Not logged in
  Home   Markets   Shares   Funds   Portfolio   Toolbox   Charting   Alerts   Directory   
 Admin   

Tue 19 Feb 2008, 9:38 SIM - Simmer And Jack - Report to shareholders for the three months ended 31
SIM
 SIIF                                                                            
SIM - Simmer And Jack - Report to shareholders for the three months ended 31    
December 2007.                                                                  
SIMMER AND JACK MINES, LIMITED                                                  
(Incorporated in the Republic of South Africa)                                  
(Registration number 1924/007778/06)                                            
("Simmers" or "the company")                                                    
Share code: SIM                                                                 
ISIN: ZAE000006722                                                              
Simmer & Jack Mines, Limited                                                    
Report to shareholders for the three months ended 31 December 2007.             
Key features of Q3 F2008 for the Group:                                         
*    Grew revenue 5.3% from R207 million in Q2 to R218 million.                 
*    Recorded a 368% jump in profit from mining activities of R10.8 million     
    compared to a loss of R4.0 million in Q2, as a result of improved           
    recoveries at TGME and higher gold prices achieved during the quarter.      
*    Decreased loss per share by 14% from 5.06c per share in Q2 to 4.36c per    
    share in Q3.                                                                
*    Commissioned two new value-adding projects, namely the new Kemix CIP plant 
    at Buffelsfontein Gold Mine while First Uranium`s MWS saw the new 10.5km    
pipeline and monitoring station come on stream in the quarter under review. 
*    As previously reported, gold production increased 16%, compared to the     
    equivalent period in F2007, but showed a 1.9% decline against the previous  
    quarter owing to the lock-up of 151kg as a result of the commissioning of   
the new CIP plant at Buffels. This `lock-up` of gold is common when         
    commissioning new plant and milling equipment and refers to gold that goes  
    through the system but is locked as a temporary inventory within the new    
    processing plant. It can be accessed when the plant is cleaned or           
decommissioned at a later stage.                                            
*    Group unit cash costs increased marginally by 1.2% per kilogram from R156  
    396/kg in Q2 to R158 190 /kg in Q3.                                         
*    Overall production costs for the group decreased by 1.9% in Q3             
*    Ended the period with cash on hand of R1.7bn.                              
*    Added 1 090 new employees and contractors to the Group during the quarter  
    bringing the total to 8 565 new jobs created by the Group since the         
    beginning of 2005.                                                          
*    Recorded a 38 % increase in attributable gold Reserves and a 519% increase 
    in attributable uranium Reserves as a result of an updated reserve          
    declaration on First Uranium`s Buffelsfontein Tailings Recovery Project     
    (BTRP), operated by MWS.                                                    
*    First Uranium acquired the remaining 10% of Ezulwini Mining Company (Pty)  
    Limited (EMC), from the Waterpan Mining Consortium, in consideration for 6  
    141 009 common shares in First Uranium. As a consequence, Simmers` holding  
    in First Uranium reduced from 65.47% to 62.4% and EMC became a wholly-owned 
subsidiary of First Uranium.                                                
Buffelsfontein Gold Mine Limited (Buffels or BGM)                               
*    Produced 938.68 kg of gold at a cash cost of R161,919/kg compared to 1     
    041.59kg in Q2. The reduction is due to the lock-up of 151kgs as a result   
of the commissioning of the mine`s new Kemix plant. Had the plant been      
    operating under normal circumstances, i.e. without the lock-up coming in to 
    play, Buffelsfontein would have reported a 4.6% increase in production      
    against the second quarter.                                                 
*    Achieved 376 334 fatality-free shifts.                                     
*    Increased face length by 4% from 1 763 m (Q2) to 1 841m in Q3              
*    Completed an initial technical assessment of the Strathmore project. The   
    study conducted by TWP Consulting, indicates that the Strathmore project    
has the potential to treble the mine`s current gold and uranium resources.  
Transvaal Gold Mining Estates Limited (TGME)                                    
*    Frankfort Mine achieved 959 fatality free shifts during Q3 F2008.          
*    Lost time frequency rate improved by 15%.                                  
*    Gold production up 81%.                                                    
*    Revenue up 98.2%.                                                          
*    Costs per kg reduced by 39.4%.                                             
*    Improved net loss by 35%.                                                  
*    Determined metallurgical solution to refractory nature of underground ore  
    that will allow TGME to execute and bring its significant underground       
    resources to account.                                                       
*    Added 9 588 ounces to bring the total compliant surface resource to 133 312
ounces.                                                                     
First Uranium Corporation - comprising the Ezulwini Mining Company and          
Buffelsfontein Tailings Recovery Project (BTRP), of which the operational entity
is Mine Waste Solutions (MWS).                                                  
*    Toll-treated 27,951 tonnes of ore from the Ezulwini Mine at a recovered    
    grade of 5.6 grams of gold per tonne, producing 5,055 ounces of gold at a   
    Cash Cost of $348 per ounce.                                                
*    Started drilling specific targets related to the possible expansion of the 
existing Ezulwini Mine.                                                     
    Completed construction of the pump station at MWS and the 10.5-kilometre    
    pipeline to the MWS gold plant at a total cost of $11.7 million.            
    Completed the clean up and processing of the remaining tailings of the MWS  
No.2 tailings dam and commenced hydraulic mining and pumping of material    
    from the Buffelsfontein No.2 dam to the MWS gold plant for processing       
    during mid-December.                                                        
*    Processed a total of 832,208 tonnes of tailings through the MWS gold plant 
at a recovered grade of 0.275 grams of gold per tonne, producing a total of 
    7,357 ounces of gold at a Cash Cost of $674 per ounce.                      
*    Completed a pre-feasibility study of MWS incorporating higher average      
    uranium and gold price assumptions and increased capital investment, which  
projected the project`s expected net present value (NPV) increasing by 71%  
    to $505 million and its internal rate of return (IRR) increasing from 69%   
    to 151%.                                                                    
*    Entered into an interim off-take agreement with a third party pursuant to  
which the third party will purchase yellowcake from First Uranium from June 
    2008 until January 2009 at rates based upon the then prevailing spot        
    prices.                                                                     
*    Issued 6.1 million First Uranium common shares to Waterpan Mining          
Consortium (Waterpan) in connection with the acquisition of the remaining   
    10% interest in Ezulwini Mining Company (Proprietary) Limited (EMC) which   
    owns and operates the Ezulwini Mine, resulting in EMC becoming wholly-owned 
    by First Uranium (the Waterpan Transaction).                                
*    Ended the period with $215.2 million in cash and cash equivalents.         
CHANGES TO THE BOARD                                                            
David Brown resigned as director with effect from 31 December 2007.             
CHANGES TO THE MANAGEMENT TEAM                                                  
Subsequent to the end of Q3, the Group restructured its executive team to best  
allocate the experience and strengths of management and position the Group for  
future growth.                                                                  
*    Jim Fisher, formerly Chief Operating Officer for FIU moves to Executive    
Vice President, Corporate Development in First Uranium`s Toronto office.    
*    Syd Caddy, formerly Simmers` Executive in charge of New Business           
    Development, joins FIU as Executive Vice President and Chief Operating      
    Officer, responsible for all FIU`s operating and exploration activities     
*    John Gould joins FIU as Vice President Exploration and Business Development
    responsible for all FIU`s exploration, technical services and growth        
    projects and will report to Syd Caddy.                                      
*    Barry Smit, formerly part of the Simmers team, joins FIU as Consulting     
Mining Engineer and will focus on FIU`s expansion project at the Ezulwini   
    Mine                                                                        
*    Wouter de Vos, previously GM of Buffelsfontein Gold Mine, joins FIU as     
    General Manager of the Ezulwini Mine, an underground uranium and gold mine. 
*    Mark Glasspool, currently GM at TGME, will replace Wouter de Vos, taking up
    the reins at Buffelsfontein Gold Mine later this month. A replacement GM    
    for TGME will be announced shortly.                                         
FINANCIAL OVERVIEW                                                              
Simmers is in a growth and development phase that includes significant          
exploration activity. Short-term results should therefore be viewed in the      
context of a company gearing itself to optimally deliver into the future. The   
emphasis remains on growing mineral resources and completing capital projects to
deliver on a sustainable, low cost production basis well into the future.       
In Q3 F2008, Simmers generated revenue of R218 million compared to R207 million 
for the previous quarter (Q2 F2008). The increase is mainly due to the increased
production at TGME and higher metal prices received.                            
Group cash unit costs increased by 1.2% per kilogram from R156 396/kg in Q2 to R
158 190/kg in Q3, notwithstanding the impact of the lock-up of 151kg of gold as 
a result of the commissioning of the new CIP plant (the Kemix plant) at Buffels.
Had the lock-up not occurred, cash costs would have equated to R141 459/kg.     
The total production cost decreased quarter on quarter from R211 million to R207
million. This excludes production costs from Ezulwini Mine that were capitalised
owing to the fact that this project is still in a pre-production phase. The     
build-up of production at the Ezulwini mine during Q3 2008 resulted in the toll-
treatment of 27,951 tonnes of ore at a yield of 5.6 grams of gold per tonne,    
producing 5,055 ounces of gold at a cash cost of US$355 per ounce.  Production  
during the first two months of Q3 2008 was negatively influenced by the lower   
than planned grades, but this was more than offset in December, when Ezulwini   
Mine`s production exceeded the planned rate due to higher than expected grades. 
The Ezulwini production costs would have accounted for R11.6 million of the     
total production cost.                                                          
As at the end of the quarter Simmers had cash and cash equivalents of R1.7      
billion compared to R2.1 billion for the previous quarter. This is mainly due to
expenditure on capital projects at Buffels of R29.5 million, First Uranium of   
R273.1 million and R28.4 million at TGME, as well as working capital and        
operational requirements.                                                       
As at 31 December 2007 Simmers had total assets of R3.7 billion (R3.7 billion   
for Q2); total liabilities of R1.4 billion (R1.4 billion for Q2) and            
shareholder`s equity of R2.3 billion (R2.3 billion in Q2).                      
MATERIAL TRANSACTIONS                                                           
In Q3, Ezulwini Mine generated revenue of R27.7 million and production costs of 
R11.7 million. These were capitalised owing to the fact that this project is    
still in a pre-production phase.                                                
The production for the Group would have been as much as 30% higher compared to  
the equivalent period in F2007, were it not for the fact that Buffelsfontein    
Gold Mine`s production for the third quarter was affected by the lock-up of     
151kg of gold as a result of the commissioning of its new CIP plant.            
Further material transactions disclosed are: (i) the expenditure on the approved
capital projects at Buffels, TGME and at First Uranium amounting to R331        
million; and, (ii) share option costs with respect to the issuance of share     
options to new employees as well as the costing of shares that vested during the
quarter which accounted for R14.2 million.                                      
POWER CRISIS                                                                    
On 25 January 2008, Eskom, South Africa`s national power utility, declared that 
it was unable to guarantee power supply to the country`s mining industry.       
Mines were subsequently permitted to operate at 70% of their historical power   
usage, sufficient to operate basic maintenance and safety functions. Following  
discussions with industry, this was raised to 80%, with the promise that power  
could be gradually increased to 90% provided the national grid remained stable. 
In effect this means that while the Group`s operations are currently operating  
at 90% power, there is no guarantee that this supply can be sustained. Eskom    
expects the immediate power crisis to last between four and six weeks. Once the 
situation has stabilised, mining companies will still only be permitted to use  
90% of their historical power usage for the foreseeable future - probably until 
2012.                                                                           
Eskom has advised that historical usage will be based on the amount of power    
consumed during September and October of 2007. The issue for Simmers is that    
significant growth projects came on line post that period. By December 2007 the 
Group had already exceeded its historical base load power as defined by Eskom,  
and was preparing to ramp up power usage in line with the roll-out of these     
growth projects.                                                                
In terms of consumption, 70% of a mine`s power demands are a base load for      
essential services i.e. pumping of water, ventilation of working places, winding
operations for essential staff, the operation of fridge plants and lighting of  
essential underground workings. A request to cut utilisation of electricity by  
10% can reduce production capabilities by as much as 20% as the only power usage
that can safely be reduced is the portion devoted to operations.                
As a Company committed to sustainable growth, to stop these development projects
in mid-stream is simply not an option. Simmers was created specifically as a    
growth and development company and we are still in the very early phases of our 
plans.  The Company however is encouraged by statements from the Ministry of    
Trade and Industry that the Eskom power crisis will not impact on growth and    
development projects.  To this end, Simmers is working closely with Eskom to cut
power where it can and to secure the power it needs to complete its projects.   
These discussions are ongoing and the Company will review current production and
expansion plans as soon as assurances are forthcoming from Eskom.               
In the interim, management has conducted a desk-top analysis on the possibility 
of the Group generating its own power should Eskom be unable to accommodate its 
growth targets.                                                                 
The initial impact of the power situation on each operation is as follows:      
Buffelsfontein Gold Mine                                                        
*    Assuming Eskom`s calculation of the historical base load correlates with   
management`s view of the base load required for this particular operation - 
    in this instance, 57 MVA* - the current mine plan will be able to go ahead  
    without significant changes to total production. To ensure that Buffels can 
    operate within 90% of this power target, the surface tonnages will be       
curtailed in favour of underground operations.  On this basis, operating at 
    90% power will result in a production variance of 6% of the current plan.   
    This has been achieved through extensive rationalisation of current         
    operations.                                                                 
* 1 Megavolt Ampere = 1 Mega Watt at a power factor of 1.                   
*    New growth projects: the successful commissioning of the new Kemix plant   
    paves the way for the introduction of the Mega Float Project  designed to   
    treat some 29 million tonnes of old waste rock material at an average grade 
of 0.52 g/t. The Mega Float Project has not been factored into historic     
    base load usage, so will require its own power supply in the short to       
    medium term. This is expected to require 5 MVA of power at an estimated     
    capital cost of          R20 million. Despite this, the project economics   
remain sufficiently attractive, and are expected to add an average of 63    
    kilograms of gold per month to Buffels` production profile for the nine     
    years of the project. The project also allows Buffels to bring              
    approximately 10 million additional tonnes of waste rock dumps that were    
previously considered unviable, to account.                                 
TGME                                                                            
TGME currently comprises an underground mine at Frankfort, a gold plant at      
Pilgrim`s Rest and a substantial exploration drilling project. While the        
Frankfort mine and the drilling programmes are generator-powered, the plant has 
felt the brunt of the power crisis as it has been subject to load shedding. With
the increasing stabilisation of the national grid these load shedding episodes  
have become less severe, but it is unclear whether this is a temporary respite. 
Simmers is monitoring the situation. Should it deteriorate to a point where it  
has material effect on production levels, the installation of a 2.5 MVA         
generator, with 6.6kV will be considered.                                       
First Uranium                                                                   
After a preliminary review of the feasibility of the Corporation generating its 
own power, First Uranium`s Board has concluded that the Corporation`s two       
projects are sufficiently robust to continue development as planned based on the
addition of power generation capacity.                                          
The initial impact of this decision is as follows:                              
For the Ezulwini Mine:                                                          
*    Given the uncertainty of power supply to a third-party gold plant which    
    toll treats the Corporation`s ore, the FIU Board has decided to postpone    
the ramp-up of the underground production and to accelerate the shaft       
    refurbishment programme.                                                    
*    The weekly operating plan to date has been to focus on mine development and
    hoisting for three days and shaft rehabilitation for four days; henceforth  
the intention is to focus entirely on shaft refurbishment until the         
    operation`s gold plant is commissioned.                                     
*    The first 50,000 tonne per month module of the gold plant remains on       
    schedule for commissioning in April 2008 using existing generator capacity; 
should Eskom power not be forthcoming, the Ezulwini Mine has existing power 
    generating capacity of 13 MVA which will be utilized.                       
*    The first 50,000 tonne per month module of the uranium plant remains on    
    schedule for commissioning in June 2008; a feasibility study of power       
generating options is underway to reduce power reliance on Eskom;           
*    Commissioning of the remaining modules of the gold and uranium plant will  
    be deferred by approximately a year to January 2010 to coincide with the    
    corresponding mine development plan.                                        
For MWS:                                                                        
*    The current MWS operation is presently unaffected by the Power Situation as
    it has been drawing additional power from Buffelsfontein Gold Mine.         
*    Upgrading of the MWS gold plant to increase the design capacity to 630,000 
tonnes per month remains on schedule for completion in Q4 2008.             
*    The expansion of the current operations, however, will require additional  
    power; a power generation feasibility study has been initiated with the     
    expected result that the expansion will be delayed by approximately three   
months.                                                                     
The decision to invest in generating its own power is a temporary measure until 
the power situation has normalized.  It is expected that the Group will be able 
to monetise a significant proportion of this investment once the power crisis   
has passed.                                                                     
GROUP OUTLOOK                                                                   
The power constraints come at a time when the Group is finally beginning to see 
results at all its operations, after an intense period of investment in         
development and construction.                                                   
The spot price for uranium ranged between $75 and $92 per pound during Q3 2008  
and closed on $90 per pound at the end of December. This is well above the $50  
per pound on which First Uranium has based its project economics for the next 20
years. First Uranium Corporation has entered into short-term non-fixed delivery 
spot market uranium contracts but has not yet signed any contracts that have    
defined commitments to supply uranium and does not expect to do so until it is  
nearer production in June 2008.                                                 
In terms of production, Q4 will see Ezulwini Mine focusing full time            
on the refurbishment of the shaft pillar, given that power concerns have        
curtailed toll-treatment at the neighbouring plant. In this way, the            
shaft refurbishment will now be complete 3 months ahead of schedule, to         
coincide with the opening of the first module of the Ezulwini gold plant on     
schedule in April 2008.                                                         
At MWS it will be business as usual in Q4, with the upgrading of the MWS gold   
plant to increase the design capacity to 630,000 tonnes per month still on      
schedule for completion in Q4 2008. The power generation feasibility study      
required to expand the current operations has also been initiated.              
At Buffels, production for Q4 will be impacted by safety stoppages and the      
unexpected curtailing of production in the latter part of January. A fatal      
accident on 24 January resulted in the mines` number two shaft closed for 5     
days. This incident coincided with Eskom`s communique that it could not         
guarantee power supply which resulted in three shifts being lost, amounting to a
loss of approx 500 ounces per day.                                              
On the plus side, Buffels will be in a position to halve its CAPEX requirements 
going forward, having been through a period of intense capital build up. This   
excludes new ventures such as the Mega Float Project, for which board approval  
for capital funding of R181-million, including power generation facilities, will
be sought in Q4.                                                                
Buffels also anticipates being able to access large ore blocks for the first    
time since operations resumed at the mine in 2005. This is expected to have a   
significantly positive effect on production in the next 2 to 3 quarters. The    
full benefits of all the value-add projects completed in the last and current   
quarter will also facilitate a continuous increase in production with the       
associated decrease in unit costs.                                              
At TGME, the BIOX project has been initiated and will progress to a final       
process design which will incorporate acceptability trials on representative ore
samples from both Beta and Rietfontein Mine. TGME will seek board approval and  
funding for BIOX expansion and underground mine development which includes      
additional funding for the continuation of the surface heap leach exploration   
project. While the Board has given its approval in principle that funds will    
need to be raised for this project, this approval is subject to an independent  
technical evaluation of the surface and underground projects, due out in March  
2008. Approval will also rest on the requisite mining rights having been        
granted.                                                                        
SELECTED UNAUDITED FINANCIAL INFORMATION                                        
The following table sets out selected, unaudited financial information relating 
to Simmers for the quarter ended 31 December 2007 and year to date.             
Selected Consolidated Financial       Q3         Q2        Var    YTD          
 Information                           31 Dec 07  30 Sep           31 Dec 07    
 (in `000s of ZAR)                     R`000      07        %      R`000        
                                                  R`000                         
Income Statement                                                               
 Gold revenue                          218 135    207 160   +5.3   589,189      
 Production costs                      207 319    211 197   +1.8   610 347      
 Profit / (Loss) from mining           10 816     (4 037)   +367.9 (21 158)     
activities                                                                     
 Amortisation & depreciation           11 422     14 608    +21.8  33 227       
 General administration & overhead     5 697                +83.7               
 expenditure                                      35 032           74 421       
(Loss) from operations before         (6 303)    (53 677)  +88.3  (128 806)    
 interest and taxation                                                          
 Interest received                     27 682     37 701    -26.6  100 832      
 Dividends received                    1          2 615                         
-99.9    2 616      
                                                  -                             
 Finance charges                       43 956     41 086    -7.0   104 380      
                                                                                
(Loss) before taxation                (22 576)   (54 447)  .+58.5 (129 738)    
                                                                                
 Balance Sheet                                                                  
 Total assets                          3 743 327  3 738546  +0.1   3 743 327    
Cash and cash equivalents             1 726 100  2 051472  -15.9  1 726 100    
 Current liabilities                     321 704   275 483  -16.8    321 704    
 Non-current liabilities               1 146 831  1 180669  +2.9   1 146 831    
 Share capital                           841 172   829 520  -1.4     841 172    
Revenue                                                                         
Increased production at TGME combined with higher metal prices received         
contributed to the 5.3% increase in revenue, compared to Q2.                    
Production costs                                                                
At Buffels total production costs (including depreciation for production        
equipment and other non-cash production expenses) for the December 2007 quarter 
improved by 3.5%, falling from R157.9 million for Q2 to R152.3 million. The cash
production element (only taking into account direct production costs) thereof   
also improved by 4.4%. This was primarily as a result of lower summer tariffs   
charged by Eskom during Q3.                                                     
An increase of 9.6% at TGME in the production costs of R21.3 million for Q3 was 
reported compared to Q2. The increase is mainly due to production related       
expenses that increased proportionately to the increase in production.          
Ezulwini mine began producing gold this quarter and reported production costs of
R11.6 million, which have been capitalised.                                     
Profit / (Loss) from mining activities                                          
A profit from mining activities amounting to R10.8 million was realised during  
Q3 compared to a loss of R4 million in Q2. This 368% increase relates mainly to 
higher production at TGME linked with overall improved gold prices achieved. The
focus on ramp up and construction brings cash flow closer, with gold operations 
expected to be cash positive by end June 2008 (Q1 F2009). First Uranium is      
expected to be cash positive by end March 2009 (Q4 F2009). This is based on     
meeting production forecasts prior to the onset of the power crisis.            
Financial Position and Liquidity                                                
Cash and non-cash assets                                                        
Cash and cash equivalent balances at 31 December 2007 decreased from R2.1       
billion in Q2 to R1.7 billion in Q3 primarily as a result of the planned capital
expenditure at Buffels, Ezulwini Mine and TGME. Other increases in current      
assets relate to gold-in-circuit and stockpile inventory increases at Ezulwini  
Mine and MWS; increases in trade and other receivables comprising of value-added
tax for goods and services refunds.                                             
Non-current assets increased from R1.5 billion in Q2 to R1.8 billion due to the 
capitalisation of assets at Ezulwini, Buffels and TGME.                         
Total Liabilities                                                               
As at 31 December 2007 Simmers had total liabilities of R1.4 billion (September 
07: R1.4 billion).                                                              
Additional Information                                                          
A detailed Management Discussion and Review (MD&A) for the quarter can be found 
on the Company`s website at www.simmers.co.za under the heading `Latest Results`
on the Simmers home page. The full MD&A for First Uranium Corporation is posted 
on  www.firsturanium.com                                                        
Conference call                                                                 
Simmers will conduct a conference call with investors to discuss the Company`s  
third quarter results for the 2008 financial year and related matters at 16h00  
Johannesburg time on Tuesday 19 February 2008. The conference call will be      
available simultaneously to all interested investors and the media at South     
Africa                      on 011 535 3600, or toll-free on 0800 200 648 (South
Africa only).                                                                   
An announcement regarding toll free numbers for the USA, UK and Canada as well  
as playback details is available on the company`s website on www.simmers.co.za  
Forward-looking Information                                                     
This MD&A and financial statements for the quarter ended 31 December, 2007      
contain certain forward-looking statements.  Forward-looking statements include 
but are not limited to those with respect to the price of uranium and gold, the 
estimation of mineral resources and reserves, the realization of mineral reserve
estimates, the timing and amount of estimated future production, costs of       
production, capital expenditures, costs and timing of development of new        
deposits, success of exploration activities, permitting time lines, currency    
fluctuations, requirements for additional capital, government regulation of     
mining operations, environmental risks, unanticipated reclamation expenses,     
title disputes or claims and limitations on insurance coverage and the timing   
and possible outcome of pending litigation.  In certain cases, forward-looking  
statements can be identified by the use of words such as "plans", "expects" or  
"does not expect", "is expected", "budget", "scheduled", "estimates",           
"forecasts", "intends", "anticipates", or "does not anticipate", or "believes"  
or variations of such words and phrases, or state that certain actions, events  
or results "may", "could", "would", "might" or "will" be taken, occur or be     
achieved.  Forward-looking statements involve known and unknown risks,          
uncertainties and other factors which may cause the actual results, performance 
or achievements of Simmers to be materially different from any future results,  
performance or achievement expressed or implied by the forward-looking          
statements.  Such risks and uncertainties include, among others, the actual     
results of current exploration activities, conclusions of economic evaluations, 
changes in project parameters as plans continue to be refined, possible         
variations in grade and ore densities or recovery rates, failure of plant,      
equipment or processes to operate as anticipated, accidents, labour disputes or 
other risks of the mining industry, delays in obtaining government approvals or 
financing or in completion of development or construction activities, risks     
relating to the integration of acquisitions, to international operations, to    
prices of uranium and gold.  Although Simmers has attempted to identify         
important factors that could cause actual actions, events or results to differ  
materially from those described in forward-looking statements, there may be     
other factors that cause actions, events or results not to be as anticipated,   
estimated or intended.  It is important to note, that: (i) unless otherwise     
indicated, forward-looking statements indicate the Mines` expectations as at 28 
January 2008; (ii) actual results may differ materially from the Mine`s         
expectations if known and unknown risks or uncertainties affect its business, or
if estimates or assumptions prove inaccurate; (iii) the Mine cannot guarantee   
that any forward-looking statement will materialize and, accordingly, readers   
are cautioned not to place undue reliance on these forward-looking statements;  
and (iv) the Mine disclaims any intention and assumes no obligation to update or
revise any forward-looking statement even if new information becomes available, 
as a result of future events or for any other reason.                           
Date: 19/02/2008 09:38:27 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: