Not logged in
  Home   Markets   Shares   Funds   Portfolio   Toolbox   Charting   Alerts   Directory   
 Admin   

Thu 8 Oct 2009, 7:05 NHM - Northam Platinum Limited - Northam concludes Booysendal feasibility study
NHM
NHM                                                                             
NHM - Northam Platinum Limited - Northam concludes Booysendal feasibility study 
NORTHAM PLATINUM LIMITED                                                        
(Incorporated in the Republic of South Africa)                                  
(Registration number 1977/003282/06)                                            
Share code: NHM    ISIN: ZAE000030912                                           
("Northam")                                                                     
Northam concludes Booysendal feasibility study                                  
Johannesburg, 8 October 2009                                                    
Key features                                                                    
*    Modular approach confirmed                                                 
*    Tonnages:                                                                  
*    Module 1 - 120 000 tonnes milled per month                             
    *    Module 2 - 120 000 tonnes milled per month                             
*    Production and sales volumes:                                              
    *    Module 1 - 130 000 (3PGM+Au) per month                                 
*    Module 2 - 115 000 (3PGM+Au) per month                                 
*    Financing decision to follow on the completion of value engineering process
*    Northam Board approval and construction of mine expected in early 2010     
*    First module capex - R3 billion (2009 terms)                               
*    Combination of steady state Zondereinde mine and significant greenfields   
    growth at Booysendal provides compelling PGM investment opportunity         
Northam Platinum Limited is pleased to report that the Booysendal feasibility   
study report is complete and is in the process of being compiled, while a review
of the design and layout is under way.  Final board approval for the project is 
expected early in calendar year 2010.                                           
Northam`s acquisition of the Booysendal project became effective in August 2008,
with work on the feasibility study having begun in June 2008.  Booysendal is    
located on the eastern limb of the Bushveld Complex, near the town of Lydenburg.
Commenting on the results of the study, Northam CEO Glyn Lewis said today, "The 
feasibility study has confirmed our approach to the project. Booysendal is      
living up to our expectations and is likely to be a significant, long-life      
producer, and one of the new-generation PGM mining projects of the future.      
"The mining plan confirms that a modular approach, initially focussing on the   
UG2 reef, should be implemented. The plan is to mine at a rate of 150 000 tonnes
per month and upgrade this production through a Dense Media Separation ("DMS")  
plant to produce a concentrator feed of 120 000 tonnes per month. The second    
module will have a similar production profile when it is brought into operation,
resulting in a total concentrator fed of 240 000 tonnes milled per month. For   
module 1, at full capacity, in mid 2009 money terms, the average operating cost 
is expected to be R410 per tonne mined.                                         
"These operating parameters are expected to give rise to sales of some 130 000  
ounces (3PGM+Au - platinum palladium, rhodium, gold) per annum on completion of 
module 1, rising by a further 115 000 ounces (3PGM+Au) per annum, to a total of 
245 000 ounces (3PGM+Au) for both modules.                                      
"The capital cost for module 1 is expected to be R3.0 billion (in 2009 terms)   
over a five-year period with similar capital expenditure anticipated for module 
2.  Our intention remains to fund the project through a combination of a rights 
issue, internal retentions and medium-term bank debt."                          
Northam will begin the construction of an access road and water pipeline and    
start the boxcut for the module 1 on-reef decline in the first half of 2010.    
First concentrate from module 1 is anticipated in 2013, reaching full production
in 2015.  Module 1`s life-of-mine is expected to exceed 20 years, during which  
period further production expansions would be developed.                        
The national power utility, Eskom, has undertaken a feasibility study for an    
80MVa substation to be situated on the Booysendal property.  Eskom is currently 
also in the process of conducting the Environmental Impact Assessment (EIA)     
study for the transmission lines from the nearby Steenberg sub-station.  The    
application for the first 20MVa has been submitted and a budget quote is        
awaited.  Our critical path analysis has identified the supply of electricity as
a key factor.                                                                   
The conversion of Booysendal`s old order mining right to a new order mining     
right over nine of the 11 farms was executed on 10 September 2009. The          
application for new order mining rights on the remaining two farms and the      
transfer of the Der Brochen extension is in progress.                           
The scale of Booysendal, together with the accessibility of the reef horizon    
from surface, provides the project with significant inherent flexibility and    
growth potential.  Further expansions of the mine (such as increasing the UG2   
mining rate, or exploitation of the Merensky reef) will be the subject of a     
further feasibility study.                                                      
Further updates will be provided to the market in due course.                   
Key features: Booysendal feasibility study                                      
Key features of the Booysendal project arising from the feasibility study are:  
Modular approach                                                                
    *    The UG2 reef will be optimally mined by developing on a modular basis. 
         Each module aims to produce 150 000 run-of-mine (RoM) tonnes per       
month. The North Shaft complex, comprising four declines (three on     
         reef and one in the footwall) makes up module 1, with a similar        
         decline configuration considered for the South Shaft or module.        
    *    In order to minimize the environmental impact, a reverse decline       
system (which has a smaller total footprint than a conventional adit)  
         will be used to access the primary decline cluster to allow for the    
         efficient transport of ore, men, material and machinery and access to  
         the Merensky reef horizon.                                             
*    Depending on prevailing economic circumstances and power availability, 
         construction of the second module should begin in 2013.                
Access to the reef                                                              
    *    A modified room and pillar mining method will be employed to extract   
the UG2 reef, which will be transported to surface via a footwall      
         conveyor system connected to the reverse declines. This will allow for 
         maximum flexibility in the mine design and easy future access to the   
         Merensky reef horizon.                                                 
Throughput                                                                      
    *    Each module will produce approximately 150 000 tonnes per month of RoM 
         ore with a DMS circuit to be used to remove 30 000 tonnes per month of 
         low grade/waste material so as to improve the grade of ore delivered   
to the UG2 concentrator plant.                                         
Anticipated costs                                                               
    *    The average operating cost for North Shaft is expected to be R410 per  
         tonne mined. There may be a marginal increase in operating cost once   
the second module is producing, principally as a result of logistical  
         costs arising from the need for a surface cable ropeway conveyor from  
         the second module to an expanded metallurgical facility, and the       
         marginally lower grade UG2 that is anticipated at South Shaft.         
Environmental permitting                                                        
    *    Environmental permitting for the first on-reef decline has been        
         approved. The Environmental Management Plan (EMP) amendment for the    
         reverse declines and plant infrastructure is currently underway.       
Approval is expected in the first half of 2010. Extensive              
         environmental surveys and studies have been undertaken so as to        
         minimise both the footprint of the mine, and its impact on the         
         environment.                                                           
Timing and production build-up                                                  
    *    The construction of North Shaft is planned to begin in the second half 
         of 2010, with the first PGM concentrate being produced in 2013, after  
         commissioning of the processing plant.                                 
*    Construction of the South Shaft should begin in 2013, with the first   
         PGM ounces being produced in 2016.                                     
Capital costs                                                                   
    *    The project capital cost for module 1 is estimated at R2.97 billion    
(in 2009 terms). The project capital cost at module 2 is estimated to  
         be similar (in 2009 terms).                                            
Smelting                                                                        
*    Given the proposed implementation at Booysendal of Northam`s successful    
vertical sparger technology in the UG2 concentrator circuit, it is          
    anticipated that the current smelter capacity at Northam`s Zondereinde mine 
    will be adequate for the treatment of module 1 UG2 concentrate.             
*    Accommodating concentrates from module 2 would require an upgrade of       
smelter capacity and extensions to the crystallizing and electro-winning    
    circuits.                                                                   
Power supply                                                                    
*    Eskom has completed the feasibility study for an 80 MVa substation to be   
situated at Booysendal and is doing the EIA study for the transmission      
    lines from Steenberg. Northam has submitted an application for the first    
    20 MVa and Eskom is in the process of preparing the budget quote. Critical  
    path analysis has identified electricity as a key factor and significant    
attention is being paid to this aspect. The spare capacity at Mototolo      
    (which, by agreement, is available to Northam) is adequate for the          
    construction of the necessary mining infrastructure.                        
About Northam and Booysendal                                                    
Northam Platinum Limited (Northam) is the only fully independent, black-owned   
and controlled integrated PGM producer listed on the JSE Limited (JSE). The     
company wholly owns and operates the cash-generative Zondereinde platinum mine  
and metallurgical complex on the upper end of the western limb of the South     
African Bushveld Complex near the town of Thabazimbi.                           
Northam is planning to develop its wholly-owned 103 million ounce (3PGM+Au)     
Booysendal project, which is located near Lydenburg on the eastern limb of the  
Bushveld Complex. In addition, the company holds a 7.5% interest in the Pandora 
joint venture, a PGM mining operation on the western limb of the Bushveld       
Complex, near Brits, in partnership with Anglo Platinum, the Bapo Ba Mogale     
community and Lonmin.                                                           
The company has a combined resource base of 130 million ounces (3PGE+Au)        
(including 8.1 million ounces (3PGE+Au) in mineral reserve at Northam`s         
Zondereinde mine). The progressive development of Booysendal will add some 245  
000 ounces (3PGM+Au) to the company`s existing annual output of some 300 000    
ounces (3PGM+Au) with more than 50 years life-of-mine. As an independent, fully 
integrated PGM producer, Northam has full control over the entire PGM           
beneficiation stream of its metals from mine to market.                         
Northam wishes to confirm that the information contained in this announcement   
was reviewed by an internal expert employed by Northam, Mr F R Rautenbach       
(NDT - metalliferous mining), prior to release.                                 
Distributed by:                                                                 
Russell & Associates, Johannesburg                                              
Tel: +27 (0)11 880 3924                                                         
Fax: +27 (0)11 880 3788                                                         
Northam will be hosting a presentation of the feasibility study results.        
Details as follows:                                                             
*    Date and time: Thursday 8 October 2009 at 11:30                            
*    Venue: Glenhove Conference Centre, 52 Glenhove Road, Melrose Estate.       
*    Details of webcast and audio facilities will be published on the company`s 
    website at www.northam.co.za                                                
Sponsor                                                                         
BJM Corporate Finance (Proprietary) Limited                                     
Date: 08/10/2009 07:05:02 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: