Johannesburg and Toronto and other        
    expenses of operating a public company, which were not applicable in Q3     
    2007 and 2007 YTD.                                                          
*    the Q3 2008 stock-based compensation expense reflects the amortized cost   
of 1,223,001 stock options granted during FY 2007 and the amortized cost    
    of 325,715 stock options granted during 2008 YTD                            
*    during Q3 2008, pumping costs not capitalized at the Ezulwini Mine were    
    included in expenditures until hoisting commenced at the end of October     
2007. As of November 2007, pumping costs are included in the cost of        
    production, which has been capitalized to Mine infrastructure costs in      
    Property, Plant and Equipment                                               
Non-operating income and expenses                                               
Non-operating income and expenses for the periods reported included:            
*    interest income in Q3 2008 and 2008 YTD represents interest earned on      
    the net proceeds from the Offering and the Debentures.                      
*    interest expense in Q3 2008 and 2008 YTD consists of the interest paid     
on the Debentures.                                                          
*    foreign exchange gains on translation in Q3 2008 and for 2008 YTD          
    reflect the strengthening of the Canadian dollar and the South African      
    Rand against the US dollar                                                  
Cash and Capital Expenditures                                                   
Cash and cash equivalents at the end of Q3 2008 were $215.2 million as          
compared with $154.6 million at the end of Q3 2007.  The increase in cash was   
primarily attributable to the net proceeds of $130.6 million received from      
the sale of the Debentures in May 2007, offset by $28.0 million and $76.4       
million of cash utilized for capital expenditure at the Company`s two mining    
operations during Q3 2008 and 2008 YTD, respectively.                           
The Company currently holds its funds in cash and bank-sponsored guaranteed     
investment certificates.  It has no exposure to asset-backed commercial         
paper.                                                                          
Production Overview                                                             
The build-up of production at the Ezulwini Mine during Q3 2008 resulted in      
the toll-treatment of 27,951 tonnes of ore at a yield of 5.6 grams of gold      
per tonne, producing 5,055 ounces of gold at a cash cost of $348 per ounce.     
Production during the first two months of Q3 2008 was negatively influenced     
by the lower than planned grades, but this was more than offset in December,    
when Ezulwini`s production exceeded the planned rate due to higher than         
expected grades.  During Q3 2008, 247.5 metres were developed, bringing the     
total metres developed in the shaft pillar to 833 metres.  Progressive grades   
encountered on the MA and MB raises in the shaft pillar to date were 5.09 and   
5.81 grams of gold per tonne, respectively.                                     
Stoping for de-stressing of the 41 level MB raise has resulted in an area of    
712 square metres being mined at an in-situ stope grade of 4.74 grams per       
tonne.  In the Middle Elsburg ("ME") uranium and gold section, stope            
production in the newly re-established 45 10B stope commenced in Q3 2008 and    
has resulted in an area of 1,059 square metres being mined at an in-situ        
stope grade of 25.78 grams of gold per tonne.                                   
As of the end of December 2007, the clean-up process on surface and             
underground has generated a stockpile in excess of 124,000 tonnes containing    
an average grade of 1.1 grams per tonne of gold or approximately 2,800 ounces   
of recoverable gold, assuming an average recovery rate of 64%.  This            
stockpile is expected to be utilized during mill commissioning, which is        
currently scheduled for April 2008.                                             
At MWS, production activities during Q3 2008 were limited to hydraulic mining   
using high pressure water cannons to slurry the tailings, clean up and          
processing of material from the MWS No.2 tailings dam. As a result of the       
late commissioning of the production infrastructure at the Buffelsfontein       
No.2 tailings dam it was necessary to continue hydraulic mining MWS No. 2       
tailings dam until December rather than October, as previously anticipated.     
The project to construct the initial long-life pump station and 10.5-           
kilometre pipeline was initiated in June 2007 and, while it was delayed due     
to late delivery of slurry pumps and heavy rains that fell during October       
making construction difficult, these new production facilities were             
commissioned in mid-December.                                                   
As the resources in the MWS No.2 tailings dam neared exhaustion during Q3       
2008, it was necessary to use mechanical loading and placement of the remnant   
material, in addition to hydraulic mining, which resulted in increased          
handling costs relative to a normal reclamation operation in addition to the    
reduced tonnages. As a result, only 770,436 tonnes of tailings (0.4 million     
tonnes in Q1 2008 and 1.2 million tonnes in Q2 2008) were reclaimed from the    
MWS No.2 tailings dam during Q3 2008.                                           
The pump station and the pipeline between the Buffelsfontein property and the   
MWS gold plant were completed and commenced operation during December 2007      
which enabled the Company to stop mining from the MWS No.2 tailings dam and     
to initiate the hydraulic mining of the Buffelsfontein No.2 tailings dam on     
the Buffelsfontein property.  The material from the Buffelsfontein No.2         
tailings dam is being transported via the pipeline to the MWS gold plant for    
processing.  Full commissioning of the introduction of the material from        
Buffelsfontein No. 2 tailings dam to the plant is ongoing.                      
The high pressure pump train located at Buffelsfontein No.2 tailings dam is     
performing as designed, despite having a low utilization of 75% during the      
quarter.  Once the second train of standby pumps is, the utilization is         
expected to increase to 95%, which will sustain production at or better than    
the planned rate of 20,800 tonnes per day.  In the meantime, production rates   
have reached 20,000 tonnes per day.                                             
During December, 61,772 tonnes of material from the Buffelsfontein No.2         
tailings dam were processed through the MWS gold plant.  The initial lower      
daily tonnages at the start of the hydraulic mining of the Buffelsfontein       
No.2 tailings dam were the result of vegetation restricting the flow of         
material to the pump station.  By the end of December, the vegetation was       
sufficiently removed to allow the daily tonnages to exceed 17,000 tonnes per    
day.                                                                            
To date, the achieved grade of 0.36 grams of gold per tonne mined from the      
Buffelsfontein No.2 tailings dam is in line with the resource estimates for     
the initial mining benches, although lower than the planned 0.40 grams of       
gold per tonne.  The grade is expected to improve as the lower portion of the   
dam is mined resulting in higher grade material being treated.                  
Definitions                                                                     
1.   "Cash Costs" are costs directly related to the physical activities of      
    producing gold, and include mining, processing and other plant costs,       
third-party refining and smelting costs, marketing expense, on-site         
    general and administrative costs, royalties, in-mine drilling               
    expenditures that are related to production and other direct costs.         
    Sales of by-product metals are deducted from the above in computing cash    
costs. Cash costs exclude depreciation, depletion and amortization,         
    corporate general and administrative expense, exploration, interest, and    
    pre-feasibility costs and accruals for mine reclamation. Cash costs are     
    calculated and presented using the "Gold Institute Production Cost          
Standard" applied consistently for all periods presented.  Total cash       
    costs per ounce is a non-GAAP measurement and investors are cautioned       
    not to place undue reliance on it and are urged to read all GAAP            
    accounting disclosures presented in the consolidated financial              
statements and accompanying footnotes.                                      
2.   First Uranium is currently focused on the rehabilitation and bringing      
    into production of the Ezulwini underground uranium and gold mine (the      
    "Ezulwini Mine") and the recovery of uranium and gold from the existing     
and future surface tailings at the Buffelsfontein mine through gold and     
    uranium plants originally planned to be constructed near the tailings at    
    the Buffelsfontein mine (the "Buffelsfontein Tailings Recovery              
    Project").  In June 2007, the Company acquired Mine Waste Solutions         
(Proprietary) Limited ("MWS"), an existing tailings treatment company       
    which had an operating gold recovery plant in place.As a result of the      
    MWS purchase, First Uranium changed its plans for the Buffelsfontein        
    Tailings Recovery Project so that the historical and future tailings        
from the Buffelsfontein mine (the "Buffelsfontein Tailings") will now be    
    transported by pipeline to the MWS site and processed through MWS`s         
    existing gold plant and, subject to their completion, through the new       
    uranium recovery plant and additional gold recovery facilities which are    
currently being constructed at the MWS site. For greater clarity, the       
    Buffelsfontein Tailings Recovery Project, as enhanced and modified by       
    the addition of MWS, will henceforth be referred to as MWS.                 
Cautionary Language Regarding Forward-Looking Information                       
This news release contains certain forward-looking statements.  Forward-        
looking statements include but are not limited to those with respect to the     
availability of electrical power, the possible addition of owner-operated       
power generation, price of uranium and gold, the estimation of mineral          
resources and reserves, the realization of mineral reserve estimates, the       
timing and amount of estimated future production, costs of production,          
capital expenditures, costs and timing of development of new deposits,          
success of exploration activities, permitting time lines, currency              
fluctuations, requirements for additional capital, government regulation of     
mining operations, environmental risks, unanticipated reclamation expenses,     
title disputes or claims and limitations on insurance coverage and the timing   
and possible outcome of pending litigation.  In certain cases, forward-         
looking statements can be identified by the use of words such as "goal",        
"objective", "plans", "expects" or "does not expect", "is expected",            
"budget", "scheduled", "estimates", "forecasts", "intends", "anticipates", or   
"does not anticipate", or "believes" or variations of such words and phrases,   
or state that certain actions, events or results "may", "could", "would",       
"might" or "will" be taken, occur or be achieved.  Forward-looking statements   
involve known and unknown risks, uncertainties and other factors which may      
cause the actual results, performance or achievements of First Uranium to be    
materially different from any future results, performance or achievement        
expressed or implied by the forward-looking statements.  Such risks and         
uncertainties include, among others, the actual results of current              
exploration activities, conclusions of economic evaluations, changes in         
project parameters as plans continue to be refined, possible variations in      
grade and ore densities or recovery rates, failure of plant, equipment or       
processes to operate as anticipated, accidents, labour disputes or other        
risks of the mining industry, delays in obtaining government approvals or       
financing or in completion of development or construction activities, risks     
relating to the integration of acquisitions, to international operations, to    
prices of uranium and gold.  Although First Uranium has attempted to identify   
important factors that could cause actual actions, events or results to         
differ materially from those described in forward-looking statements, there     
may be other factors that cause actions, events or results not to be as         
anticipated, estimated or intended.  It is important to note, that: (i)         
unless otherwise indicated, forward-looking statements indicate the Company`s   
expectations as at November 9, 2007; (ii) actual results may differ             
materially from the Company`s expectations if known and unknown risks or        
uncertainties affect its business, or if estimates or assumptions prove         
inaccurate; (iii) the Company cannot guarantee that any forward-looking         
statement will materialize and, accordingly, readers are cautioned not to       
place undue reliance on these forward-looking statements; and (iv) the          
Company disclaims any intention and assumes no obligation to update or revise   
any forward-looking statement even if new information becomes available, as a   
result of future events or for any other reason.                                
In making the forward-looking statements in this news release, First Uranium    
has made several material assumptions, including but not limited to, the        
assumption that: (i) consistent supply of sufficient power will be available    
to develop and operate the projects as planned; (ii) approvals to transfer or   
grant, as the case may be, mining rights will be obtained; (iii) metal          
prices, exchange rates and discount rates applied in the preliminary economic   
assessments are achieved; (iv) mineral resource estimates are accurate; (v)     
the technology used to develop and operate its two projects has, for the most   
part, been proven and will work effectively; (vi) that labour and materials     
will be sufficiently plentiful as to not impede the projects or add             
significantly to the estimated cash costs of operations; (vii) that Black       
Economic Empowerment ("BEE") investors will maintain their interest in the      
Company and their investment in the Company`s common shares to a sufficient     
level to continue to support the Company`s compliance with 2014 BEE             
requirements; and (viii) that the innovative work on stabilizing the main       
shaft at the Ezulwini Mine will be successful in maintaining a safe and         
uninterrupted working environment until 2024.                                   
About First Uranium Corporation                                                 
First Uranium Corporation is focused on the development of South African        
uranium and gold mines with the goal of becoming a significant producer         
through the re-opening and development of the Ezulwini Mine, and the            
construction of the Mine Waste Solutions tailings recovery facility.  First     
Uranium also plans to grow production by pursuing acquisition and joint         
venture opportunities.                                                          
First Uranium Corporation                                                       
1240-155 University Avenue, Toronto, ON Canada  M5H 3B7                         
www.firsturanium.com                                                            
For further information, please contact:                                        
Bob Tait, VP Investor Relations at +1 416 558-3858 or bob@firsturanium.com      
14 February 2008                                                                
Date: 14/02/2008 09:25:04 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: