Not logged in
  Home   Markets   Shares   Funds   Portfolio   Toolbox   Charting   Alerts   Directory   
 Admin   

Tue 1 Dec 2009, 9:00 AFE / AEA - African Eagle Resources Plc - Update On Metallugical Tests On
AEA
AEA                                                                             
AFE / AEA - African Eagle Resources Plc - Update On Metallugical Tests On       
              African Eagle`s Dutwa Nickel Project In Tanzania                  
African Eagle Resources plc                                                     
(Incorporated in England and Wales, registered number 3912362)                  
AIM share code: AFE      AIM ISIN: GB0003394813                                 
JSE share code: AEA      JSE ISIN: GB0003394813                                 
UPDATE ON METALLUGICAL TESTS ON AFRICAN EAGLE`S DUTWA NICKEL PROJECT IN         
TANZANIA                                                                        
Preliminary Results from Phase 2 Metallugical Testwork Received                 
                                                                                
-  Initial column test results show rapid leach kinetics                        
-  Up to 70% nickel extraction after just 16 days acid leaching                 
-  Low acid consumption of 200-230 kg/tonne                                     
-  Promising initial tank leach results                                         
African  Eagle`s Managing Director Mark Parker comments,  "These  results       
are  extremely  encouraging,  showing very  fast  reaction  kinetics  and       
confirming  the  good nickel extraction and low acid consumption  of  the       
Dutwa  ores.  The results show that the project is amenable to both  heap       
leach and tank leach, and point the way to further tests to determine the       
optimum  process  parameters.  The  fast  leaching  reaction,  low   acid       
consumption and good nickel extraction are extremely positive  indicators       
for the viability and profitability of the project."                            
African Eagle has received interim results from the current phase of            
metallurgical testwork, which is being conducted by Mintek of South             
Africa.  The results include the first tank leach and column leach test         
data, together with further "bottle roll" leach test results and rock           
property test results.                                                          
The  test results will help to determine the best extraction process  and       
to  optimise  parameters such as acid concentration, residence  time  and       
leach temperature in the engineering design for the feasibility study.          
Column tests                                                                    
Three column tests are being conducted to investigate the likely                
behaviour of the ore under heap leach conditions. Coarsely crushed ore          
(25mm or less in size) is packed into vertical plastic pipes, 1 metre           
high and 200mm diameter, and continuously irrigated with sulphuric acid.        
The acid dissolves the nickel and other metals as it percolates down the        
column.                                                                         
After only 16 days, 60% to 70% of the nickel had been extracted, with low       
net acid consumption of 200 to 230kg/t.  This shows extremely fast              
leaching reaction kinetics, much faster than most published nickel              
laterite data.  Although column test data cannot be simply scaled up to         
determine full-sized heap behaviour, these results are extremely                
encouraging.                                                                    
Fast reaction kinetics has important profitability implications for the         
heap leach method, as it means that working capital will not be tied up         
for many months while the heap reaches full productivity.  At Caldag in         
Turkey, for example, operator European Nickel plc reports that almost one       
year of leaching was required to extract 60% of the nickel from trial           
heaps and 540 days to extract 80%. Mintek reports that other nickel             
laterite ores it has column-tested have also taken much longer to achieve       
comparable recoveries.                                                          
Tank leach tests                                                                
Three tank leach tests have been conducted to investigate the ore               
behaviour under high temperature agitated vat leach conditions.  The ore        
samples were pulverised to three different particles sizes for these            
tests. The tests were conducted over 24 hours, but again, very fast             
reaction kinetics was seen and almost all of the nickel extraction              
occurred within the first hour. The fast initial leaching exhausted the         
acid quickly and nickel extractions reached 64%, but future tests using         
higher initial acid concentrations should give better recovery.                 
Bottle roll tests                                                               
Three additional bottle roll tests were conducted to investigate the            
effects of changing the acid concentration and the solids to liquid             
ratio.  The results showed that leaching efficiency falls if the acid           
concentration is reduced.                                                       
Physical property tests                                                         
The results of the following tests have also been received:                     
-  Bond impact work index                                                      
 -  Bond abrasion index                                                         
 -  Bond ball work index                                                        
 -  Bond rod work index                                                         
-  Uni-axial compressive strength                                              
 -  Agglomerate stability tests                                                 
 -  Bulk and true SG determination                                              
 -  Moisture content                                                            
-  Natural and complete sizing                                                 
The physical property test results will be used in the engineering design       
for the feasibility study.                                                      
Technical terms                                                                 
A glossary of technical terms used by African Eagle in this announcement        
And     other     published     material     may     be     found      at       
www.africaneagle.co.uk/p/glossary.asp                                           
For further information:                                                        
Mark Parker                                                                     
Managing Director                                                               
African Eagle                                                                   
+44 20 7248 6059                                                                
+44 77 5640 6899                                                                
Nicola Marrin                                                                   
Seymour Pierce Limited, London                                                  
Nominated Adviser                                                               
+ 44 20 7107 8000                                                               
Charmane Russell                                                                
Russell & Associates, Johannesburg                                              
+ 27 11 8803924                                                                 
+27 82 8928052                                                                  
Ed Portman / Leesa Peters                                                       
Conduit PR, London                                                              
+44 20 7429 6607                                                                
+44 77 3336 3501                                                                
1 December 2009                                                                 
About African Eagle                                                             
African  Eagle  is  a  diversified mineral  exploration  and  development       
company  operating in eastern and central Africa. The Company`s principal       
advanced  assets  are  the Dutwa nickel laterite discovery  in  Tanzania,       
where  the  Company completed a scoping study in June 2009, and  its  49%       
interest in the Mkushi Copper Mines joint venture project in Zambia,  for       
which a draft feasibility study was completed in Q4 2008.                       
African Eagle is evaluating a second promising nickel laterite deposit at       
Zanzui in Tanzania and has defined a JORC gold resource estimated at half       
a  million  ounces  at its Miyabi gold project in Tanzania.  The  Company       
holds  a well-balanced portfolio of promising earlier stage gold, copper,       
platinum  and uranium projects, including the Ndola and Mokambo  projects       
in the Zambian Copperbelt and the Igurubi gold project in Tanzania.             
Zambia,  Tanzania and Mozambique, the sites of African Eagle`s  projects,       
are  all countries which have highly prospective geology, relatively  low       
above-ground  risks and track records of successful major investments  in       
the metals and minerals industries.                                             
In December 2008, African Eagle resolved to prioritise the Dutwa project,       
because  the  Board  believes  that, of all the  Company`s  projects,  it       
offered  the  greatest  potential  to  add  value.  To  take  its   other       
discoveries  into production, African Eagle is seeking industry  partners       
with  records of successful mine development, by means of joint ventures,       
farm-ins, spin-outs or other mechanisms.                                        
About the Dutwa Project                                                         
African Eagle has discovered a significant nickel laterite deposit in the       
Dutwa project area in the Lake Victoria Goldfield.  Within Tanzania,  the       
project  is favourably situated 100km east of the railhead at Mwanza  and       
close  to the main Mwanza-Nairobi trunk road, a major power line and  the       
shore of Lake Victoria.                                                         
The  Company holds a 90% interest, with option to acquire 100%, over  the       
Dutwa  laterite  deposit and in 2009, signed a Letter of  Intent  for  an       
option  and  joint venture over another nickel laterite at  Ngasamo,  5km       
west. In all, African Eagle has explored a total area of more than 750km2       
in the project area.                                                            
Since  the  discovery of the Dutwa nickel deposit in June  2008,  African       
Eagle  has  explored  the  project  very  quickly  and  cost-effectively,       
including   resource  drilling  and  an  independent  resource  estimate;       
laboratory metallurgical and mineralogical tests which revealed that  the       
deposit could be processed efficiently by sulphuric acid leaching.  On 24       
June  2009,  the Company announced the results of its "proof of  concept"       
scoping  study.  The  study, by GRD Minproc of Perth, Western  Australia,       
indicated that the project can be economically viable, and African  Eagle       
has now begun work towards a definitive feasibility study.                      
The Study indicates that Dutwa, if it were in production today, would  be       
profitable.  Earnings, on an EBIT basis, would be of the  order  of  $110       
million  per  annum on average over the life of mine, giving an  internal       
rate of return around 20%.                                                      
As  a potentially low-cost producer, the upside for the Dutwa project  is       
considerable if nickel prices are above the $7/lb used in the base  case.       
The following table shows the key metrics for several upside cases.             
Ni price         US$/  9.00  8.50  8.00  7.50  7.00  6.50                       
                 lb                                                             
Life of mine      $M  2,600 2,300 2,000 1,800 1,500 1,200                       
EBIT                                                                            
Pre-tax IRR        %     31    27    24    21    17    13                       
Post-tax IRR       %     27    24    21    18    15    11                       
Pre-tax NPV       $M    640   530   420   310   200    90                       
Post-tax NPV      $M    430   350   270   190   110    30                       

Base case:                     Abbreviations:                                   
                                                                                
Nickel price = US$ 7/lb        EBIT = Earnings before                           
($15,430/tonne)                interest and tax                                 
Cobalt price = US$ 10/lb       IRR = Internal Rate of                           
Discount rate = 10%            Return                                           
Transport cost = US$100/tonne  NPV = Net Present Value                          
(8Cents (USD)/tonne/km)        DCF = Discounted cash flow                       
Tax rate = 30%, fiscal         analysis                                         
incentives not accounted                                                        
Royalty = 3%                   All numbers stated to 2                          
significant digits                                
The financial modelling was                                                     
conducted in US dollars with                                                    
an estimated accuracy of +/-                                                    
30%                                                                             
The Study adopted a fairly broad brush approach to many of the costs,  to       
demonstrate  "proof  of concept" and provide indicative  economics.   GRD       
Minproc  estimated  individual capital and operating costs  to  +/-  30%,       
based  on  their  considerable experience with  nickel  laterites.  These       
variables will be determined with more accuracy and confidence during the       
forthcoming feasibility work.                                                   
The  Study  identified  several  key areas  where  further  testwork  and       
detailed  study  are especially likely to result in improvements  to  the       
"bottom line" or to important gains in confidence.  These areas include:        
 -  Improved  global deposit model and the potential  for  early  "high-        
 grading".   The Ngasamo resource will be drilled and incorporated  into        
a  more  sophisticated  global resource model and  mining  plan.   From        
 this,  it will be possible to establish whether richer ore can be mined        
 first, giving increased early cash-flow and an improved NPV.                   
 -  Ore beneficiation and project scale. The capital and operating costs        
of  the  plant would be reduced if mechanical beneficiation of the  ore        
 prior  to  leaching  yields a smaller tonnage of  richer  material  for        
 processing through the plant.                                                  
 -  Advanced leaching testwork. Column and vat leach tests at bench  and        
pilot  scale  will determine the best operating conditions to  optimise        
 nickel  extraction,  including acid concentration, residence  time  and        
 temperature.                                                                   
 -  Reagent cost reductions.  The cost of reagents, notably sulphur  and        
lime,   will  be  a  significant  component  of  operating  costs   and        
 profitability   will   increase  considerably  if   these   costs   are        
 minimised.   Transport is a substantial part of the reagent  costs  and        
 ways  to  minimise this will be investigated, as will the  availability        
of more local sources, particularly of lime.                                   
 -  More sophisticated fiscal and economic modelling.  Tanzania offers a        
 number  of  tax incentives for exploration and mine development,  which        
 were not fully accounted in the Study economic model.                          
In  August,  the  Company  raised GBP3.3M additional  capital  through  a       
Placing  and  Offer,  to address these issues and  progress  the  project       
towards  feasibility.   Further metallurgical testing  has  commenced  on       
drill core samples at Mintek laboratories in South Africa and the Company       
has started infill drilling at Dutwa and resource drilling at Ngasamo.          
African Eagle acquired the Dutwa project for its gold potential, but  the       
Company`s  exploration team quickly recognised that there was significant       
nickel  laterite potential. There is very little outcrop, so the  Company       
conducted  extensive  ground magnetic surveys to  reveal  the  underlying       
structure  and  geology.  The  Company  also  compiled  historical  data,       
including  detailed geological maps and trench results dating from  1956,       
when  rock chip samples from the trenches over the ultramafic rocks  were       
reported as yielding up to 1.9% nickel.                                         
Greenstones  and granites underlie the project area. The greenstones,  of       
Archaean  Nyanzian age, are mostly metamorphosed volcanic and sedimentary       
rocks,  with  some  banded  iron formation in  the  east.  Several  large       
ultramafic  bodies occur within the greenstones and the nickel  laterites       
form a blanket up to 60m thick on top of these.                                 
To investigate the nickel discovery, the Company undertook trial drilling       
in  June  2008. The results were very encouraging and a 139-hole  reverse       
circulation  (RC)  drilling  programme was  completed  to  delineate  the       
resource.  African Eagle also undertook a 10-hole diamond drill programme       
to   obtain   core   samples  for  metallurgical  testing   and   density       
measurements.                                                                   
In  November  2008, African Eagle announced an initial  Inferred  Mineral       
Resource estimate of 31 million tonnes at an average grade of 1.1% nickel       
and 0.034% cobalt. At a cut-off grade of 0.5% nickel, this gives Dutwa  a       
contained  metal  endowment of some 340,000 tonnes of nickel  and  11,000       
tonnes  of  cobalt.  The estimate was prepared by independent consultants       
SRK  Consulting (UK) Ltd in line with the Australasian Code for Reporting       
of  Mineral  Resources  and  Ore  Reserves  (the  JORC  Code).  A  little       
additional drilling and more advanced geostatistics and deposit modelling       
will be needed to upgrade the resource to Indicated category.                   
Ngasamo Hill, 5km west of the Dutwa deposit, is geologically very similar       
and  holds  a  laterite deposit of the order of 15 to 20 million  tonnes,       
which  would  increase the global resource at Dutwa  from  the  currently       
defined  31  million  tonnes at 1.1% nickel, to  some  45  -  50  million       
tonnes.   Drilling and metallurgical tests will be needed to confirm  the       
size,  grade  and  compatibility of Ngasamo.  Under  its  agreement  with       
Ngasamo`s  owners, (Safina a.s. of the Czech Republic and  its  Tanzanian       
subsidiary Precious Metals Refinery Company Ltd), African Eagle can  earn       
an  interest  of  at least 50% and up to 75% in Ngasamo by  carrying  out       
exploration and evaluation work, up to a feasibility study.                     
Mintek  Laboratories  in  Johannesburg investigated  the  mineralogy  and       
metallurgy  of  mineralised  drill samples from  the  deposit,  including       
extended  `bottle  roll` sulphuric acid leach tests to investigate  metal       
recoveries  and  acid consumption. Mintek also carried out  mineralogical       
characterisation by X-ray diffraction (XRD), scanning electron microscopy       
(SEM) and polished section work.                                                
The bottle roll test results showed nickel extractions of 70-90% with  an       
average  of 83%.  Cobalt extractions were mostly in the range 70 to  85%.       
The  acid consumptions, averaging 209kg/t, are very low compared to other       
Ni laterite ores worldwide.                                                     
The  mineralogical  investigations show that the  laterite  is  extremely       
silica-rich, with low iron and magnesium content, indicating  that  Dutwa       
is  not a typical laterite nickel deposit.  Mintek believes that much  of       
the  nickel and cobalt occurs in "wad" with manganese content of  20-60%,       
nickel content of up to 20% and cobalt content of up to 10%.                    
The unusual mineralogy of the deposit is highly beneficial, as it results       
in  lower  acid  consumption and is expected  to  give  good  heap  leach       
permeability or favourable liquid-solid separation in tank leaching.  The       
concentration  of  nickel  and cobalt in the  manganese  wad  offers  the       
possibility  that mechanical selection of high-grade material  may  allow       
reduced throughput and hence a lower cost processing plant.                     
The  Company  is  also  investigating  other  potential  nickel  laterite       
deposits  in Tanzania, and has completed a trial programme of RC drilling       
to  test  a  laterite at its Zanzui project, 60km to the south of  Dutwa.       
Results included 42m at 1.05% nickel (including 6m at 2.80%) and  33m  at       
0.91% nickel (including 9m at 1.41%).                                           
Date: 01/12/2009 09:00:03 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: