Thu 29 Oct 2009, 16:31 FSE - Firestone Energy Limited - Firestone Energy Limited - Sept 2009 Quarterly
FSE
FSE                                                                             
FSE - Firestone Energy Limited - Firestone Energy Limited - Sept 2009 Quarterly 
Activities Report                                                               
FIRESTONE ENERGY LIMITED                                                        
(formerly Centralian Minerals Limited)                                          
(Registration number: ABN 058 436 794)                                          
(SA company registration number: 200/023973/10                                  
Share code on the JSE: FSE                                                      
Share code on the ASX: FSE                                                      
ISIN: AU000000FSE6                                                              
("FSE" or "the Company")                                                        
Firestone Energy Limited - Sept 2009 Quarterly Activities Report                
About Firestone Energy:                                                         
Firestone Energy is an independent Australian exploration company focused on    
developing coal projects in South Africa. The company is currently exploring the
richly endowed Waterberg coal field in the Limpopo Province of South Africa.    
The Company is committed to value-added growth through becoming an independent  
coal and energy producer at its projects in South Africa.                       
The Company has entered into two joint ventures with Sekoko Resources, a South  
African black empowerment company (BEE) and Sekoko has two directors on the     
Board of Firestone Energy.                                                      
Corporate Details:                                                              
ASX: FSE                                                                        
JSE: FSE                                                                        
Issued Capital:                                                                 
2,331 million ordinary shares                                                   
Major Shareholders:                                                             
Sekoko Resources (Pty) Ltd                                                      
Colbern Fiduciary Nominees Ltd                                                  
Bell Potter Nominees Ltd                                                        
Directors and Officers:                                                         
Non Executive Directors                                                         
John Dreyer (Chairman)                                                          
Timothy Tebeila                                                                 
Amanda Matthee                                                                  
Colin McIntyre                                                                  
Managing Director (wef 1 Nov)                                                   
John Wallington                                                                 
Company Secretary                                                               
Simon Storm                                                                     
Contact:                                                                        
Level 1, 63 Hay Street                                                          
Subiaco, Western Australia 6008                                                 
Tel: +61 (0)8  9381 2755                                                        
Web: www.firestoneenergy.com.au                                                 
Firestone Energy Limited (ASX/JSE: FSE) is pleased to report that during the    
quarter ended September 2009 substantial progress has been made in the          
development of the Waterberg Coal JV project in Lephalale, Limpopo Province,    
South Africa.                                                                   
HIGHLIGHTS FOR THE QUARTER                                                      
A$25m capital raising completed to fund BFS                                     
Second JV underway with a significant increase to coal resource in addition to  
first 2 farms and J/V.                                                          
New Chairman and Managing Director appointed                                    
PFS and new resource calculation near completion                                
Mining Permit for Small Scale mine approved                                     
100% strike rate of Coal in all 122 holes drilled                               
Northern Territory - Australia                                                  
-    The two exploration licenses (ELs 7810 and 10166) near Tennant Creek in the
    Northern Territory which have been managed by Emmerson Resources Ltd, on    
behalf of the Company are to be relinquished.                               
Exploration                                                                     
-    Prior to the establishment of the second joint venture, Firestone Energy`s 
    joint venture partner, Sekoko Coal has drilled 122 bore holes on the six    
farms bringing the total of drilled holes to 163 holes.  All the holes      
    drilled intersected coal and were logged and sampled by suitably qualified  
    geologists. The diameter of the core holes drilled by Sekoko is 86mm. The   
    results from the laboratories have been expedited and an updated resource   
classification will be published within the next quarter.                   
-    The Board has approved a contract for the Infrastructure Engineering and   
    Design for the mine. It is estimated that this will be completed by mid     
    2010.                                                                       
-    Firestone and its JV partner, Sekoko, have made tremendous progress with   
    the pre-feasibility study and all indications are that this will be         
    completed by the end of this calendar year.                                 
Firestone Energy Limited - Sept 2009 Quarterly Activities Report                
Overview                                                                        
While global financial and commodity conditions remained challenging during the 
September 2009 Quarter, Firestone Energy Limited (ASX/JSE: FSE) was active on a 
number of fronts.                                                               
The main focus of activity was completing preparations and compilations of      
various supporting documentation and/or report for the Mining Right Application.
Pre-feasibility Study                                                           
Work is progressing on schedule in most of the areas of the PFS with many       
sections nearing completion. Pre-Feasibility Study approaches completion with   
draft reports being currently reviewed.                                         
Firestone Energy`s joint venture partner, Sekoko Coal has been advised by the   
municipal authorities that these Waterberg new coal projects are highly regarded
as important future contributors to the local economy and are a key part of the 
regional development strategy. This very strong local support from the Lephalale
Local Municipality and the Waterberg District Municipality is expected to assist
in expediting the Permitting issues and the Mining Right Application approval.  
Potential Markets                                                               
Firestone Energy is also looking to capitalise on the current power crisis in   
South Africa. Firestone Energy/Sekoko JV properties are strategically located   
power stations with Exxaro`s Grootegeluk Colliery in close proximity to two of  
Eskom`s coal-fired power stations, Matimba and Medupi (currently under          
construction and expected completion in 2011), may make transportation costs    
from the mine attractive to Eskom.                                              
Corporate                                                                       
During the reporting period, the Company announced that joint venture partner,  
Sekoko Coal Pty Ltd, has been granted mining approval from the South African    
Department of Mining and Energy (DME) to commence an initial small scale mining 
operation from the company`s Waterberg coal project in South Africa. Permits are
also in place to construct a box-cut/small-scale mine and develop a trial open  
cut and underground mining operation. It is planned to commence mining          
operations by beginning of 2010 and will eventually build up to a rate of 60,000
ROM tonnes per month, which after washing would yield approximately 30,000      
tonnes per month of saleable coal.  The small scale mine will be low cost open  
cut mining and mining contractors will be used for the operations. The Company  
continues to work towards securing an off-take sales agreement with South       
African State owned power utility, Eskom.                                       
The Company also received shareholder approval for a milestone transaction      
acquiring a 2.9 billion tonne additional resource. As announced on 3 July 2009, 
the second JV agreement with Sekoko Coal is over four farms - Smitspan 306LQ,   
Hooikraal 315LQ, Minnasvlakte 258LQ, and Massenberg 305LQ - with an estimated   
combined coal resource tonnage of 2.9Bt (1,122.8Bt of saleable coal after       
washing). Under the terms of the Joint Venture Agreement, approved by           
Shareholders, Firestone`s wholly joint venture whereby Lexshell will now earn an
initial 30% interest in the Properties in consideration for:                    
-    the issue to Sekoko of new shares in Firestone in the amount of ZAR293     
    million (approximately A$43.4 million) at an issue price of A$0.05 per      
    share, which amounts to approximately 868,176,563 Firestone shares (as      
    approved by Shareholders today);                                            
-    a reimbursement of expenses to Sekoko of up to ZAR 32.99 million (approx   
    A$5.1 million) which has been spent by Sekoko in the exploration and        
    development of the Properties; and following the approval of the Bankable   
    Feasibility Study ("BFS") and decision to mine by the Management Board of   
the joint venture, a management fee of ZAR50 million (approximately A$7.41  
    million) be paid to Sekoko (or its nominee) over a 7 year period from the   
    date of commercial production.                                              
Firestone has the opportunity to earn a further 30% interest (for a total of    
60%) upon expenditure of ZAR 50 million (approximately A$7.41 million) to       
complete a Bankable Feasibility Study enabling the establishment of a future    
commercial mining operation.                                                    
Funding                                                                         
During the quarter, the Company received A$2.68 million of funding through      
convertible loans from sophisticated and professional investors. Interest of 9% 
per annum was payable on the loans.  The lenders agreed to apply the proceeds of
repayment of the loans to subscribe for fully paid ordinary shares in Firestone 
at a price of A$0.04 per share. This also occurred during the quarter and 67    
million ordinary shares were issued. The funds were applied for progressing the 
Company`s Waterberg Coal joint venture with Sekoko Coal (Pty) Ltd and for other 
short term working capital requirements.                                        
In addition, during the quarter the Company announced that it had executed      
binding documentation for a fully underwritten $25m capital raise involving the 
issue of convertible notes with a conversion price of A$0.04 cents per share.   
BBY Limited is the Underwriter to the entire Issue.                             
Firestone intends to allocate the net proceeds of the raising towards:          
-    The Bankable Feasibility Study for a large scale 18Mt per annum coal mining
    operation at the Company`s Waterberg coal project in South Africa.          
-    Meeting all financial commitments due to its Joint Venture partner, Sekoko 
Coal (Pty) Limited.                                                         
-    Additional working capital requirements.                                   
Key terms of the Convertible Note                                               
The following is a summary of the key terms of the Convertible Notes.           
Issuer               Firestone Energy Limited                                   
Security             Unsecured                                                  
Issue Price          A$500,000 per Convertible Note                             
Interest Rate        10% p.a. payable semi-annually                             
Term                 3 years from the date of issue                             
Issue Size           Up to A$25 million                                         
Conversion Process   Holders of Convertible Notes may elect to                  
                     convert them at any time prior to 2.00pm AWST              
on the last day of the term.                               
Conversion Factor    On conversion, each Convertible Note will                  
                     convert into 12.5 million fully paid ordinary              
                     shares (at an effective issue price of A$0.04              
per share). The shares will rank equally with              
                     the existing fully paid ordinary shares in                 
                     Firestone except in respect of the                         
                     restrictions on transferability noted below.               
Board Appointments                                                              
During the reporting period, the Company announced the appointment of Colin     
McIntyre, who is a is a highly experienced and credentialed mining engineer,    
mining manager and company director, bringing to the Firestone Board 35 years   
experience in the mining industry, including fourteen years with Western Mining 
Corporation.                                                                    
The Company also announced that John Dreyer, a current non executive Director of
the company, had accepted the role as non executive Chairman. Mr Dreyer`s       
leadership and considerable mining and corporate experience will be invaluable  
as Firestone Energy continues to develop its South African projects. Mr Dreyer  
is a lawyer by profession and has held a number of senior executive positions   
through his career, including the position of an Executive Director of Anglo    
American Platinum, Corporation. In 2004 Mr. Dreyer retired from Anglo Platinum  
and joined Pangea Diamond Fields as a director and shareholder. He was          
instrumental in the listing of that company on AIM (LSE). Prior to joining      
Anglo, Mr. Dreyer was Chief Executive Officer of Tavistock and JCI Coal, and was
previously Managing Director of Shell South Africa. He is also a former Director
of the Richards Bay Coal Terminal Company.                                      
Following the resignation of Mr Garth Higgo, the Company has been fortunate to  
secure the services of Mr John Wallington as Managing Director from 1 November  
2009. Mr Wallington, who is based in Johannesburg, brings a wealth of coal      
experience to this new executive position. For the last 11 years of his 27 years
with Anglo Coal, he has held senior executive positions in Anglo Coal including 
Senior Vice President (1997 - 2001) and CEO (2001 - 2008). A mining engineer by 
profession, Mr Wallington has extensive practical, technical and corporate      
experience that is necessary to oversee the implementation and final development
of the BFS for FSE`s coal assets in the famous Waterberg Coal Region located at 
the north end of South Africa.                                                  
Coal Resource                                                                   
The resource has been estimated in accordance with the SAMREC and JORC codes and
the SANS 10320:2004 (South African National Standard) method of classification  
of thick inter-bedded coal deposits using some 136 boreholes of which 95 were   
recently drilled by Sekoko. All recent boreholes intersected coal and were      
logged and sampled by suitably qualified independent geologists.  The recent    
borehole data, together with the historic data, have been used to create        
geological models and allow estimation of the coal resources. The total coal    
resource estimate based on the data available at June 2009 (Venmyn Rand) is     
tabled below whilst coal quality by resource category and farm is tabled at the 
end of this announcement.                                                       
Farm            GTIS        GTIS         GTIS        GTIS                       
Zone        Coal         Coal        Coal                       
                Tonnage1    Tonnage2     Tonnage2    Tonnage2                   
                Total Mt    Inferred     Indicated   Total Mt                   
                            Mt           Mt                                     
Smitspan        1,850.3     150.2        541.2       691.4                      
306LQ                                                                           
Hooikraal       136.5       74.3         21.0        95.3                       
315LQ                                                                           
Minnasvlakte    736.6       225.9        51.1        277.0                      
258LQ                                                                           
Massenberg      187.6       45.0         14.1        59.1                       
305LQ                                                                           
TOTAL           2,910.9     495.4        627.4       1,122.8                    
1 Waterberg coal typically occurs interlaminated with shale which for the most  
part cannot be mined separately from the coal and thus the zone gross in-situ   
tonnage is the tonnage of coal and shale.                                       
2In the interest of balanced reporting it is the Company`s intention to also    
report the gross in-situ tonnage of coal rather than the tonnage of coal and    
shale.  In order to estimate the gross in-situ tonnage of coal in each zone,    
rather than the zone tonnage including the rock, each zone tonnage was          
discounted by the percent yield at a relative density of 1.9gm/cc (in effect    
removing the influence of the shale) to derive an estimate of the coal tonnage. 
Information in this report that relates to exploration results, coal resources  
or reserves on the properties Smitspan 306LQ, Hooikraal 315LQ, Minnasvlakte     
258LQ and Massenberg 305LQ is based on information compiled by Ms Catherine     
Telfer who is employed by Venmyn Rand (Pty) Ltd and is a member of The          
Australian Institute of Mining and Metallurgy and The South African Institute of
Mining and Metallurgy.  Ms Telfer has sufficient experience which is relevant to
the style of mineralisation and type of deposit under consideration and to the  
activity which she is undertaking to qualify as a Competent Person as defined in
the 2004 Edition of the "Australasian Code for the Reporting of Exploration     
Results, Mineral Resources and Ore Reserves".  Ms Telfer consents to the        
inclusion in the report of the matters based on her information in the form and 
context in which it appears.                                                    
Coal Resource Estimate Gross Tonnes In Situ                                     
                       Inferred Mt  Indicated Mt    Total Mt                    
Vetleegte 304LQ        170.4        458.9           629.3                       
Information in this report that relates to exploration results, coal resources  
or reserves is based on information compiled by Mr Dawie van Wyk who is employed
by GeoCoal (Pty) Ltd and is a member of the South African Council for Natural   
Scientific Professions.  Mr van Wyk has sufficient experience which is relevant 
to the style of mineralisation and type of deposit under consideration and to   
the activity which he is undertaking to qualify as a Competent Person as defined
in the 2004 Edition of the "Australasian Code for the Reporting of Exploration  
Results, Mineral Resources and Ore Reserves".  Mr van Wyk consents to the       
inclusion in the report of the matters based on his information in the form and 
context in which it appears.                                                    
John Dreyer                                                                     
Chairman                                                                        
For further information please contact:                                         
Mr. John Dreyer                    Tel: +61 8 9381 2755                         
Chairman                           Fax: +61 8 9381 4799                         
Pretoria                                                                        
29 October 2009                                                                 
Sponsor and Corporate Advisor                                                   
River Group                                                                     
Date: 29/10/2009 16:31:01 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: