Not logged in
  Home   Markets   Shares   Funds   Portfolio   Toolbox   Charting   Alerts   Directory   
 Admin   

Wed 21 May 2008, 7:52 FUM - First Uranium Provides Production And Projec
FUM
FIU                                                                             
FUM - First Uranium Provides Production And Project Development Update For      
              Quarter Ended March 31, 2008                                      
First Uranium Corporation                                                       
(Continued under the laws of British Columbia, Canada)                          
(Registration number C0777384)                                                  
(South African registration number 2007/009016/10)                              
Share code:  FUM & ISIN: CA33744R1029                                           
FIRST URANIUM CORPORATION                                                       
May 21,  2008                                                                   
FIRST URANIUM PROVIDES PRODUCTION AND PROJECT DEVELOPMENT UPDATE FOR QUARTER    
ENDED MARCH 31, 2008                                                            
All amounts are in US dollars unless otherwise noted.                           
Toronto and Johannesburg - First Uranium Corporation (TSX:FIU, JSE:FUM)         
(ISIN:CA33744R1029) ("First Uranium" or "the Company") today announced its      
production results for the fiscal quarter ended March 31, 2008 ("Q4 2008"),     
during which the Company processed 1,592,242 tonnes of reclaimed tailings at    
its Mine Waste Solutions tailings recovery project ("MWS") and 18,669 tonnes    
of underground gold ore from its Ezulwini Mine ("Ezulwini") through a toll      
treatment arrangement.  Gold production totaled 9,725 ounces for the period.    
Subsequent to March 31, 2008, the Company commenced production of uranium and   
gold ore at Ezulwini, which is currently being stockpiled on surface.  The      
Company`s uranium plants are on schedule to begin to be commissioned in June    
2008 at Ezulwini and in December 2008 at MWS.                                   
In mid-June 2008 First Uranium expects to announce its annual audited           
financial results for the year ended March 31, 2008                             
Highlights for Q4 2008                                                          
Mine Waste Solutions tailings recovery project ("MWS")                          
-    gold plant feed capacity upgraded from 6.0 to 7.6 million tonnes of        
    processing per annum ("MTPA")                                               
-    approximately 1.6 million tonnes of tailings were processed, producing     
    7,030 ounces of gold                                                        
-    first 7.8 MTPA pump station completed at Buffelsfontein tailings dam       
    complex                                                                     
-    commissioning of gold plant upgrades and a new mining and processing       
    system scheduled for completion in July 2008                                
-    30-megawatt power plant for expansion sourced                              
    preliminary assessment for construction of a Company-owned sulphuric        
    acid plant was completed, with completion of a specification and            
    procurement study scheduled for July 2008                                   
-    construction of new 7.8 MTPA uranium and pyrite flotation plant on track   
    to commence commissioning during December 2008 (part of "Phase 1B" of       
    the MWS project)                                                            
-    construction of new 7.8 MTPA gold plant and 1.5 MTPA uranium plant on      
track to commence commissioning during December 2008 (also part of          
    "Phase 1B" of the MWS project)                                              
Ezulwini Mine ("Ezulwini")                                                      
-    toll treated 18,669 tonnes of underground ore to produce 2,695 ounces of   
gold                                                                        
-    the third party toll treating gold ore from Ezulwini suspended this        
    operation due to the power shortage and, as a result, the Company           
    postponed the ramp-up of the underground development and accelerated the    
shaft refurbishment program                                                 
-    underground development and hoisting of ore started again in April and     
    uranium and gold ore is being stockpiled on surface                         
-    2.4 MTPA gold plant commissioning commenced during April 2008 (3 months    
earlier than anticipated at the time of the Company`s initial public        
    offering in December 2006) and on schedule for production of gold on        
    carbon in June and gold bullion in July 2008                                
-    first of four 0.6 MTPA mills is being commissioned, with the second mill   
due to commence commissioning in September 2008                             
-    underground stope availability is on schedule in the Middle Eslburg        
    (uranium and gold) section but somewhat behind schedule in the Upper        
    Elsburg (gold) section, which is not expected to affect the planned         
production profile                                                          
-    standby diesel generated power connected into new plant                    
-    1.2 MTPA uranium plant construction on track to commence commissioning     
    in July 2008 for uranium concentrate (yellow cake, ammonium diuranate,      
or "ADU") production in August 2008                                         
Affecting both projects, First Uranium also disclosed the results of updated    
technical reports on April 21, 2008 which detail the Company`s proactive        
approach to reducing future operating costs and securing sufficient power and   
sulphuric acid to run its operations as planned.   Summary cash flow models     
related to these technical reports have been posted to the Company`s website    
(www.firsturanium.com) and provide revised estimates for production, capital    
and operating costs.  The full technical reports are scheduled to be filed on   
SEDAR and posted to the website by early June.                                  
Mine Waste Solutions                                                            
Buffelsfontein No. 2 Dam Commissioning                                          
Commissioning of the gold plant expansion from 6 MTPA to 7.6 MTPA and the       
installation of the pumping system to bring tailings from the Buffelsfontein    
dam complex has progressed on schedule and within budget.                       
As expected, the transition of mining from the Stilfontein dam complex to the   
Buffelsfontein dam complex has resulted in a reduction in unit cash costs for   
gold production and it is expected that planned life of project unit costs      
will be achieved when final commissioning is completed by mid-2008.             
Results from the mining of Buffelsfontein No. 2 Dam to date have confirmed      
the mineral resource estimates for gold and uranium, as well as the estimated   
sulphur content. Minor modifications to the hydraulic mining system to          
improve throughput and to the carbon-in-leach ("CIL") plant flow sheet to       
improve recovery are being implemented and are expected to be completed in      
July 2008; after which the commissioning of the first phase of the transition   
to the Buffelsfontein complex of dams should be complete. These modifications   
include:                                                                        
-    installation of a slime re-pulping system to break up clay lumps and       
    improve hydraulic mining rates to 1.9 million tonnes per quarter and to     
stabilize pulp densities pumped to the plant                                
-    completion of the current work to re-route flotation tailings from the     
    tailings disposal line to the CIL gold circuit to reduce float tails        
    grades and increase overall gold recovery rates to expected levels          
-    installation of high shear oxygen reactors to improve gold recovery        
    grades to 0.19 grams per tonne in the expanded CIL circuit                  
MWS Quarterly Production Results                                                
                                Q3 2008      Q4 2008                            
Tonnes processed                 832, 208     1, 592, 242                       
Grade of gold recovered          0.27         0.14                              
(grams/tonne)                                                                   
Gold recovered (kilograms)       229          219                               
Gold recovered (ounces)          7,357        7,030                             
Construction                                                                    
Sourcing of the additional power plant required to commission the Phase 1B      
expansion (which includes a 7.8 MTPA uranium and pyrite flotation plant, a      
7.8 MTPA gold plant and a 1.5 MTPA uranium plant) has progressed according to   
schedule.  Construction of the Phase 1B complex is progressing according to     
budget and is on schedule to commence commissioning in December 2008.           
Ezulwini Mine                                                                   
Upper Elsburg ("UE") and Shaft Re-engineering Project                           
The Company has completed the installation of the safety support systems to     
prevent future impact on the main shaft from possible ground movement within    
the weak Western Areas Formation ("WAF") where it intersects the shaft.         
Additional support installation above and below this area is 85% complete.      
Support through the WAF zone in the ventilation shaft is 66% complete and       
support above and below the WAF zone in the ventilation shaft is 60%            
complete.                                                                       
While development work on the UE reef horizon (gold) which is being             
undertaken to provide access to the shaft de-stress cut in order to relieve     
possible future pressure on the main shaft is behind schedule (about 74%        
complete), the delay is not expected to impact the operation`s production       
profile as the opening up of previously un-mined portions of the UE ore body    
outside of the shaft pillar area is ahead of schedule.                          
The ore loading system at the shaft bottom has been replaced and now exceeds    
current mining requirements. The final commissioning of the new hanging tower   
steel work in the main shaft is expected to be completed by March 2009.  This   
new system will allow for a long-life low-maintenance shaft system.  Once the   
shaft is de-stressed, mining in the shaft de-stress cut area is expected to     
continue for a further six years.                                               
Results from development sampling, stope sampling and run of mine belt          
sampling continue to provide positive reconciliations to the gold grades        
estimated in the current UE mineral resource block model.                       
Surface stockpiling of production from the UE development and stoping           
operations has commenced.                                                       
Middle Elsburg ("ME") Project                                                   
As disclosed in the Company`s news release dated February 13, 2008, mining in   
the ME uranium and gold section of the Ezulwini Mine was curtailed during the   
quarter due to the power shortage situation. Production has since recommenced   
as has hoisting and stockpiling of uranium and gold bearing ore on surface.     
The opening up, sampling and preparation of new stopes has resulted in          
sufficient mining areas being available to meet start up production             
requirements. It is anticipated that commercial production rates from the ME    
uranium and gold ore-body will be achieved during the year ending March 2009,   
as scheduled.                                                                   
Results from development sampling, stope sampling and run of mine belt          
sampling continue to provide positive reconciliations to the gold and uranium   
grades estimated in the current ME mineral resource block model.                
Ezulwini Quarterly Production Results                                           
                                Q3           Q4                                 
Gold tonnes toll-treated         27,951       18,669                            
Grade of gold recovered          5.6          4.5                               
(grams/tonne)                                                                   
Gold recovered (kilograms)       157          84                                
Gold recovered (ounces)          5,055        2,695                             
Ezulwini Surface Stockpile Status (as at May 16, 2006)                          
                               Gold grade      U3O8 grade                       
Source             Tonnes       (grams/tonne)*  grams/tonne*                    
Clean up and       127,500      1.1             -                               
development                                                                     
Upper Elsburg      4, 338       4.7             -                               
stopes                                                                          
Middle Elsburg     2,501        3.6             800                             
stopes                                                                          
*Sampled belt grades                                                            
Gold and Uranium Plant Commissioning                                            
In the event that Eskom experiences difficulties in supplying the additional    
power that it agreed to do in line with its binding agreement with Ezulwini     
Mining Company, the Company has installed the switchgear necessary to utilize   
the existing standby diesel generators at site should they be required to       
start up the new plant.   Commissioning of the 2.4 MTPA gold plant commenced    
on schedule and on budget during April 2008. The first 0.6 MTPA milling unit    
is currently being commissioned and it is anticipated that first gold will be   
loaded onto carbon during June with gold bullion produced in July 2008. The     
commissioning of the second 0.6 MTPA mill is scheduled for September 2008 at    
which point milling capacity will be utilized to consume existing stockpiles    
while mining rates ramp up as per plan. The civil engineering work required     
for the final two mills is complete and installation and the start of the       
commissioning of these mills are on schedule for February 2009.                 
The construction of the 1.2 MTPA uranium plant is on budget and on schedule     
for commissioning to commence during June of 2008.  The first ADU shipments     
are anticipated to be ready for dispatch during August 2008.                    
Mineral Resource Update                                                         
The verification of historic sampling data, the gathering of new sampling       
results and the addition of new properties is expected to result in a           
significant increase in the amount of verified data available to perform an     
update of the previous mineral resource estimate. In addition, results from     
new surface and underground drilling continue to be added to the geological     
data base. It is anticipated that a revised mineral resource estimate and       
updated technical report will be completed early in the Company`s fiscal        
second quarter (July - September).                                              
Sulphuric Acid Plant                                                            
As disclosed on April 21, 2008, the Company is proceeding with plans to         
construct its own sulphuric acid manufacturing plant, which will utilize the    
Company`s significant stores of sulphur bearing pyrite to secure a long-life    
low-cost source of supply of sulphuric acid.  A preliminary Company             
assessment has been completed and it is anticipated that the detailed           
specification and procurement study for a standard 600 tonne per day            
sulphuric acid plant will be completed by the end of July 2008. The Company     
anticipates that the environmental impact assessment process necessary to       
secure an operating license for the acid plant will be concluded by July 2009   
and has engaged the services of reputable consulting firms who are well         
experienced in the design, permitting and construction of pyrite burning acid   
plants in Southern Africa.  First Uranium is evaluating options for financing   
the acid business as a stand alone entity and discussions are underway.         
"Our near-term objectives are to expand our gold production, commission our     
uranium plants and generate cash," said Gordon Miller, President and Chief      
Executive Officer of First Uranium.  "Our long-term objective is to become      
one of the world`s lowest cost uranium producers and we have met or exceeded    
almost all of our target dates for project milestones along the way and, most   
importantly, we have started to commission our plants on schedule.   We have    
also taken significant risk out of our projects by re-engineering the shaft     
at Ezulwini, acquiring generators to meet our power requirements and made       
plans to build an acid plant to provide a low-cost secure supply of sulphuric   
acid."                                                                          
Technical Disclosure                                                            
Technical disclosure in this news release relating to the tonnage of the        
stockpiles has been prepared by Warren de Witt, who is a "qualified person"     
under NI 43-101 and is independent of First Uranium.  Mr. de Witt has           
reviewed and approved the disclosure in this news release.                      
Cautionary Language Regarding Forward-Looking Information                       
This news release contains certain forward-looking statements.  Forward-        
looking statements include but are not limited to those with respect to the     
availability of electrical power, the planned addition of owner-operated        
power generation, price of electrical power and sulphuric acid, the             
estimation of mineral resources and reserves, the realization of estimated      
pyrite content in the MWS tailings dams, the timing and amount of estimated     
future production, costs of production, capital expenditures, costs and         
timing of development of new deposits, success of exploration activities,       
permitting time lines, currency fluctuations, requirements for additional       
capital, availability of financing on acceptable terms, government regulation   
of mining operations, environmental risks, unanticipated reclamation            
expenses, title disputes or claims and limitations on insurance coverage and    
the timing and possible outcome of pending litigation.  In certain cases,       
forward-looking statements can be identified by the use of words such as        
"goal", "objective", "plans", "expects" or "does not expect", "is expected",    
"projected", "assumed", "budget", "scheduled", "estimates", "forecasts",        
"intends", "anticipates", or "does not anticipate", or "believes" or            
variations of such words and phrases, or state that certain actions, events     
or results "may", "could", "would", "should", "might" or "will" be taken,       
occur or be achieved.  Forward-looking statements involve known and unknown     
risks, uncertainties and other factors which may cause the actual results,      
performance or achievements of First Uranium to be materially different from    
any future results, performance or achievement expressed or implied by the      
forward-looking statements.  Such risks and uncertainties include, among        
others, the actual results of current exploration activities, conclusions of    
economic evaluations, changes in project parameters as plans continue to be     
refined, availability of equipment, materials and fuel, possible variations     
in grade and ore densities or recovery rates, failure of plant, equipment or    
processes to operate as anticipated, accidents, labour disputes or other        
risks of the mining industry, delays in obtaining government approvals or       
financing or in completion of development or construction activities, risks     
relating to the integration of acquisitions, to international operations, to    
prices of uranium and gold, to price of electrical power and sulphuric acid.    
Although First Uranium has attempted to identify important factors that could   
cause actual actions, events or results to differ materially from those         
described in forward-looking statements, there may be other factors that        
cause actions, events or results not to be as anticipated, estimated or         
intended.  It is important to note, that: (i) unless otherwise indicated,       
forward-looking statements indicate the Company`s expectations as of the date   
of this news release; (ii) actual results may differ materially from the        
Company`s expectations if known and unknown risks or uncertainties affect its   
business, or if estimates or assumptions prove inaccurate; (iii) the Company    
cannot guarantee that any forward-looking statement will materialize and,       
accordingly, readers are cautioned not to place undue reliance on these         
forward-looking statements; and (iv) the Company disclaims any intention and    
assumes no obligation to update or revise any forward-looking statement even    
if new information becomes available, as a result of future events or for any   
other reason.                                                                   
In making the forward-looking statements in this news release, First Uranium    
has made several material assumptions, including but not limited to, the        
assumption that: (i) consistent supply of sufficient power will be available    
to develop and operate the projects as planned; (ii) approvals to transfer or   
grant, as the case may be, mining rights will be obtained; (iii) metal          
prices, exchange rates and discount rates applied in the preliminary economic   
assessments are achieved; (iv) mineral resource estimates are accurate; (v)     
the technology used to develop and operate its two projects has, for the most   
part, been proven and will work effectively; (vi) that labour and materials     
will be sufficiently plentiful as to not impede the projects or add             
significantly to the estimated cash costs of operations; (vii) that Black       
Economic Empowerment ("BEE") investors will maintain their interest in the      
Company and their investment in the Company`s common shares to a sufficient     
level to continue to support the Company`s compliance with 2014 BEE             
requirements; and (viii) that the innovative work on stabilizing the main       
shaft at the Ezulwini Mine will be successful in maintaining a safe and         
uninterrupted working environment until 2024.                                   
About First Uranium Corporation                                                 
First Uranium Corporation (TSX:FIU, JSE:FUM) is focused on the development of   
its South African uranium and gold mines with the goal of becoming a            
significant producer through the re-opening and underground development of      
the Ezulwini Mine and the expansion of the Mine Waste Solutions tailings        
recovery facility.  First Uranium also plans to grow production by pursuing     
value-enhancing acquisition and joint venture opportunities in South Africa     
and elsewhere.                                                                  
First Uranium Corporation                                                       
1240-155 University Avenue, Toronto, ON Canada  M5H 3B7                         
www.firsturanium.com                                                            
For further information, please contact:                                        
Bob Tait, VP Investor Relations                                                 
at 416 342-5639 (office), 416 558-3858 (mobile) or bob@firsturanium.ca          
Date: 21/05/2008 07:52:46 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: