Not logged in
  Home   Markets   Shares   Funds   Portfolio   Toolbox   Charting   Alerts   Directory   
 Admin   

Mon 17 Nov 2008, 9:55 CZA - Coal of Africa Limited - Update On Mooiplaats Coal Project
CZA
CZA                                                                             
CZA - Coal of Africa Limited - Update On Mooiplaats Coal Project                
Coal of Africa Limited                                                          
(previously, "GVM Metals Limited")                                              
(Incorporated and registered in Australia)                                      
(Registration number ABN 008 905 388)                                           
Share code on the JSE Limited: CZA                                              
ISIN: AU000000CZA6                                                              
Share code on the Australian Stock Exchange Limited: CZA                        
ISIN: AU000000CZA6                                                              
(`CoAL` or `the Company`)                                                       
17 November 2008                                                                
UPDATE ON MOOIPLAATS COAL PROJECT                                               
Coal of Africa Limited ("CoAL" or "the Company") is pleased to provide the      
following update on progress of production at its Mooiplaats thermal coal       
project in South Africa:                                                        
Mining                                                                          
Blasting of the access ramp floor has been completed, and concreting is in      
progress. Boxcut walls are being supported and the first continuous miner is    
expected to commence cutting of the underground coal portals during the latter  
half of November 2008, at which time the Company also expects to take delivery  
of its second continuous miner.                                                 
Coal Processing Plant and Infrastructure                                        
Rain has caused some delays in civil work, however this is not expected to have 
a major impact on the construction schedule. Processing structures are expected 
to be erected on site during Q1 2009, with commissioning by March 2009 and first
sales to take place by the end of H1 2009. Water allocation for the project is  
currently being reviewed by the Department of Water Affairs and Forestry (DWAF),
together with Eskom.  Power generating sets, transformers and substations have  
been delivered, as well as several conveyor drive components. Surface           
infrastructure is under construction and is expected to be completed by the end 
of Q1 2009.                                                                     
Logistics                                                                       
Road construction is progressing well and is anticipated to be completed by the 
end of January 2009.                                                            
Successful discussions were held with a local coal producer to obtain interim   
access to rail loading facilities, together with the proposed processing of a   
2,000 tonne bulk sample of coal from the first underground production to assess 
lean coal qualities for marketing purposes.                                     
Negotiations with Transnet Freight Rail are close to completion and the Company 
remains confident that it will secure adequate rail allocation to match the     
already secured port capacity at the dry bulk terminal at Richards Bay.         
Managing Director, Simon Farrell commenting on the Mooiplaats progress said, "I 
am pleased to report continued progress at the Mooiplaats coal project, largely 
in line with scheduled timing. Cutting of the underground coal portals will     
commence shortly, and the second continuous miner is scheduled for handover on  
24th November.                                                                  
These developments leave us on track for commissioning by March 2009 and first  
sales to take place by the end of H1 2009."                                     
AUTHORISED BY                                                                   
Simon Farrell                                                                   
Managing Director                                                               
For more information contact:                                                   
Simon Farrell, Managing Director                                                
Coal of Africa                                                                  
+61 417 985 383 or +61 8 9322 6776                                              
Petronella Gorrie                                                               
The Event Shop                                                                  
+27 82 827 8815                                                                 
Jos Simson / Gareth Tredway                                                     
Conduit PR                                                                      
+44(0) 20 7429 6603                                                             
Olly Cairns / Romil Patel                                                       
Blue Oar Securities Plc                                                         
+61 8 6430 1631/ +44(0) 20 7448 4400                                            
About Mooiplaats:                                                               
The Mooiplaats coal project is a series of adjacent `farms` comprising roughly  
16,000ha adjacent  to the Camden power station in the Mpumalanga province in    
South Africa.   The first two continuous miners are expected to be cutting coal 
by the end of the 2008. Following ramp up, a total of seven continuous miners   
are expected to produce 3.5 to 4 million ROM tonnes per year by mid 2010.       
The Company has secured long term port allocation for the export of coal mined  
at Mooiplaats through the Richards Bay dry bulk terminal operated by Grindrod.  
The throughput agreement provides CoAL with an allocation of 900,000 tonnes of  
coal per annum commencing in 2009 and the potential to increase its export      
capacity to 3 million tonnes per annum once the terminal expansion has been     
completed.                                                                      
About CoAL:                                                                     
Coal of Africa Limited ("CoAL" or "the Company"), is primarily focused on the   
acquisition, exploration and development of metallurgical and thermal coal      
projects.  CoAL`s key projects, along with its leading metals processing company
NiMag Group (Pty) Ltd are in South Africa.  The Company was incorporated in     
Western Australia and listed in 1980.  Since 2005, CoAL has also listed on both 
the AIM and JSE markets, allowing further growth in the Company`s coal assets.  
www.coalofafrica.com                                                            
Sponsor                                                                         
PricewaterhouseCoopers Corporate Finance (Pty) Ltd                              
Date: 17/11/2008 09:55:01 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: