Wed 3 Feb 2010, 7:27 FSE - Firestone Energy Limited - Highlights of Pre-feasibility study completed
FSE
FSE                                                                             
FSE - Firestone Energy Limited - Highlights of Pre-feasibility study completed  
for first stage pit on Smitspan Farm                                            
FIRESTONE ENERGY LIMITED                                                        
(formerly Centralian Minerals Limited)                                          
(Registration number: ABN 058 436 794)                                          
(SA company registration number: 200/023973/10                                  
Share code on the JSE: FSE                                                      
Share code on the ASX: FSE                                                      
ISIN: AU000000FSE6                                                              
("FSE" or "the Company")                                                        
HIGHLIGHTS OF PRE-FEASIBILITY STUDY COMPLETED FOR FIRST STAGE PIT ON SMITSPAN   
FARM                                                                            
Firestone Energy Limited (ASX/JSE Code: FSE) is pleased to announce highlights  
from the pre-feasibility study completed recently for the Smitspan property.    
Key Points                                                                      
-    21 year mine life with production up to 7mtpa saleable product.            
-    Smitspan first stage pit plan dimensions - 4.2km long and up to 1.6km wide 
    - Average 28m overburden with first stage planned mine depth to 90m.        
-    Low 2.7:1 waste to saleable product ratio.                                 
-    Indicative Capex of A$400m / 14.5% IRR (Tolerances +/- approx 25%).        
-    BFS work program and parameters refined and approved.                      
The first stage pit indentified on Smitspan farm has been planned to include an 
area of some 4.2km by 1.6km with coal intersected from 28m overburden depth down
to some 90m in the selected seams. The excavation envelope and general layout of
the mining blocks is illustrated in Figure 1 on page 3. The preferred pit       
boundary is shown as the red line and the Smitspan boundary (An area in excess  
of 11km2) shown as the yellow boundary line.                                    
The resultant minable coal seams (11 to 7) gives an expected 21 year mine life  
with production rates ramping up to 7mtpa of beneficiated product comprising    
some 80% power station coal and 20% exportable quality metallurgical coal with  
attractive low phosphorous properties.                                          
The pit boundary is defined by an attractive waste / ROM ratio of around 1:1    
producing a waste / saleable ratio of 2.7:1, enabling low cost open cut mining. 
The mine is being planned as a conventional truck and shovel operation retaining
the flexibility to respond to changing circumstances.                           
Coal extends beyond the pit boundaries in all directions with particular        
interest being the agreed addition of the Swanepoelpan farm as announced        
yesterday (T3 agreement). The Swanepoelpan property shares a 1.8km boundary with
Smitspan and hosts coal with an expected similar stripping ratio, both of which 
should enable substantial pit extensions that are not as yet contemplated in the
results for the pre-feasibility study.                                          
All financial figures derived for the PFS are within a tolerance of around +/-  
25% indicating a potential IRR of some 14.5% with indicative initial Capex      
estimated to be around A$400m.                                                  
The Board approved the final PFS report and also agreed parameters for the next 
six months to complete the Bankable Feasibility Study. The additional in-fill   
drilling committed to has commenced and should lead to substantially improved   
confidence in the projected yields and product qualities from the various zones 
of the coal seam.                                                               
The Board is very excited about the future of Firestone`s rapidly expanding coal
assets (now exceeding 1.3bn tons * excluding T3), within the Waterberg Coal     
region which contains some 50% of South Africa`s remaining coal resources,      
making the area increasingly the focus of likely future increased power         
generation and possible synthetic fuel production.                              
The increasing confidence and efforts of Firestone and Sekoko with the Waterberg
coal project has enabled the JV partners to continue to participate fully in    
state power utility Eskom`s coal proposal process and to accelerate ongoing     
discussions with all interested parties.                                        
Tim Tebeila, (Non-Executive Director of Firestone and Chairman of Sekoko        
Resources) stated that, "the size and scale of the Waterberg project as         
indicated by the positive results of the PFS, together with the increasing      
footprint and opportunity provided by the acquisition of additional, adjoining  
properties must put the JV partners clearly amongst the leaders for the         
consideration of major off-take partners".                                      
* The total coal resource estimate based on the data available at October 2009  
(Venmyn) is tabled below:                                                       
FARM         ZONE Tonnage  Measured     Indicated     Inferred      Total Coal  
Mt            GTIS Coal    GTIS Tonnage  GTIS Coal     GTIS Tonnage 
                          Tonnage Mt   Coal          Tonnage                    
Smitspan     1 901 058     97 152       416 109       106 836       620 097     
Hooikraal    358 444       0            7 282         155 491       162 773     
Minnasvlakte 705 855       0            26 507        230 687       257 194     
Massenberg   337 034       0            20 797        109 687       130 336     
Vetleegte    449 673       0            28 873        131 303       160 176     
Total        3 802 014     97 152       499 568       733 856       1 330 576   
Information in this report that relates to exploration results and coal         
resources on the properties Smitspan 306LQ, Hooikraal 315LQ, Minnasvlakte 258LQ 
and Massenberg 305LQ and Vetleegte 304LQ is based on information compiled by Ms 
Catherine Teller who is employed by Venmyn Rand (Pty)Ltd and is a member of The 
Australian Institute of Mining and Metallurgy and the South African Institute of
Mining and Metallurgy.  Ms Telfer has sufficient experience which is relevant to
the style of mineralisation and type of deposit under consideration and to the  
activity which she is undertaking to qualify as a Competent Person as defined in
the SAMREC and JORC Codes.  Ms Telfer consents to the inclusion in the report of
the matters based on her information in the form and context in which it        
appears.                                                                        
For further information please contact:                                         
John Wallington                                                                 
Managing Director                                                               
Telephone: +61 8 9381 2755                                                      
Pretoria                                                                        
3 February 2010                                                                 
Corporate Adviser and Sponsor                                                   
River Group                                                                     
Date: 03/02/2010 07:27:58 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: