Tue 10 Feb 2009, 15:30 GBG - Great Basin Gold - Burnstone Gold Project: Number 1 Vertical Shaft
GBG
GBG                                                                             
GBG - Great Basin Gold - Burnstone Gold Project: Number 1 Vertical Shaft        
                        Enters Phase 2 Of Development Financial Forecast Update 
GREAT BASIN GOLD LIMITED                                                        
(INCORPORATED IN CANADA AND REGISTERED AS AN EXTERNAL COMPANY IN SOUTH AFRICA)  
(REGISTRATION NO. 2006/021304/10)                                               
SHARE CODE: GBG      ISIN NUMBER: CA3901241057                                  
("Great Basin Gold" or the "Company")                                           
BURNSTONE GOLD PROJECT:                                                         
NUMBER 1 VERTICAL SHAFT ENTERS PHASE 2 OF DEVELOPMENT                           
FINANCIAL FORECAST UPDATE                                                       
February 10, 2009, Vancouver, BC - Great Basin Gold Ltd, ("Great Basin" or the  
"Company"), (TSX: GBG; NYSE Alternext: GBG; JSE: GBG) announces the successful  
erection of the permanent headgear at the Number 1 Vertical Shaft of its        
Burnstone Project in the Mpumalanga Province, 80 kilometers from Johannesburg,  
South Africa.                                                                   
The Company`s plan for the Burnstone Project is to access the gold-bearing      
Kimberley Reef primarily by means of a decline while extraction of ore and waste
will occur via a shallow vertical shaft.  Great Basin has undertaken the decline
shaft using employees instead of contractors. The design, sinking, equipping and
commissioning of the Vertical Shaft was contracted to Grinaker - LTA Mining, a  
business unit of Aveng (Africa) Ltd.  Site preparation for the vertical shaft   
started in January 2008, and sinking commenced in April 2008.                   
The 7.5-meter diameter Vertical Shaft is planned to be sunk to a final depth of 
501 meters, and is designed to allow for the extraction of 125,000 tonnes of ore
and 55,000 tonnes of waste per month. It will also be equipped for the          
transportation of personnel and material.  Under the mine plan, an additional   
50,000 tons of ore per month will be mined later via a second decline accessing 
Area 2.                                                                         
The initial, pre-sink phase was completed by the end of 2008, having reached a  
depth of 164 meters below surface.  Preparations for the next main sink phase,  
which is to take place at a faster rate of excavation, are now underway and     
nearing completion. As part of these preparations, the permanent headgear was   
erected, allowing for three temporary sinking winders to be installed.  The     
winder installations have been completed and two of the three winders were      
licensed to operate as of January 7, 2009.  The third Kibble winder will be     
licensed by end of February 2009.  These winders will be replaced by a permanent
winder arrangement near to the time of the completion of the project.           
Erecting the 45-meter high pre-assembled headgear was a complex process,        
requiring detailed planning and precision in execution.  The erection process   
commenced on Saturday, January 17 and was completed on Monday, January 19, 2009 
when the raker legs were installed.                                             
Good progress has been made underground with drifts to access mining blocks B   
and C, which are currently under development.  The decline shaft has also       
progressed to within 35 meters of intersection with the Kimberley Reef.  Mining 
from the decline and Block B is planned to commence in the March 2009 quarter   
and access to Block C is scheduled in the June 2009 quarter.                    
The Metallurgical Plant design is in its final stages and will be completed by  
end February 2009.  Some used equipment has been purchased for the Burnstone    
facility.  The mills have been subjected to non-destructive testing to determine
the level of refurbishment required.  The Metallurgical Plant commissioning is  
on track for completion by mid 2010.                                            
The 2007 Optimised Feasibility Study (see Great Basin News Release dated July 5,
2007) has been updated by Great Basin`s in-house engineering and financial team 
("2009 Update") based on mineral resources announced in 2008 (see Great Basin   
News Release dated February 19, 2008) and mine planning by Turgis Engineering.  
A number of the project plans remain as in the 2007 Optimised Feasibility, with 
other key parameters described below.  A technical report currently being       
finalized is expected to be filed on www.sedar.com during February 2009.        
-2-                                                                             
The continued exploration has resulted in a 15% increase in proven and probable 
mineral reserves to 30 million tonnes grading 4.2 g/t at a 4 g/t gold cut-off1, 
and increasing the planned number of ounces to be mined from 3.5 million to 4.1 
million ounces over a mine life of 15 years. Capital expenditure estimates have 
been updated to reflect the change in mine plan.                                
During 2008, the Company spent US$37 million (ZAR337 million) to develop the    
mine and related infrastructure, bringing the total expenditure on the Burnstone
Project to US$54 million (ZAR490 million). The remaining required capital       
necessary to bring the mine into commercial production is estimated at US$124   
million (ZAR1.1 billion).                                                       
Cash costs for mining and processing are estimated at US$303 per ounce          
(ZAR88,000 p/Kg). At a long term gold price of US$750/oz, the Project has an    
Internal Rate of Return (IRR) of 33% and an after-tax Net Present Value (NPV) of
US$612 million using a 5% discount rate. Using the current gold price of        
US$900/oz and R9.00 to the US Dollar, the analysis indicates an IRR of 43% and  
an after-tax NPV of US$879 million.                                             
The Company is in the process of negotiating a project funding facility with a  
syndicate of South African Banks and is optimistic that the negotiations will be
successfully concluded this month, subject to execution of final documentation. 
Ferdi Dippenaar, President and CEO, commented: "Erecting the permanent headgear 
and installing the associated infrastructure are important and significant      
milestones as we will be able to continue with the fast sink, lining and        
equipping of this shallow 501-meter vertical shaft.  Despite intersecting water 
on 164 Level as well as in the barrel during the pre-sinking, the team managed  
to gain approximately 4 weeks on the scheduled sinking program.  Good progress  
is also being made with underground infrastructure development with multiple    
access points to the deposit, which should see Burnstone producing approximately
40,000 oz over the next year."                                                  
Johan Oelofse, PrEng, FSAIMM, Chief Operating Officer for Great Basin is a      
qualified person He supervised the 2009 Update and has reviewed this news       
release.                                                                        
For additional details on Great Basin Gold Ltd. and its gold properties, please 
visit the Company`s website at www.grtbasin.com or contact Investor Services:   
Tsholo Serunye in South Africa                    +27 (0)11 301 1800            
Michael Curlook in North America                  +1 888 633 9332               
Barbara Cano at Breakstone Group in the USA       +1 646 452-2334               
Ferdi Dippenaar                                                                 
President and CEO                                                               
1 The mineral reserves are comprised of 27.6 million tonnes grading 4.27 g/t of 
proven reserves and 2.4 million tonnes grading 4.01 g/t of probable reserves.   
No regulatory authority has approved or disapproved the information contained in
this news release.                                                              
Cautionary and Forward Looking Statement Information                            
This release includes certain statements that may be deemed "forward-looking    
statements". All statements in this release, other than statements of historical
facts, that address possible future commercial production, bank loan            
arrangements, reserve potential, exploration drilling results, development,     
feasibility or exploitation activities and events or developments that Great    
Basin Gold expects to occur are forward-looking statements. Although the Company
believes the expectations expressed in such forward-looking statements are based
on reasonable assumptions, such statements are not guarantees of future         
performance and actual results or developments may differ materially from those 
in the forward-looking statements. Factors that could cause actual results to   
differ materially from those in forward-looking statements include market prices
for precious metals, credit availability, development and exploration successes,
continuity of mineralization, uncertainties related  to the ability to obtain   
necessary permits, licenses and title and delays due to third party opposition, 
geopolitical uncertainty, changes in government policies regarding mining and   
natural resource exploration and exploitation, and continued availability of    
capital and financing, and general economic, market or business conditions.     
Investors are cautioned that any such statements are not guarantees of future   
performance and those actual results or developments may differ materially from 
those projected in the forward-looking statements. For more information on the  
Company, Investors should review the Company`s annual Form 40-F filing with the 
United States Securities and Exchange Commission and its Canadian jurisdiction  
filings that are available at www.sedar.com.                                    
-3-                                                                             
All information relating to the contents of the 2009 Update and to the 2007     
Optimised Feasibility Study, including but not limited to statements of the     
Burnstone project`s potential and information such as capital and operating     
costs, production summary, and financial analysis are forward looking           
statements.  The 2009 Update was prepared to quantify the Burnstone project`s   
capital and operating cost parameters and to determine the project`s likelihood 
of feasibility and optimal production rate. The capital and operating cost      
estimates which were used have been developed based on detailed capital cost to 
production level relationships.                                                 
The following are the principal risk factors and uncertainties which, in        
management`s opinion, are likely to most directly affect the ultimate           
feasibility of the Burnstone project. The mineralized material at the Burnstone 
project is currently classified as a measured and indicated resource, and a     
portion of it qualifies under Canadian mining disclosure standards as a proven  
and probable reserve, but readers are cautioned that no part of the Burnstone   
project`s mineralization is not yet considered to be a reserve under US mining  
standards as all necessary mining permits and project financing would be        
required in order to classify the project`s mineralized material as an          
economically exploitable reserve.  Although work has been done to confirm the   
mine design, mining methods and processing methods assumed in the 2009 Update,  
construction and operation of the mine and processing facilities depend on      
securing environmental and other permits on a timely basis.                     
Authorization has been received for mining. Additional permits, when required,  
have yet to be applied for and there can be no assurance that required permits  
can be secured or secured on a timely basis. Although costs, including design,  
procurement, construction and on-going operating costs and metal recoveries have
been established at a level of detail required for a feasibility study, these   
could be materially different from those contained in the 2009 Update.  There   
can be no assurance that these infrastructure facilities can be developed on a  
timely and cost-effective basis.  Energy risks include the potential for        
significant increases in the cost of fuel and electricity.  The 2009 Update     
assumes specified, long-term prices levels for gold.  The price of this metal is
historically volatile, and the Company has no control of or influence on its    
price which is determined in international markets.  There can be no assurance  
that the price of gold will continue at current levels or that it will not      
decline below the prices assumed in the 2009 Update.                            
Prices for gold have been below the price ranges assumed in 2009 Update at times
during the past ten years, and for extended periods of time.  The project will  
require additional financing.  Although interest rates are at historically low  
levels, there can be no assurance that debt and/or equity financing will be     
available on acceptable terms.  Other general risks include those ordinary to   
very large construction projects, including the general uncertainties inherent  
in engineering and construction cost, the need to comply with generally         
increasing environmental obligations, and accommodation of local and community  
concerns. South African mining tenure laws require that significant economic    
ownership in Burnstone be held by historically disadvantaged South Africans     
(HDSAs) and for which ownership rights the Company may not be significantly     
compensated. The Company has an agreement with Tranter Gold (Pty) Ltd which     
represents the required interest by HDSA.  The economics of the Burnstone       
Project are sensitive to the US Dollar and South African Rand exchange rate and 
this rate has been subject to large fluctuations in the last several years.     
Date: 10/02/2009 15:30:02 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: