Not logged in
  Home   Markets   Shares   Funds   Portfolio   Toolbox   Charting   Alerts   Directory   
 Admin   

Mon 31 Mar 2008, 7:36 WEZ - Wesizwe Platinum Limited - Completion of bankable feasibility study and
WEZ
 WEZ                                                                             
WEZ - Wesizwe Platinum Limited - Completion of bankable feasibility study and   
capital construction go-ahead                                                   
Wesizwe Platinum Limited                                                        
(Incorporated in the Republic of South Africa)                                  
(Registration number 2003/020161/06)                                            
JSE code: WEZ   ISIN: ZAE000075859                                              
COMPLETION OF BANKABLE FEASIBILITY STUDY AND CAPITAL CONSTRUCTION GO-AHEAD      
Highlights                                                                      
*    Construction given the go-ahead on the back of positive Bankable           
    Feasibility Study (BFS) confirming commercial viability of the              
    Frischgewaagd-Ledig Complex                                                 
*    Results show a base case with a Net Present Value of R9,5 billion at a     
     real discount rate of 5% and an Internal Rate of Return at 18 % with an    
    anticipated Life of Mine of 35 years                                        
*    Capital cost estimates of R5,6 billion                                     
*    58 month construction programme commencing in the third quarter of 2008    
*    Construction funding will be arranged by a consortium of South African     
    banks and will consist of a mix of equity and debt finance                  
*    Electrical self-generation contingency of R168 million taken into account  
to allow for possible electricity supply delay by Eskom                     
*    The total run of mine (ROM) production would be 2,76 million tons of ore   
    per annum, producing an average of 350 000 PGE(4) ounces at steady state    
    yielding a total of 10 million ounces                                       
*    Production profile starts with a combination of tonnage output from the    
    two reefs, building up to 180 000 tpm from Merensky and 50 000 tpm from     
    UG2. Once the Merensky is depleted, the output profile shifts to 230 000    
    tpm from UG2                                                                
*    Primary access through a twin vertical shaft system comprising of a 8,5 m  
    diameter downcast main, men and materials shaft (980 m depth) and an upcast 
    ventilation shaft/second outlet of 7,5 m diameter (910 m depth)             
*    Best mining practices confirm a hybrid mining method comprising            
conventional drilling, blasting and cleaning with trackless transport of    
    ore                                                                         
*    Plant design includes primary one-stage crushing into a SAG mill with Mill-
    Float-Mill-Float (MF2) circuit                                              
Comment                                                                         
Mike Solomon, Chief Executive Officer, said:                                    
"This is a significant milestone in the short history of the project as we are  
now undergoing the critical transition from a pure exploration play to being a  
fully fledged platinum producer, over the next five years.                      
We are delighted with the results of the BFS, which was delivered a full year   
ahead of schedule in terms of the January 2005 project plan. We have yet again  
delivered on the promises made to investors at that time.                       
The study confirms the commercial viability of the project with a Net Present   
Value of R9,5 billion and an IRR of 18 %, which are well within the commercial, 
economic and technical parameters planned for at the outset of the project.     
It also cogently demonstrates the success of the Reverse Engineering approach   
that we have taken.                                                             
The proposed mine design, comprising an underground mine and a surface          
concentrator plant, allows for fast production build-up and flexibility to      
address the characteristics of the ore body. The estimated Life of Mine is 35   
years at a monthly production rate of 230 000 tpm, producing an average of 350  
000 PGE(4) ounces per annum when steady state is reached in 2016. First         
production of ounces is scheduled for 2011 with a 5 year ramp to steady state.  
The capital cost estimate of R5,6 billion is exected to peak in 2013. The       
consortium of South African banks announced in December 2007 will act as lead   
equity and debt arrangers to secure the necessary finance for the development   
of the project.                                                                 
We look forward to an exciting new stage in the company`s life as we continue   
to build shareholder value through the capital construction phase."             
Introduction                                                                    
Wesizwe Platinum Limited has concluded its BFS and given the go-ahead for       
the construction of a platinum mine on its core assets on the farms             
Frishgewaagd portions1, 3, 4, and 11, and the farm Ledig portions 1 and 2.      
The execution of the BFS was carried out by a core multi-disciplinary team      
which included:                                                                 
*    Wesizwe EXCO and financial staff                                           
*    Wesizwe Platinum Owner`s Team                                              
*    TWP (study and potential EPCM contractor)                                  
*    Murray & Roberts Cementation (shaft sinking contractors)                   
*    The Mineral Corporation (mineral advisors)                                 
*    TWP-ES (environmental consulting)                                          
In addition, external third party reviews were conducted on many significant    
aspects of the work and recommendations were incorporated into the BFS to       
further optimise designs and models. Where appropriate, simulations were also   
carried out to verify designs.  The technical risk is considered manageable     
as there are no new or unproven technologies incorporated in the project.       
Commercial viability                                                            
The recommendation from the Pre-feasibility Study, published on 30 March 2007,  
to take one option through to full feasibility formed the basis of the BFS.     
The financial results of the study confirm that the project is commercially     
viable. The Net Present Value (NPV) is R 9,5 billion including mineable         
Inferred Resources (R4,7 billion excluding Inferred Resources) with a real      
Internal Rate of Return (IRR) at 18%  (16% excluding Inferred Resources).       
These figures are calculated on a base commodity price of US $1,125/oz for      
platinum, US $315 for palladium, US $4 200 for rhodium and US $650 for gold     
converted to ZAR with a short-term exchange rate ranging from R7,57 to R8,90    
in 2012 and a long-term exchange rate of R9,17 and real discount rate of 5%.    
The project has a estimated life of mine of 35 years at a monthly production    
rate of 230 000 tpm and producing an average of 350 000 ounces PGE(4) per       
annum during steady state, at an average cash cost of R320/ton. It is worth     
noting that the 230 000 tpm production rate is a major improvement on the 180   
000 tpm envisaged during the Pre-feasibility Study stage and reflects the       
underlying quality and size of the ore body, and extent of the proposed mine.   
Metallurgical test work has also shown that the project is feasible and that    
the proposed plant design should achieve the planned production performance.    
Confirmation of the detailed metallurgical operating parameters will be         
obtained once mining commences and bulk ore samples are made available for      
further metallurgical test work.                                                
Capital Costs                                                                   
The base date (October 2007) capital cost estimate is R5,6 billion. This        
figure includes an overall contingency of R275,3 million. An additional         
electrical self-generation contingency of R168 million was taken into           
account to allow  for any electricity supply delays by Eskom.                   
Production profile                                                              
The production profile starts with a combination of tonnage output from the     
two reefs, building up to 180 000 tpm from Merensky and 50 000 tpm from UG2.    
Once the Merensky is depleted, the output profile shifts to 230 000 tpm from    
UG2 with a mine life of 35 years.                                               
Mining practices confirm a hybrid mining method comprising a combination of     
conventional and mechanised mining of the two platinum reefs.                   
The Merensky and UG2 ore and waste will be handled in separate ore-passes and   
silos as they are hoisted, and in the case of ore, treated separately.  This    
will be controlled by an integrated ore management system.                      
Funding                                                                         
Wesizwe is not yet a cash generating entity and its exploration programme up    
to BFS has been funded by equity. The construction phase of the project is      
expected to be funded by way of a combination of equity and debt finance.       
A consortium of South African banks (Deutsche Securities (SA) (Pty) Ltd, ABSA   
Capital a division of ABSA Bank Limited, and the Development Bank of Southern   
Africa Limited) has been mandated to arrange this finance. The banks will       
provide a project debt and equity package and will assist with the equity       
offering for the equity portion of the financing. The directors and management  
of Wesizwe will determine the appropriate debt equity ratio for the project     
finance.                                                                        
Infrastructure Design                                                           
Wesizwe`s Frischgewaagd-Ledig Complex project will consist of an underground    
mine and a surface concentrator plant. The current mine infrastructure designs  
were conducted through a process of exacting iterations in parallel with the    
updating of the geological studies. To this extent, the proposed design is      
considered to represent the most appropriate method to exploit Wesizwe`s        
mining block as it allows flexibility to address the structural geology.        
This greenfield project takes into account the establishment of all surface     
infrastructure, servitudes for bulk power and water supply, the sinking and     
equipping of ventilation and main shafts, associated underground infrastructure,
ancillary excavations and access development to establish a footprint for full  
production.                                                                     
The mine design allows for fast production build-up to enhance shareholder      
value in the project. The Wesizwe BFS has addressed the major activities with   
sufficient technical details to give confidence to the estimates in accordance  
with best practice.                                                             
The design of the shaft sinking and development, the largest capital cost       
activity, involved Murray & Roberts Cementation from early on in the planning   
phase, to ensure close alignment between the design engineers and the principal 
contractors on cost estimation, project scheduling and project implementation.  
This provides a high level of confidence in Wesizwe`s ability to deliver the    
project on time and within budget.                                              
The proposed access to the ore body is through the sinking of an independent    
twin vertical shaft system.  This will comprise of an 8,5 m diameter (depth 980 
m) down-cast man, material and rock shaft and an up-cast ventilation shaft of   
7,5 m diameter (depth 910 m). The shafts are strategically positioned to most   
effectively access both reef planes.                                            
The mine design is specifically designed to allow for optimum flexibility in    
terms of mining method (conventional, mechnanised or hybrid) over the Life of   
Mine and was guided by the latest geological information (structure as of June  
2007 and block model as of August 2007) as well as the preliminary results      
obtained from the 3D Geoseismic Survey confirming the presence of flat-lying    
Merensky and UG2 reefs which should, to a greater or lesser extent, be amenable 
to mechanised mining.                                                           
The intention is to build the concentrator plant in three modules that will     
allow flexibility and ensure optimum PGM recoveries. The design includes primary
one-stage crushing into a SAG mill with Mill-Float-Mill-Float (MF2) circuit.    
The plant will treat the Run-of-Mine ore to produce a concentrate that will be  
sold through an off-take agreement to be finalised in due course.               
Construction Programme                                                          
The BFS envisages a 58 month construction programme which will include sinking  
activities and construction of the first module of the concentrator plant.      
Scheduled construction will begin during the third quarter of 2008 with         
production ramp up commencing in 2011 reaching steady state production of 230   
000 tpm by 2016.                                                                
Conclusion                                                                      
The results of the BFS are very positive and confirm that the project is        
commercially viable with IRR at 18 % and Net Present Value of R9,5 billion.     
The third party reviews by independent consultants confirm that there are no    
major technical risks with the proposed designs.                                
The mining layout allows flexibility in term of mining method to overcome       
possible unforeseen and difficult geological conditions.                        
Metallurgical test work has also shown that the project is feasible and that    
the proposed plant design should achieve the planned production performance.    
Wesizwe is delighted to proceed to the implementation phase of the project.     
Johannesburg                                                                    
31 March 2008                                                                   
ENQUIRIES                                                                       
College Hill                                                                    
Fred Cornet                                                                     
Tel:  +27 (0) 11 447 3030                                                       
Wesizwe Platinum Limited                                                        
Tel: +27 (0) 11 994 4600                                                        
www.wesizwe.com                                                                 
Date: 31/03/2008 07:36:03 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: