Tue 13 May 2008, 16:42 TEL - Teal Increases Quarterly Copper Concentrate
TEL
TEL                                                                             
TEL - Teal Increases Quarterly Copper Concentrate Production In The DRC To      
              12,000 Tonnes                                                     
TEAL Exploration & Mining Inc.                                                  
Corporate Access Number:  31403                                                 
ISIN:  CA8781511099                                                             
(Incorporated in Yukon, Canada on 1 June 2005)                                  
SA Company Registration Number:  2006/003229/10                                 
JSE share code:  TEL                                                            
JSE short name:  TEAL                                                           
TEAL INCREASES QUARTERLY COPPER CONCENTRATE PRODUCTION IN THE DRC TO 12,000     
TONNES                                                                          
*    The Lupoto copper mine in the DRC increases quarterly concentrate          
    production from 9,000 tonnes to 12,000 tonnes                               
*    Exploration drilling program continuing at the Kasonta Copper Project in   
    the DRC with initial assay results received, of which the best include:     
*    23 metres at 4.8% copper (from a depth of 25 metres); and              
    *    6 metres grading 4.4% copper (from a depth of 52 metres)               
*    Independent Technical Report increases measured and indicated resources    
    at Konkola North`s South and East limbs from 24.9 million tonnes at         
2.36% copper to 51 million tonnes at 2.35% copper - an increase of 105%     
    *    South and East limb inferred resources now 26.9 million tonnes from    
         the 47.6 million tonnes announced previously - however grade           
         increases by 24% from 1.98% to 2.46% copper                            
*    The inferred resource within Area `A` now totals 219.5 million         
         tonnes at a copper grade of 2.64% - for 12,8 billion pounds copper     
*    Antofagasta Minerals acquires an initial 30% interest in two of TEAL`s     
    exploration properties in Zambia                                            
*    Antofagasta pays $5m for the 30% interest and has the right to a       
         50% interest in the properties by spending an additional $4.5m, of     
         which $2m is committed expenditure                                     
*    TEAL in discussion to increase debt from $50m to $85m                      
*    The new facilities, which will remain guaranteed by ARM, would be      
         for a one-year period from first draw-down                             
In releasing results for the three month period ended March 31, 2008, TEAL      
Exploration & Mining Incorporated (TSX-"TL") (JSE-"TEL") ("TEAL" or the         
"Company") announced that its Lupoto mine in the Democratic Republic of Congo   
("DRC") has increased quarterly copper concentrate production from 9,000        
tonnes to 12,000 tonnes.                                                        
Total run-of-mine ore produced for the quarter was 205,605 tonnes. Lower        
grade ore continues to be stock-piled for future use in a processing plant,     
which forms part of a pre-feasibility study that is underway for a larger       
mine that will produce approximately 40,000 tonnes a year of LME `A` grade      
copper cathodes.                                                                
Resource definition drilling and exploration: TEAL had previously identified    
a resource with inferred historical estimates (in terms of National             
Instrument 43-101) of 6.7 million tonnes grading 3.13% copper at the Lupoto     
Copper Project.  In addition to the 73 boreholes previously drilled by Union    
Miniere du haut Katanga ("UMHK") and Gecamines, TEAL has drilled an             
additional 136 boreholes for 15,589 metres. A three phase drilling campaign     
at the Lupoto Copper Project, which started in March 2007, has now been         
completed.  The first two drilling phases were undertaken to confirm and        
verify the historical mineral resource estimate and to undertake infill         
drilling to upgrade the mineral resource confidence level.  The third phase     
of drilling was aimed at increasing the resource along strike in areas          
previously not drilled.  SRK Consulting (South Africa) (Pty) Limited was        
appointed in March 2008 to complete an Independent Technical Report. The        
result of the resource estimation and the final technical report according to   
NI 43-101 is expected in May 2008.                                              
At Kalumines` Kasonta Copper Project, situated about 1,000 meters to the east   
of the Lupoto Copper Project, TEAL started exploration drilling in January      
2008. The Kasonta area is defined by a clearing due to copper poisoning of      
soils. This anomaly was never drilled in the past, but extensive pitting and    
trenching was undertaken by UMHK and G?camines. This work previously defined    
an inferred historical resource estimate, pre-dating NI 43-101, of 1,5          
million tonnes grading 5.18% copper, estimated to a depth of 30 metres.         
The phase 1 drilling program, now underway, aims to evaluate the copper         
mineralization at Kasonta by drilling along grid lines spaced, initially, 300   
meters apart. This drilling program has progressed well with 22 holes,          
totalling 6,780 metres of core, already completed. The results of the first     
two boreholes, for which assay results have been received, are summarized as    
follows:                                                                        
Borehole ID         Depth from (m) Intersection (m)    TCu%                     
    KASD 134        0.00               16.00               2.73                 
                   26.50               16.50               2.02                 
                   46.80                6.70               1.92                 
59.50                2.30               1.55                 
                   65.50               10.50               1.97                 
    KASD 136        0.00               10.50               3.20                 
                   25.00               23.30               4.80                 
52.00                6.00               4.39                 
                        133.00          2.30               1.47                 
The Konkola North Copper Project is a large undeveloped underground copper      
resource located within the greater Konkola area. Existing infrastructure at    
the Konkola North South Limb deposit includes a 423-metre deep, vertical and    
concrete lined shaft, complete with head-frame, two ventilation shafts and      
three main access haulage levels, interlinked with several production sub-      
levels.                                                                         
During the last quarter, TEAL received an Independent Technical Report,         
signed-off by SRK Consulting South Africa (Pty) Limited ("SRK"), for the        
resource estimation of the Konkola North Copper Project. The updated measured   
and indicated resource estimation statements for the South and East Limb        
areas are now:                                                                  
*    Combined:           51.0 million tonnes at a grade of 2.35% copper;        
*    South Limb:         32.3 million tonnes at a grade of 2.16% copper; and    
*    East Limb:          18.8 million tonnes at a grade of 2.67% copper.        
Together with Area `A`, a resource of 246.4 million tonnes at 2.62% copper is   
estimated in the inferred category within the total Konkola North property.     
All resource categories were estimated at a 1% total copper cut-off.            
The latest updated resource estimation by SRK shows that the resources          
estimated in the measured and indicated categories have increased by 105% to    
51 million tonnes at similar grades. This equates to an increase of over        
600,000 tonnes of contained copper.  Correspondingly, the resources defined     
in the inferred category has decreased to 26.9 million tonnes from 47.6         
million tonnes, however the copper grade has increased by 24% from 1.98%        
total copper to 2.46% total copper.                                             
The Konkola North Copper Project feasibility study, based on an operation to    
mine the South and East Limb ore bodies utilizing the previously developed      
infrastructure which will be re-equipped, envisages an operation producing      
1,500,000 tonnes of run-of mine copper ore per annum from the existing shaft.   
The feasibility study has largely been completed.  The impact of the new        
fiscal regime in Zambia is bow being assessed.                                  
The recently updated resources in SRK`s Independent Technical Report relating   
to the southern portion of the Konkola North property, referred to as the       
greater Area `A`, show resources in the inferred category of 219.5 million      
tonnes at a copper grade of 2.64% (equivalent to 12,78 billion pounds of        
copper). Additional exploration drilling work is required to increase the       
geological confidence of this resource, and an 18,000 metre exploration         
drilling program is underway. TEAL has to date completed three boreholes and    
a further four boreholes are presently in progress.                             
Korea Zinc Company, Limited ("KZC") was TEAL`s previous partner in various      
exploration areas within the Copperbelt Joint Venture area in Zambia. During    
the last quarter, TEAL acquired KZC`s 30% interest and the joint venture        
agreement has now been terminated.                                              
At the same time, TEAL signed a joint venture agreement with Antofagasta        
Minerals SA ("Antofagasta Minerals") for an initial 30% interest in two of      
TEAL`s exploration licences that are held in the Copperbelt Joint Venture.      
Subject to certain conditions precedent, TEAL and Antofagasta Minerals will     
create an incorporated joint venture to hold the two licence areas - PLLS 73    
(TEAL`s Area 2) and PLLS 100 (TEAL`s Area 4) - as well as all previous          
geological data and information pertaining to these two areas.  Antofagasta     
Minerals, which has paid TEAL $5 million for its 30% interest, has agreed to    
expenditure of $4.5 million, of which $2 million is committed expenditure, to   
acquire an additional 20% interest in the two exploration areas. TEAL           
(Zambia) Limited, a wholly-owned TEAL subsidiary, is the current licence        
holder. The two licence areas cover approximately 2,067km2 of strategically     
positioned geological terrains adjacent to large operating mines on the         
Zambian Copperbelt. The two large scale prospecting licences incorporated in    
the new joint venture are adjacent to TEAL`s 100%-owned mining licences in      
Zambia, namely: the Konkola North Copper Project mining licence area; and the   
Mwambashi Copper Project mining licence area. TEAL now has 100% ownership of    
the Mwambashi mining licence.                                                   
The Otjikoto Gold Project is situated within TEAL`s 100% owned Otavi            
Exploration Area, which totals 3,800km2 in north-central Namibia, where the     
Company discovered vein-hosted gold mineralization. The gold occurs as `free`   
and often coarse gold within predominantly pyrrhotite-magnetite-pyrite veins.   
During the quarter, TEAL completed an additional 25 diamond drill holes for     
4,300 metres to further define the high grade gold shoots. In addition, a       
further 49 reverse circulation boreholes (3,800 meters) were completed to       
further increase and upgrade the indicated resource category. To date about     
75% of all assays of the boreholes drilled on the Otjikoto Gold Project have    
been received and a new geological model has been created. Updated resource     
estimation for the Otjikoto Gold Project is commencing, and is expected to be   
completed by end June 2008.                                                     
TEAL recently made application for a number of mineral exploration licences     
in the Republic of Mozambique and six licences were approved of which three     
are reconnaissance licences and three are exploration licences. These           
applications granted are primarily for uranium, with associated metals.         
Recent airborne geophysical surveys acquired by TEAL allowed for the            
identification of a number of well defined radiometric targets. These include   
targets for various styles of uranium mineralization, which are now held        
under exclusive exploration and reconnaissance licences totaling some           
1,297km2.  TEAL intends to commence field reconnaissance of the exclusive       
exploration licences within the next two months and initiate studies of the     
reconnaissance licences. TEAL has established a new company, TEAL Mining        
Mo?ambique, Limitada, to operate its exploration activities in the country.     
TEAL is currently in discussions to increase its bridging facilities to a       
total of $85 million.  This is an increase of $35 million on the $50 million    
facility that TEAL had secured.  The new facilities, which will be in place     
for at least a one year period, will be guaranteed by African Rainbow           
Minerals Limited ("ARM"), TEAL`s major shareholder, subject to South African    
Reserve Bank approval.  As at March 31, 2008, the Company had available         
resources of $6.0 million as well as $5 million undrawn on the Company`s $50    
million bridge loan facility, which is repayable on August 31, 2008.            
Over the last quarter, the Company generated an increased operating revenue     
of $6.6 million (December 31, 2007: $4.1 million) following higher sales of     
copper concentrates from the Lupoto Copper Project in the DRC, which reached    
full production towards the end of the 2007 calendar year. After deducting      
the cost of sales of $4.2 million ($2 million), a gross profit of $2.3          
million ($2.1 million) was recorded for the three months. The cost increase     
is primarily as a result of higher mining costs at Lupoto following increased   
production tonnages mined.  After other expenses, primarily exploration and     
development expenses of nearly $5 million, TEAL recorded a consolidated net     
loss of $6.5 million, or $0.12 cents a share, which compares to a loss of       
$4.7 million, or $0.09 loss per share, for the three months ended December      
31, 2007.                                                                       
Mr. Claus Schlegel, Pr. Sci. Nat. (No. 400149/90), TEAL`s Vice President:       
Exploration and Business Development, is the "qualified person" for the         
content of this press release in terms of National Instrument 43-101.           
ends                                                                            
NOTES:                                                                          
TEAL is incorporated under the laws of the Yukon, Canada and its common         
shares are listed on the Toronto Stock Exchange ("TSX") and the JSE Limited     
("JSE"). The common shares of the Company trade under the symbol "TL" on the    
TSX and "TEL" on the JSE.                                                       
TEAL is a mineral development and exploration company with development          
projects and exploration areas in Namibia, Zambia and the DRC. TEAL has a       
portfolio of base and precious metal development projects and complementary     
exploration areas, and the Company continues to seek other opportunities,       
mainly in southern and central Africa                                           
TEAL has targeted specific core projects: the Konkola North Copper Project in   
Zambia; the Otjikoto Gold Project in Namibia; and the Kalumines Copper-Cobalt   
Project in the DRC. TEAL also has interests in various other mineral licence    
areas in Zambia and in Namibia on which the Company continues drilling and      
other exploration activities.                                                   
ADDITIONAL TEAL INFORMATION CAN BE FOUND AT: www.tealmining.com                 
For further details contact:                                                    
Julian Gwillim (VP: Investor Relations and Corporate Development) on +27 82     
4524 389 (SA); or julian@tealmining.com,                                        
Tuesday, May 13, 2008                                                           
Sponsor: Investec Bank Limited                                                  
Date: 13/05/2008 16:42:01 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: