Not logged in
  Home   Markets   Shares   Funds   Portfolio   Toolbox   Charting   Alerts   Directory   
 Admin   

Thu 11 Feb 2010, 10:14 AQP - Aquarius Platinum Limited - 2010 Half year financial results - December
AQP
AQP                                                                             
AQP - Aquarius Platinum Limited - 2010 Half year financial results - December   
2009                                                                            
Aquarius Platinum Limited                                                       
(Incorporated in Bermuda)                                                       
Registration Number: EC26290                                                    
Share Code JSE: AQP                                                             
ISIN Code: BMG0440M1284                                                         
Aquarius Platinum                                                               
2010 HALF YEAR FINANCIAL RESULTS - DECEMBER 2009                                
Key Points: Operational                                                         
-    Attributable production for the first half of the 2010 financial year was  
208,857 PGM ounces, 7% higher than the previous 6 months to June 2009,      
    though 20% lower compared to the 6 months to December 2008, due largely to  
    the temporary closure of Everest                                            
-    Group Cash costs for the first half 2009 increased by 7% compared to first 
half 2008 to $682 per PGM ounce from $639 per ounce, reflecting lower       
    production and a stronger Rand                                              
Key Points: Financial                                                           
-    Average basket prices increased by 25% to $1,026 per PGM ounce compared to 
the six months ended June 2009                                              
-    Revenues increased by 48% to $206.1 million despite lower production as a  
    result of higher PGM prices                                                 
-    Net profit of $3.9 million (US 0.86 cents per share), impacted by a number 
of one-off charges including $20.8 million relating to early redemption of  
    convertible notes and $7.8 million relating to a Zimbabwean deferred tax    
    liability recalculation due to the change in corporate tax rate             
-    Successfully raised $300m through a convertible bond issue, strengthening  
the balance sheet                                                           
-    Consolidated cash balances at period end of $464.6 million                 
-    Interim dividend of US 2.0 cents per share declared                        
Key Points: Strategic                                                           
-    Integration and production ramp-up at Blue Ridge progressing well          
-    Everest re-establishment project initiated and progressing well            
-    Mimosa and Platinum Mile expansions completed                              
Commenting on the results, Stuart Murray, CEO of Aquarius Platinum said:        
"The improvement in the Dollar basket price during the first six months of the  
2010 financial year has enabled Aquarius to return to profitability despite a   
strong Rand and the lower production caused principally by the unprotected      
industrial action at Kroondal and Marikana in the first quarter. Aquarius staff 
have worked hard to successfully control costs and mitigate production loss. I  
am pleased with the progress made with the ramp-up at Blue Ridge, the re-       
establishment project at Everest and the outcome of the Mimosa expansion.       
With the improved outlook in terms of revenue per ounce, the second half        
financial results should be an improvement on the first half. The belief in     
improved times ahead has enabled the company to resume the payment of           
dividends."                                                                     
Aquarius Half Year Group Attributable Production                                
(Please refer to www.aquariusplatinum.com for the graph)                        
Production                                                                      
Total on mine PGM production for the period was 417,714 PGM ounces.  This       
represents a 2% increase compared to the six months ended June 2009, and an 8%  
decrease (due to the temporary closure of Everest) when compared to the December
2008 period.  Production attributable to Aquarius was up 7% to 208,857 PGM      
ounces for the half year ended December 2009 when compared to the six months    
ended June 2009, though 20% lower compared to the previous corresponding period 
(pcp). This decrease was due to the temporary closure of the Everest Mine on 7  
December 2008.                                                                  
Production by Mine and Attributable to Aquarius                                 
PGMs (4E)     Mine                      Attributable to Aquarius                
Half Year    Half Year     Half Year    Half Year                  
            ended        ended         ended        ended                       
            Dec 2009     Dec 2008      Dec 2009     Dec 2008                    
Kroondal      197,061      211,438       98,530       105,720                   
Marikana      68,381       81,333        34,190       40,667                    
Everest       -            64,068        -            64,068                    
Mimosa        100,907      86,870        50,454       43,435                    
CTRP          3,827        3,548         1,913        1,774                     
Platinum Mile 14,471       9,088         7,236        4,544                     
Blue Ridge    33,067       -             16,534       -                         
Total         417,714      456,345       208,857      260,208                   
The period under review was impacted by the suspension of operations at Everest 
as well as the unprotected industrial action that took place at Kroondal and    
Marikana in September 2009. These factors resulted in a decrease in production  
compared to the first half of the 2009 financial year. However growth is being  
maintained as shown in the following graph as a result of the Mimosa expansion, 
Platinum Mile expansion and the Blue Ridge acquisition; and the negative impact 
shown is of a temporary nature and will not detract from the longer term AQPSA  
profile.                                                                        
(Please refer to www.aquariusplatinum.com for the graph)                        
Foreign Exchange                                                                
The Rand continued to strengthen over the 6 months to December 2009 moving from 
an average of 8.79 in the period to December 2008 to a period average of 7.65.  
The Rand closed the half year at R7.39 to the US Dollar.                        
Rand Dollar Exchange Rate                                                       
(Please refer to www.aquariusplatinum.com for the graph)                        
Platinum Group Metal Prices                                                     
US Dollar PGM prices continued to reflect an improving fundamental market       
demand and significant interest in Exchange Traded Funds (ETF) continues to     
drive platinum and palladium prices. The US-based platinum and palladium ETFs   
commenced trading on 8 January 2010 on the NYSE Arca exchange, the same day     
that the Julius Baer Swiss-based physically-backed ETFs also commenced trading. 
These are the first physically-backed ETFs for the metals in the US and are     
expected to further increase investor interest in PGMs.                         
With prices rising across all PGM metals, palladium and rhodium recorded the    
largest price increases, at 58% and 72% respectively. Platinum closed the period
24% higher at $1,461 per ounce, rhodium 72% higher at $2,500 per ounce,         
palladium 58% higher at $393 per ounce, and gold 18% higher at $1,105 per ounce.
Individual PGM Prices December 2008 - 2009 (Dollar and Rand per PGM ounce)      
(Please refer to www.aquariusplatinum.com for the graph)                        
The Rand continued to strengthen against a weak US Dollar during the half year  
but stabilised towards the end of the period. This stability, linked with       
continued strength in Dollar prices reflected in strong improvement in Rand     
prices towards the end of the period. South African operations averaged $1,086  
per PGM ounce (equivalent to R8,309 per PGM ounce) and closed the period at     
R9,136 per PGM ounce.  In Zimbabwe, the average achieved basket price for the   
first half of the financial year was $859 per ounce. This resulted in a group   
basket price equivalent of $1,026 per PGM ounce, up 25% from the six months     
ended June 2009.                                                                
PGM Basket Prices December 2008 - 2009 (Dollar and Rand per PGM ounce)          
(Please refer to www.aquariusplatinum.com for the graph)                        
Financial results: Half Year to 31 December 2009                                
Aquarius showed a significant financial improvement on the previous             
corresponding period, moving from a $70.1 million loss to a profit of $3.8      
million (0.86 cents per share) for the half year ended 31 December 2009 (the    
"Result"), a $74 million turnaround.                                            
This improvement was evident in a $129 million increase in mine EBITDA, moving  
it from a negative of $72.8 million in the pcp to a positive of $56.7 million in
the current period. The improved result was despite lower comparative production
(due to the temporary closure of the Everest mine in December 2008) and reflects
improved and less volatile PGM prices.                                          
The Directors have declared an interim dividend of US 2 cents per share (2009:  
nil) payable on 26 March 2010 to shareholders registered on 5 March 2010,       
reflecting the company`s improved operational cash flow and the Directors`      
increasing confidence in the improved economic environment.                     
The Result was heavily influenced by exceptional non mining expenditure,        
primarily related to:                                                           
-    the early redemption of the Rand convertible notes resulting in net costs  
of $20.8 million; and                                                       
-    a $7.8 million increase in Mimosa`s deferred tax liability following an    
    increase from 15% to 25% in Zimbabwe`s corporate tax rate.                  
Group Financials by Operation (attributable to Aquarius)                        
$ million   Kroondal   Marikana Everes Mimos CTRP   PMR    Blue   Corpo  Total  
                             t      a                 Ridge  rate               
PGM ounces  98,530     34,190   -      50,45 1,913  7,236  16,53  -      208,85 
(4E)                                 4                 4            7           
(attributa                                                                      
ble)                                                                            
Revenue     101.6      36.4            55.1  2.1    7.4           3.5    206.1  
Cost of                                                                         
sales                                                                           
On mine     (71.2)     (33.0)   (3.4)  (28.9 (1.4)  (4.6)                (142.5 
cash costs                           )                             )            
Depreciati  (9.7)      (5.0)           (2.7) (0.1)  (2.3)         (0.1)  (19.9) 
on &                                                                            
amortisati                                                                      
on                                                                              
Gross       20.7       (1.6)    (3.4)  23.5  0.6    0.5           3.4    43.7   
profit                                                                          
Other                                                             0.4    0.4    
Income                                                                          
Corporate                                                         (8.2)  (8.2)  
admin &                                                                         
other                                                                           
costs                                                                           
Foreign     (0.6)      (1.0)           (0.8)                      18.5   16.1   
currency                                                                        
gain/(loss                                                                      
)                                                                               
Finance                                                           (10.6  (10.6) 
charges                                                      )                  
Early                                                             (20.8  (20.8) 
redemption                                                   )                  
of con                                                                          
note                                                                            
Ridge                                                             0.2    0.2    
acquisitio                                                                      
n costs                                                                         
(net)                                                                           
Reversal/(                             0.5                        -      0.5    
Impairment                                                                      
) of                                                                            
assets                                                                          
Profit/(lo  20.1       (2.6)    (3.4)  23.2  0.6    0.5           (17.2  21.3   
ss) before                                                   )                  
tax                                                                             
Tax                                                                      (17.4) 
benefit/(e                                                                      
xpense)                                                                         
Profit/(lo                                                               3.9    
ss) after                                                                       
tax                                                                             
             Net profit Half  Add back costs associated   Adjusted Net          
             year 31 Dec      with:                       profit Half           
2009                                         year 31 Dec           
                                                          2009                  
                              Early         Increase in                         
                              redemption    Zimbabwe`s                          
of Rand       corporate                           
                              convertible   tax rate                            
                              notes                                             
Revenue       $206.1m          -             -             $206.1m              
Mine EBITDA   $56.7m           -             -             $56.7m               
Operating     ($14.6m)         -             -             ($14.6m)             
expenses                                                                        
Early         ($20.8 m)        $20.8 m       -             -                    
redemption of                                                                   
Rand                                                                            
convertible                                                                     
notes                                                                           
Profit before $21.3m           $20.8m        -             $42.1m               
tax                                                                             
Income tax    ($17.4m)         -             $7.8 m        ($9.6m)              
expense                                                                         
Net profit    $3.9 m           $20.8 m       $7.8 m        $32.5m               
after tax                                                                       
On an adjusted basis for one-offs, the net profit for the period is estimated at
$32.5 million (as outlined in the table below).                                 
Revenue (PGM sales and interest) for the half year to December 2008 was up 48%  
from $139 million in the pcp to $206 million. Measured on a PGM ounce basis,    
this represents an increase from $535 per PGM ounce to $1,071 per PGM ounce.    
Gross margins recovered following improved and less volatile PGM prices during  
the half year.                                                                  
Total cash cost of production was $142.5 million, up 10% per PGM ounce in Dollar
terms, partially influenced by Rand strength. Amortisation and depreciation were
marginally lower at $20 million from $21 million reflecting lower production.   
Finance costs for the period of $10.6 million includes interest on convertible  
notes and bank borrowings at Mimosa level and a non cash element of $2.7 million
relating to the net present value adjustments to the Marikana and Kroondal      
rehabilitation provisions.                                                      
Income tax expense was higher due to a $7.8 million increase in Mimosa`s        
deferred tax liability following an increase from 15% to 25% in Zimbabwe`s      
corporate tax rate                                                              
Net operating cash generated showed a $33.5 million improvement, bringing net   
operating cash inflow to a positive $17.7 million for the period despite lower  
comparable production. Following the successful raising of $300 million of      
unsubordinated, unsecured convertible notes Aquarius` cash balances increased   
$378 million from the pcp to $465 million.                                      
On 18 January 2010, Aquarius utilised approximately $106 million from its cash  
reserves to retire the Company`s existing R650 million convertible notes in     
accordance with their terms (at an aggregate redemption price of R747.5         
million). Notification of redemption was given on 21 December 2009 and          
completion of the redemption process occurred on 18 January 2010. The impact    
arising from the notification of early redemption of the company`s rand         
convertible notes inclusive of the borrowing costs and the 15% premium was      
accounted for in the consolidated income statement for the period under review. 
Acquisition of Ridge Mining plc                                                 
On 6 July 2009, pursuant to a Scheme of Arrangement, Aquarius acquired 100% of  
the voting shares of Ridge, a company registered and headquartered in England   
and publicly listed on the AIM market of the London Stock Exchange.             
Ridge`s Blue Ridge Mine is in commissioning and ramp-up and will further        
diversify Aquarius` portfolio, increase its resource base, and add new          
production ounces and longevity to its production profile. The acquisition will 
also add significant optionality with the new Sheba`s Ridge project.            
The total cost of the business combination was US$112,703,640 and comprised the 
issue of equity instruments - both ordinary shares and options over ordinary    
shares.  Aquarius issued 33,477,945 ordinary shares with a fair value of GBP    
1.968 each, based on the quoted price of the shares of Aquarius on 6 July 2009. 
Convertible Notes                                                               
In December 2009, Aquarius concluded a capital raising of $300 million of       
unsubordinated, unsecured convertible bonds, due 2015.                          
The Bonds were issued at 100% of their principal amount and have a coupon of    
4.0% per annum, payable semi-annually in arrears. The initial conversion price  
is $6.773 per share, representing a premium of 22.5% to the volume weighted     
average price of the Company`s common shares on the London Stock Exchange (LSE) 
between launch and pricing, translated at a GBP-USD exchange rate of 1.653. With
the declaration of the interim dividend the conversion price will be adjusted   
and bondholders informed in due course of the revised conversion price.         
Part of the proceeds of the Bonds have been used to fund the early redemption of
all of the Company`s existing R650 million convertible bonds in accordance with 
their terms (at an aggregate redemption price of R747.5 million) with the       
balance for general corporate purposes and business opportunities.              
The Bonds commenced trading on the Exchange`s LSE`s Professional Securities     
Market on 21 December 2009.                                                     
Financials                                                                      
Aquarius Platinum Limited                                                       
Consolidated Income Statement                                                   
For the Half Year ended 31 December 2009                                        
$`000                                                                           
                                         Half Year Ended        Year            
                                                                Ended           
                              Note:      31/12/09    31/12/08   30/6/09         
Production                                                                      
Everest mine                              -           64,068     64,068         
All other mines                           192,323     196,140    391,607        
Attributable Production (PGM              192,323*    260,208    455,675        
Ounces)                                                                         
(before Blue Ridge production                                                   
of 16,534 ozs)                                                                  
Revenue                        (i)        206,089     139,179    310,556        
Cost of sales (including D&A)  (ii)       (162,380)   (197,321)  (334,327       
                                                                )               
Gross profit/(loss)                       43,709      (58,142)   (23,771)       
Other income                              510         186        1,815          
Corporate Admin & other costs  (iii)      (8,268)     (4,710)    (9,919)        
Finance costs                  (iv)       (10,644)    (21,590)   (35,968)       
Loss arising on notification              (20,836)    -          -              
of redemption of convertible                                                    
notes                                                                           
Foreign exchange               (v)        16,086      (36,299)   (20,328)       
gains/(losses)                                                                  
Transaction and acquisition    (vi)       246         -          -              
costs associated with Ridge                                                     
Mining                                                                          
Fair value movement in                    -           -          3,829          
derivative                                                                      
Reversal/(Impairment) of       (vii)      506         (12,582)   (13,050)       
assets                                                                          
Profit/(loss) before tax                  21,309      (133,137)  (97,392)       
Income tax credit (expense)    (viii)     (17,438)    27,165     15,808         
Profit/(loss) after tax                   3,871       (105,972)  (81,584)       
Minority interest              (ix)       -           35,842     35,842         
Net profit/(loss)                         3,871       (70,130)   (45,742)       
Earnings per share (basic -               0.86        (25.09)    (13.30)        
cents)                                                                          
Notes on the Consolidated Income Statement                                      
(i)  Revenue is higher compared to December 2008 despite lower PGM ounces       
    produced, due to improved metal prices and a less volatile price            
environment.                                                                
(ii) The 11.3% increase in cost of sales on a unit cost basis reflects Rand     
    strength, the impact of inflation on mine cash costs, and includes          
    depreciation and amortisation of $19.9 million.                             
(iii)     Relates to administration costs of the Aquarius Group  inclusive of   
         costs associated with business development   activities, legal and     
         financial advisory expenses.                                           
(iv) Finance costs reflect a $7.3 million interest expense on convertible notes 
and bank loan at Mimosa, pipeline finance of $0.4 million and interest      
    expense on the unwinding of the rehabilitation provisions of $2.7 million.  
(v)  Foreign exchange gains are mainly a result of gains on group loans due to  
    the weakening of the Dollar against the Rand.                               
(vi) Reflects net impact of transaction and acquisition costs associated with   
    the acquisition of Ridge Mining.                                            
(vii)Reflects reversal of impairment charges for listed investments.            
(vii) Income tax includes a $7.8 million increase in Mimosa`s deferred tax      
liability following an increase from 15% to 25% in Zimbabwe`s corporate tax     
rate.                                                                           
(ix) Minority interest reflects interest previously at AQPSA level, now 100%    
owned by AQP.                                                                   
Aquarius Platinum Limited                                                       
Consolidated Cash Flow Statement                                                
Half year ended 31 December 2009                                                
$`000                                                                           
Half year ended         Year ended          
                            Note:   31/12/09     31/12/08   30/06/09            
Net operating cash inflow    (i)     17,651       (15,880)   12,006             
Net investing cash outflow   (ii)    (29,881)     (24,444)   (73,380)           
Net financing cash outflow   (iii)   312,872      (30,094)   38,754             
Net increase in cash held            300,642      (70,418)   (22,620)           
Opening cash balance                 153,600      170,956    170,956            
Exchange rate movement on    (iv)    10,334       (13,584)   5,264              
cash                                                                            
Closing cash balance                 464,576      86,954     153,600            
Notes on the Consolidated Cash Flow Statement                                   
(i)  Net operating cash flow includes a $179.3 million net inflow from sales,   
$156.7 million paid to suppliers, interest income of $4.6 million, interest 
    expense of $4.3 million and income tax paid of $5.7 million.                
(ii) Reflects development and plant and equipment expenditure of $43.5 million  
    less cash balances acquired as part of the Ridge acquisition.               
(iii)     Includes $293.9 million net proceeds from a capital raising of        
    unsubordinated, unsecured convertible bonds, proceeds from the issue of     
    shares on exercise of options and warrants, loans repaid $11 million and    
    $10.8 million loan to an associate company.                                 
(iv) Reflects movement of Rand against the US dollar.                           
Aquarius Platinum Limited                                                       
Consolidated Balance Sheet                                                      
At 31 December 2009                                                             
$`000                                                                           
                                  Half year ended    Year                       
                                                     ended                      
                           Note:  31/12/09   31/12/  30/06/0                    
08      9                          
Assets                                                                          
Cash assets                        464,576    86,954  153,600                   
Current receivables         (i)    165,661    71,754  119,866                   
Other current assets        (ii)   50,255     45,017  43,652                    
Property, plant and         (iii)  299,616    195,90  230,057                   
equipment                                     4                                 
Mining assets               (iv)   389,120    260,00  270,374                   
2                                  
Other non-current assets    (v)    26,685     13,029  25,287                    
Intangibles                 (vi)   76,980     49,231  74,167                    
Total assets                       1,472,893  721,89  917,003                   
1                                  
Liabilities                                                                     
Current liabilities         (vii)  179,525    229,63  81,514                    
                                             5                                  
Non-current payables        (viii  5,532      1,986   1,555                     
                           )                                                    
Non-current interest-       (ix)   254,959    1,933   70,034                    
bearing liabilities                                                             
Other non-current           (x)    193,196    100,86  155,730                   
liabilities                                   8                                 
Total Liabilities                  633,212    334,42  308,833                   
                                             2                                  
Net assets/(liabilities)           839,681    387,46  608,170                   
                                             9                                  
Equity                                                                          
Parent entity interest             839,681    387,46  608,170                   
9                                  
Minority interest                  -          -       -                         
Total Equity                       839,681    387,46  608,170                   
                                             9                                  
Notes on the Consolidated Balance Sheet                                         
(i)  Reflects debtors receivable on PGM concentrate sales.                      
(ii) Reflects PGM concentrate inventory, reef stockpiles and consumables stores.
(iii)     Represents plant and equipment within the Group.                      
(iv) Mining assets relate to Kroondal, Marikana, Mimosa, Everest and Blue Ridge 
    mine properties and mine development.                                       
(v)  Includes recoverable portion of rehabilitation provision from Anglo        
    Platinum ($11.9 million), investments in rehabilitation Trusts of $12.6     
million and investments held for resale of $2.1 million.                    
(vi) Included intangibles relating to goodwill and contract value acquired on   
    acquisition of 50% equity interest in Platinum Mile Resources (Pty) Ltd.    
(vii)     Includes $106.7 million of Rand convertible notes subsequently paid   
out on 18 January 2010, creditor and other payables of $71.7 million and    
    tax payable of $1 million.                                                  
(viii)    Includes rehabilitation obligations on P&SA1 and P&SA2 structures.    
(ix) Includes convertible notes of $231m, DBSA and IDC loans at Blue Ridge Pty  
Ltd level of $23m,  Investec loan to Platmile of  $0.2m, AQPSA vehicle      
    leases of $0.6m and TKO loan of $0.3m.                                      
(x)  Includes deferred tax liabilities of $106.6 million, provision for closure 
    costs of $70.9 million.                                                     
OPERATIONS                                                                      
AQUARIUS PLATINUM (SOUTH AFRICA) (PTY) LTD (Aquarius Platinum Limited - 100%)   
P&SA1 at Kroondal                                                               
Safety                                                                          
-    No fatal accidents during the period - Kroondal achieved 12 fatality-free  
    months in Q2 2010                                                           
-    The 12-month rolling average disabling injury incidence rate (DIIR)        
    improved to 0.63 from 0.77 during the half year                             
Mining                                                                      
-    Underground volumes fell by 10.6% to 3.1 million tonnes due to unprotected 
    industrial action                                                           
-    Open pit operations ceased in the previous financial year                  
-    Achieved head grade in the first half increased by 1.2% compared to 1H     
    2009, to 2.60 g/t.                                                          
    Processing                                                                  
-    3.0 million tonnes of ore processed in concentrator plants, 6.8% lower than
in 1H 2009                                                                  
-    Concentrator recoveries improved marginally to 79%                         
-    Production decreased by 6.8% to 197,061 PGM ounces                         
-    Strong operational response in Q2 2010 partially offset ounces lost to     
unprotected strike in Q1                                                    
Revenue                                                                         
The Dollar PGM basket price achieved by Kroondal for the first half was         
$1,077 per PGM ounce. This was 12.7% lower than in the comparable period last   
year, but 25.9% higher than in 2H 2009.  The Rand also strengthened over the    
period, with the Rand/Dollar exchange rate averaging R7.65/$ for the six months 
as a result (1H 2009: R8.79/$). Revenue at Kroondal in 1H 2010 was consequently 
lower initially, but the stabilising and subsequent increase in PGM prices      
during the half resulted in positive sales adjustments. By comparison these     
adjustments were materially negative in 1H 2009 due to falling PGM prices.      
Overall revenue from the mine therefore increased in 1H 2010 by 84.2% to        
R1,549 million.                                                                 
Operations                                                                      
Production of ore from the Kroondal underground operations for the first six    
months of FY2010 was 3.1 million tonnes, a decrease of 10.6% compared with the  
first half of FY2009. This reduction in mined volumes was largely as a result   
of the unprotected industrial action that occurred during the first quarter of  
the financial year involving employees of the underground mining contractor,    
MRC, on three of the Kroondal shafts. This industrial action took place despite 
a wage settlement of 10.2% having been agreed between MRC and the National      
Union of Mineworkers (NUM), and eventually resulted in a mass dismissal of the  
workforce. Disruptive and intimidatory action by former employees prevented     
effective recruitment from the dismissed employee base, requiring a greater     
component of those recruited to be new employees, which delayed the engagement, 
training and deployment plan, further impacting mining volumes. This unprotected
strike action also affected both underground shafts at Marikana. The new        
workforce has been fully trained and subsequent to the replacement of the old   
workforce, industrial relations have been stable at both operations.            
During the first quarter, the underground mining contract at the K5 shaft was   
transferred from Redpath to MRC, motivated by operational and equipment         
synergies. Although the transfer process proceeded according to plan, it did    
result in lower production during the handover. At the period end, the K5 shaft 
was achieving the benefits and synergies anticipated by management as a result  
of the transfer.                                                                
Mining volumes at Kroondal fell 16.0% quarter on quarter in the first quarter of
the financial year, but rose by 21.9% in the second quarter to a satisfactory   
level following a creditable operational management response to the problems    
encountered in the first part of the financial year.                            
Primary development increased by 12.0% over the period to a total of 4,072      
metres due to improved operational efficiencies and ground conditions.          
At the end of the period, stockpiles had been increased to 130,000 tonnes of ore
in preparation for the Christmas close and to mitigate the impact of the Q3     
holiday season.                                                                 
The concentrators processed 3.0 million tonnes in the first six months of the   
financial year, representing a decrease of 6.8% versus the comparable period    
in the prior year. This reduction was again due to the knock-on effect of the   
unprotected strike. The plant head grade increased slightly to 2.60g/t for the  
first half, primarily due to a reduction in footwall waste and waste from       
off-reef mining being packed underground, while recoveries improved to 79%      
through improvement initiatives in operational stability and control. Total     
4E PGM production fell by 6.8% to 197,061 PGM ounces, 98,531 PGM ounces of      
which are attributable to Aquarius.                                             
Operating Cash Costs                                                            
Cash costs for the first half increased by 7.7% compared to 1H 2009, to R365    
per ROM ton and by 6.7% to R5,549 per PGM ounce. It is also noteworthy that Rand
costs per PGM ounce in Q2 2010 were only 2.0% higher than in the corresponding  
quarter a year ago.                                                             
The relative strength of the Rand against the Dollar is reflected in the fact   
that the cash costs in Dollar terms increased 22.5% to $725. Rand-denominated   
costs were affected by both the unprotected strike as lower production increased
the impact of fixed costs, and by increased labour costs. Electricity tariffs   
were increased materially (33%) in June 2009, resulting in increased effective  
electricity costs at Kroondal over the first half of the year. However, as a    
result of the shallow nature of the Kroondal ore body and the trackless mining  
method employed by Aquarius, electricity only comprises approximately 5% of     
cash costs. Labour remains the largest single component of Kroondal`s operating 
cash costs, representing approximately 50% of the total.                        
Kroondal: Operating Cash Costs                                                  
4E               6E                   6E net of by-                   
          (Pt+Pd+Rh+Au)    (Pt+Pd+Rh+Ir+Ru+Au)  products (Ni&Cu)                
Kroondal   R 5,549 per PGM  R 4,542 per PGE      R 4,410 per PGE                
          ounce            ounce                ounce                           
Capital Expenditure                                                             
Capital expenditure at Kroondal was R72 million in the first half of FY2010,    
or approximately R368 per PGM ounce. This was spent largely on the construction 
of underground infrastructure. Kroondal management was able to significantly    
reduce capital expenditure at the mine compared with prior periods as a result  
of reclamation and re-design initiatives. All of the expenditure incurred       
during the period was stay-in-business sustaining capital, and Kroondal`s       
expenditure is up to date as per mine plan.                                     
Firstplats transaction                                                          
The Firstplats transaction was concluded during the first half, as announced    
previously. It has resulted in a pro-rata addition of 0.46 million ounces       
of reserves into the P&SA1, thereby extending the life-of-mine of Kroondal      
in excess of one year. The additional reserves are down-dip of central shaft    
and will be mined from existing shaft infrastructure requiring only             
stay-in-business capital expenditure and enabling cost efficient ore            
extraction.                                                                     
P&SA2 at Marikana                                                               
Safety                                                                          
-    No fatal accidents during the period - Marikana achieved 12 fatality-free  
    months shortly after the close of the half year                             
-    The 12-month rolling average DIIR for the half year deteriorated to 1.08   
    compared with 0.70 in the previous corresponding period as a result of the  
    higher risk profile associated with operations moving from primarily open   
    pit mining to a combination of underground and open pit mining              
-    Management actions have been implemented which are expected to reverse this
    trend over time                                                             
Mining                                                                          
-    Underground production ramp-up continues to progress with 761,000 tons     
mined for the period despite the closure of 2 Shaft (at the end of the pcp) 
    and the unprotected industrial action                                       
-    Open pit production decreased to 420,000 tons as a result of geological    
    pothole intersections and the ramping down of opencast operations           
-    Head grade decreased to 2.67 g/t due to increased underground tonnage      
Processing                                                                      
-    Tonnes processed decreased by 15.0% compared to the first half of 2009,    
to 1,157,000, reflecting lower availability of opencast material                
-    Recoveries improved by 7.8% to 69%                                         
-    Marikana produced 68,381 4E PGM ounces during the period, a 15.9% decrease 
    compared to the first half of 2009                                          
-    Production, head grade and recoveries all improved in the second quarter of
the financial year                                                              
Revenue                                                                         
The Dollar PGM basket price achieved by Marikana for the first half was $1,093  
per PGM ounce, 8.8% lower than in 1H 2009 but 26.7% higher than in 2H 2009. As  
was the case at Kroondal, the strengthening Rand and lower basket prices        
resulted in Marikana generating lower revenue initially, but the stabilising    
and subsequent increase in PGM prices during the half resulted in positive      
sales adjustments. As a result, overall revenue at Marikana increased by 82.5%  
to R553 million in the period under review.                                     
Operations                                                                      
Total mine production for the first six months decreased by 18.0% to 1,2 million
tonnes, made up of 761,000 underground tonnes and 420,000 open pit tonnes. The  
reduction in the total was as a result of several factors, including the        
unprotected industrial action affecting Marikana`s underground operations, the  
ramping down of the opencast operations and the closure of 2 Shaft. Open pit    
mining volumes were also impacted negatively by a significant pothole           
intersection that occurred shortly prior to the commencement of the first half. 
Production improved during the second quarter as the operations stabilised.     
The Pit A opencast area was mined out during the second quarter. Opencast mining
is now focussed on the ROM and West-West pits. The majority of the oxide        
material in the West-West pit was mined out during the final months of the first
half and the remainder of the mining in the pit will be in un-oxidised material,
which should yield higher recoveries.  Pre-stripping costs were incurred in the 
West-West pit which will contribute to lower stripping ratios and mining cost   
during the next quarter.                                                        
Although delayed by the unprotected industrial action, the ratio of underground 
mining to opencast continues to increase, as the production build-up at 4 Shaft 
continues and the opencast mine approaches its end of life. Development         
activities to negate the effect of a high incidence of potholing and geological 
features at 1 and 4 Shafts are yielding results, with a commensurate increase in
production in the later months of the period under review. The amount of mining 
done adjacent to potholes has negatively influenced the in-situ grade,          
exacerbated by the necessary focus on development after the industrial action,  
resulting in lower grades due to higher than normal waste contribution. The     
grade improved towards the end of the first half as stoping tonnes increased and
panels moved away from pothole areas.                                           
Re-commissioning of the western shaft of the Firstplats acquisition (termed M5  
shaft) also commenced and first production from that mining area is expected    
during the next quarter.  The beneficial access arising from the Firstplats     
acquisition has yielded significant life of mine capital savings (precluding the
use of vertical shafts) and enabled faster mining access to the Marikana ore    
body adjacent to the acquisition area.                                          
The surface stockpile decreased to 38,000 tons at the end of the period, as ore 
stocks were used to offset lower mining volumes.                                
During the first six months, a total of 1,157,000 tons were processed in the    
Marikana concentration plant, a 15.1% decrease period on period.                
The average plant head grade decreased to 2.67g/t for the first six months      
compared to 2.87 g/t for 1H 2009 due to higher percentage of underground ore and
lower-than-expected underground grades as a result of geological anomalies.     
Plant recoveries increased to 69% as the use of oxide material from the open pit
operations declined. Marikana produced 68,381 PGM ounces in the first half of   
FY2010 (Aquarius attributable 34,191 PGM ounces), down 15.9% compared to 1H     
2009.                                                                           
Operating Cash Costs                                                            
Cash costs for the first half increased by 3.8% compared to 1H 2009, to R436 per
ROM ton and by 4.9% to R7,386 per PGM ounce. As with Kroondal it is noteworthy  
that Rand costs per PGM ounce in Q2 2010 at Marikana were only 1.2% higher than 
in the corresponding quarter a year ago. Rand cash costs in Q2 2010 also showed 
some improvement compared to the first quarter of this financial year, falling  
12% to R6,954 per PGM ounce. As with Kroondal, costs were negatively impacted by
increased labour costs and the effect of the mine`s fixed cost base during the  
unprotected industrial action in the first quarter. Electricity remains less    
than 5% of operating costs at Marikana, while labour constitutes approximately  
50%.                                                                            
The relative strength of the Rand against the Dollar is reflected in the fact   
that the cash costs per PGM ounce in Dollar terms increased 20.5% to $965.      
Marikana: Operating Costs                                                       
         4E (Pt+Pd+Rh+Au)   6E                   6E net of by-                  
(Pt+Pd+Rh+Ir+Ru+Au)  products (Ni&Cu)               
Marikana  R7,386 per PGM     R6,130 per PGE       R 5,949 per PGE               
         ounce              ounce                ounce                          
Capital Expenditure                                                             
Stay-in-business capital expenditure at Marikana decreased by 35.7% to a total  
for the period of R33.7 million (R491 per PGM ounce). This consisted primarily  
of underground infrastructure establishment. All critical capital expenditure is
up to date.                                                                     
Everest                                                                         
Safety                                                                          
-    Everest achieved a zero 12-month rolling DIIR                              
-    Everest completed 342 days without a lost time injury at the end of the    
first half                                                                      
Operations                                                                      
Mining operations were suspended at Everest in December 2008 following a        
subsidence event. The subsidence occurred over a mined-out area, and as a result
no resources were lost and stoping areas were not affected. The re-establishment
of Everest therefore relates entirely to the construction of new access points  
and associated infrastructure.                                                  
Phase 1 of the re-establishment project, involving the excavation of the box    
cuts, storm water and earth works, the installation of temporary services and an
access road was completed by the end of the first half. Phase 2, which includes 
the establishment of permanent underground services, the reclamation of         
infrastructure, equipping of declines and strike sections and there-            
establishment of stoping sections, has commenced and is proceeding as planned.  
Permanent surface infrastructure, such as mine services, roads and overland     
conveyers will also be completed during this phase.                             
Decline development in the new North boxcut is now 65% complete with belt and   
surface infrastructure construction progressing as per schedule. The South      
boxcut was also completed during the period under review and a single decline   
shaft will be developed to provide access for men and material and for          
ventilation to the south stoping areas. A steel pre-fabricated tunnel was       
constructed from the high wall to surface and the boxcut will be completely     
filled and rehabilitated (a more cost effective and environmentally acceptable  
solution). The south decline development will commence in the next quarter.     
Project execution remains on track for Everest to be in a position to resume    
milling operations in the latter part of the first quarter of next financial    
year.                                                                           
Planning for the construction of the chromite spirals plant was finalised during
the quarter, and construction activities will commence during the next quarter. 
Commissioning of the spirals plant will coincide with the resumption of milling 
operations at Everest.                                                          
Capital Expenditure                                                             
The total re-establishment project capital (both Phase 1 and Phase 2, as        
previously announced) of R259 million will put Everest in a position to resume  
operations. Project expenditure to date is well within budget, at a total of    
R66.0 million.                                                                  
Offtake agreement signed with Glencore for chromite from Everest Plant          
An offtake agreement has been signed with Glencore International AG, for the    
purchase of the chromite produced by the chromite spirals plant currently under 
construction at Everest. The agreement has been concluded on commercially       
favourable terms and the revenue from the chromite by-product will contribute to
Everest`s margins.  The chromite plant is anticipated to have annual output of  
approximately 200,000 tonnes of UG2 chromite (40% Cr2O3) at steady state and    
will commence production in Q3 of calendar year 2011.                           
RIDGE MINING (PTY) LTD                                                          
Blue Ridge Mine (Aquarius Platinum - 50%)                                       
Safety                                                                          
-    A fatality tragically occurred on 15 December 2009                         
-    The 12-month rolling average DIIR for the half year was 1.09               
-    Preventative and remedial actions are being implemented to reverse the     
negative trend in safety performance                                            
Mining                                                                          
-    Underground operations produced 413,000 tonnes during the first half of    
2010                                                                            
-    Head grade was 2.48g/t                                                     
-    Stockpiles at the end of the period totalled 173,688 tonnes                
Processing                                                                      
-    605,000 tonnes of ore were processed at Blue Ridge during the first half   
-    Recoveries were 69%                                                        
-    PGM production in the period amounted to 33,067 ounces (Aquarius           
attributable:16,534 ounces)                                                     
Operations                                                                      
The ramp-up of production at Blue Ridge continues to progress satisfactorily.   
During the period under review the focus remained on primary development to open
ore reserves and available panels to increase production to steady state.       
Underground mining is progressing well, and stoping teams are being recruited   
and trained as stoping panels are being made available through the holing of    
additional raise lines.                                                         
The concentrator plant`s availability has increased steadily, with downtime     
mainly due to power interruptions as a result of lightning, redesign and re-    
engineering of the secondary mill from a grate discharge to an overflow         
discharge configuration as well as the installation of a new tailings pipeline. 
Improved process stability and process control resulted in average recoveries   
over the half of 69%, reflecting an improvement from 65% to 74% between Q1 2010 
and Q2 2010. Throughput for the half year was 605,000 tonnes.                   
The head grade averaged 2.48g/t over the period, slightly below expectations    
mainly as a result of development dilution and the processing of lower grade    
development stockpiles.                                                         
PGM production was 33,067 PGM ounces (Aquarius attributable 16,534 PGM ounces), 
and the Dollar basket price was $1,061 per PGM ounce for the period.            
Capital Expenditure                                                             
R54.0 million was spent on sustaining capital expenditure at Blue Ridge in the  
first six months of the 2010 financial year, and a further R157.2 million of    
expansionary capital expenditure was also incurred. Aquarius continues to       
capitalise costs and revenues associated with the ramp-up phase of Blue Ridge.  
MIMOSA INVESTMENTS LIMITED (Aquarius Platinum - 50%)                            
Mimosa Platinum Mine                                                            
Safety                                                                          
-    No fatal accidents during the period - Mimosa had achieved 2.2 million     
fatality-free shifts by the end of the half year                                
-    The 12-month rolling average DIIR improved from 0.18 to 0.14 for the period
- Mimosa retains the best safety record among the Aquarius operations           
Mining                                                                          
-    Underground mining production was flat at 1,068,000 tonnes                 
-    The surface stockpile decreased by 72.5% from the comparative period to    
146,000 tonnes                                                                  
Processing                                                                      
-    1,153,000 tonnes were processed at Mimosa in 1H 2010, an increase of 13.7% 
-    Average concentrator plant recoveries rose to 76%                          
-    Total mine production increased by 16.2% to 100,907 (Aquarius attributable:
50,454 PGM ounces)                                                              
Revenue                                                                         
The Dollar PGM basket price for the period averaged $859 per PGM ounce, a 28.2% 
decrease compared to 1H 2008, but a 24.7% increase compared to 2H 2009.  The    
average nickel price over the period was 9.1% lower at $7.59 per pound and      
copper was 14.0% higher at $2.58 per pound compared to the previous             
corresponding period.                                                           
As a result of increased PGM production and positive sales adjustments          
reflecting higher PGM prices late in the period, revenue from Mimosa for the    
first six months was $110 million, a 115.7% increase compared to the previous   
corresponding period despite lower average metals prices.                       
During the period mining operations remained consistent, hoisting 1,068,000     
tonnes, the same volume as in the previous corresponding period. Tonnes         
processed at Mimosa during the first half totalled 1,153,000, an increase of    
13.7%, despite a mill shutdown in December. The surface stockpile at the end of 
the period stood at 146,000 tonnes, a reduction of 72.5% compared to the prior  
period, as ore stocks were used to supplement mining volumes.                   
The average plant head grade for the period decreased slightly to 3.59 g/t,     
while recoveries improved to 76%. Mimosa`s PGM production for the period        
increased by 16.2% to 100,907 PGM ounces (Aquarius attributable: 50,454 PGM     
ounces).                                                                        
Operating Cash Costs                                                            
Cash costs for the period increased by 25.0% to $50 per ROM ton and by 21.3% to 
$569 per PGM ounce compared to the previous corresponding period.  Net of by-   
products, cash costs were $278 per PGM ounce. The cost increases relate largely 
to the continuing effects of the dollarization of the Zimbabwean economy.       
Mimosa Operating Costs                                                          
       4E               6E                   4E net of by-                      
       (Pt+Pd+Rh+Au)    (Pt+Pd+Rh+Ir+Ru+Au)  products (Ni, Cu&                  
Co)                                
Mimosa  $569 per PGM     $540 per PGE ounce   $161 per PGE ounce                
       ounce                                                                    
Capital Expenditure                                                             
Stay-in-business capital expenditure at Mimosa increased by 44.4% to a total    
for the period of $13 million (approximately $120 per PGM ounce). This          
consisted primarily of underground infrastructure establishment. All critical   
capital expenditure is up to date.                                              
Regulatory developments in Zimbabwe                                             
The Indigenization and Economic Empowerment Regulations - Statutory Instrument  
21 of 2010 - was published in the Zimbabwean Government Gazette in early        
February 2010. In terms of these regulations, foreign companies are required to 
localise or indigenize "51% of their shares or interests therein" within 5 years
in all business sectors.                                                        
The regulations provide for the gazetting within twelve months of further rules 
"with respect to each sector and subsector of the economy what lesser share than
the minimum indigenization and empowerment quota shall be the minimum lesser    
share that indigenous Zimbabweans may hold in a business operating in the sector
or subsector in question."                                                      
The regulations further provide "what weighting (expressed as a fixed percentage
that may be added towards the fulfillment of the minimum indigenization         
empowerment quota) to assign to anyone or more" of the "socially and            
economically desirable objectives in favour of a business operating in a        
specified sector or subsector of the economy."                                  
At the time of publication of this report, the Chamber of Mines of Zimbabwe on  
behalf of the mining sector was in closed discussions with relevant authorities 
with respect to finalizing the indigenization and empowerment quota for the     
mining industry.                                                                
Aquarius is studying the regulations and its formal response to compliance will 
be guided by advice from its subsidiary, Mimosa Mining Company (Pvt) Limited.   
Mimosa is a member of the Chamber of Mines of Zimbabwe.                         
As further information becomes available the market will be kept informed.      
AQUARIUS PLATINUM (SA) CORPORATE SERVICES (PTY) LTD                             
Chromite Tailings Retreatment Plant (CTRP) (Aquarius Platinum - 50%)            
Safety                                                                          
-    The DIIR for the period was 0                                              
Processing                                                                      
-    Feed processed was 142,000 tonnes, an increase of 18.3%                    
-    Average recoveries for the period decreased from 39% to 37%                
-    3,827 PGM ounces produced (Aquarius attributable: 1,913 PGM ounces)        
Revenue                                                                         
The Dollar PGM basket price for the period was $1,179 per PGM ounce, a decrease 
of 22.9% compared to 1H 2009 but an increase of 27.0% compared to 2H 2009.  The 
CTRP produces proportionately more rhodium than the other operations, which     
contributes to the higher basket prices achieved. As was the case at the other  
South African operations, the strengthening Rand and lower basket prices        
resulted in CTRP generating lower revenue initially, but the stabilising and    
subsequent increase in PGM prices during the half resulted in positive sales    
adjustments. As a result, revenue at CTRP increased by 133.3% to R28 million.   
Operations                                                                      
Processing plant feed increased by 18.3% 142,000 tonnes over the first half,    
while the head grade fell by 8.8% to 2.28 g/t. Recoveries also decreased, from  
39% to 37%.                                                                     
CTRP produced 3,827 PGM ounces (Aquarius attributable: 1,913 PGM ounces), a 7.8%
increase compared with the previous corresponding period.                       
Operating Costs                                                                 
Cash costs decreased by 13.1% to R3,105 per PGM ounce, equal to $406 per PGM    
ounce.                                                                          
           4E               6E                   6E net of by-                  
           (Pt+Pd+Rh+Au)    (Pt+Pd+Rh+Ir+Ru+Au)  products                       
CTRP        R 3,105 per PGM  R 2,121 per PGE      R 2,040 per PGE               
           ounce            ounce                ounce                          
PLATINUM MILE RESOURCES (PTY) LTD                                               
Platinum Mile (Aquarius Platinum - 50%)                                         
Safety                                                                          
-    The DIIR for the period was 0.                                             
Processing                                                                      
-    Milling expansion completed during the period, increasing the capacity and 
processing efficiency of the plant                                              
-    Feed processed was 4.0 million tonnes, a decrease of 13.0%                 
-    Average recoveries for the period were 15%                                 
-    14,471 PGM ounces produced (Aquarius attributable: 7,236 PGM ounces)       
Revenue                                                                         
The Dollar PGM basket price for the period was $1,166 per PGM ounce, an increase
of 38.6% compared to 1H 2009. Revenue at Platinum Mile increased by 55.4% to    
R115 million.                                                                   
Operations                                                                      
The Platinum Mile milling expansion has been completed, and is yielding the     
anticipated improvements in processing capacity and efficiency by enabling      
greater plant throughput and finer grinding.                                    
Processing plant feed decreased by 13.0% to 4.0 million tonnes over the first   
half, while the head grade fell by 12.5% to 0.63 g/t. Recoveries increased,     
however, from 9% to 15%.                                                        
Platinum Mile produced 14,471 PGM ounces (Aquarius attributable: 7,236 PGM      
ounces), a 59.3% increase compared with the previous corresponding period.      
Operating Costs                                                                 
Cash costs decreased by 26.5% to R2,490 per PGM ounce, equal to $333 per PGM    
ounce.                                                                          
4E                6E                  6E net of by-products           
          (Pt+Pd+Rh+Au)     (Pt+Pd+Rh+Ir+Ru+Au)                                 
Platinum   R 2,490 per PGM   -                   -                              
Mile       ounce                                                                
Statistics       Kroondal    Marikana P&SA2 CTRP             Everest            
                P&SA1                                                           
        Unit    6     6     6      6       6        6       6       6           
                mont  mont  months months  monthsD  months  months  month       
hsDe  hsDe  Dec    Dec     ec 2009  Dec     Dec     sDec        
                c     c     2009   2008             2008    2009    2008        
                2009  2008                                                      
Safety                                                                          
DIIR     Rate/2  0.63  0.77  1.08   0.70    0        4.80    -                  
        00,000                                                                  
        hrs                                                                     
Revenue                                                                         
Gross    Millio  1,54  841   553    303     28       12      -       226        
revenue  ns      9                                                              
PGM      $/oz    1,07  1,23  1,093  1,198   1,179    1,530   -       1,224      
basket           7     3                                                        
Price                                                                           
Gross    %       29    (31)  9      (89)    57       (5)     -       (89)       
cash                                                                            
margin                                                                          
Nickel   $/lb    7.99  6.76  7.99   6.76    7.99     6.76    -       6.76       
Price                                                                           
Copper   $/lb    2.84  2.63  2.84   2.63    2.84     2.63    -       2.63       
Price                                                                           
Ave R/$          7.65  8.79  7.65   8.79    7.65     8.79    -       8.79       
rate                                                                            
On Mine Cash Costs                                                              
Per ROM  R/ton   365   339   436    420     84       106     -       511        
ton                                                                             
        $/ton   48    39    57     48      11       12      -       58          
Per PGM  R/oz    5,54  5,20  7,386  7,038   3,105    3,572   -       6,686      
(3E+Au)          9     3                                                        
$/oz    725   592   965    801     406      406     -       761         
Per PGE  R/oz    4,54  4,26  6,130  5,780   2,121    2,447   -       5,471      
(5E+Au)          2     6                                                        
        $/oz    594   485   801    658     277      278     -       623         
Production                                                                      
Undergr  ton     3,11  3,48  761    740     -        -       -       839        
ound     `000s   3     3                                                        
Open     ton     0     18    420    700     -        -       -       -          
Pit      `000s                                                                  
Total    ton     3,11  3,50  1,181  1,440   142      120     -       839        
        `000s   3     1                                                         
Plant    g/t     2.60  2.57  2.67   2.87    2.28     2.50    -       2.89       
Head     PGM                                                                    
Recover  %       79    78    69     64      37       39      -       83         
ies                                                                             
Platinu  Ozs     116,  125,  42,353 50,375  2,315    2,155   -       37,64      
m                059   709                                           3          
Palladi  Ozs     58,5  61,7  18,876 22,342  844      792     -       19,36      
um               19    34                                            5          
Rhodium  Ozs     21,5  23,0  6,742  8,123   661      592     -       6,499      
16    09                                                        
Gold     Ozs     968   987   410    494     7        8       -       562        
Total    Ozs     197,  211,  68,381 81,333  3,827    3,548   -       64,06      
PGM              061   438                                           8          
(3E+Au)                                                                         
Iridium  Ozs     8,33  8,74  2,693  3,415   324      293     -       2,487      
                0     8                                                         
Rutheni  Ozs     35,3  37,7  11,312 14,285  1,452    1,339   -       11,74      
um               90    03                                            0          
Total    Ozs     240,  257,  82,387 99,034  5,603    5,179   -       78,29      
PGE              782   889                                           5          
(5E+Au)                                                                         
Nickel   Tons    216   215   89     118     5        5       -       122        
Copper   Tons    91    91    58     61      3        2               64         
Statistics                  Mimosa                Platinum Mile   Blue          
                                                                 Ridge          
Unit         6          6          6        6      6 months       
                           monthsDec  monthsDec  monthsD  months Dec 2009       
                           2009       2008       ec 2009  Dec                   
                                                          2008                  
Safety                                                                          
DIIR           Rate/200,00  0.14       0.18       0        0      1.09          
              0 hrs                                                             
Revenue                                                                         
Gross revenue  Millions     110        51         115      74     -             
PGM basket     $/oz         859        1,196      1,166    841    1,061         
Price                                                                           
Gross cash     %            42         20         40       43     -             
margin                                                                          
Nickel Price   $/lb         7.59       8.35       7.48     5.83   7.99          
Copper Price   $/lb         2.58       3.19       3.10     2.12   2.84          
Ave R/$ rate                -          -          7.48     8.83   7.62          
On Mine Cash Costs                                                              
Per ROM ton    R/ton        -          -          9        7      -             
              $/ton        50         40         1        1      -              
Per PGM        R/oz         -          -          2,490    3,387  -             
(3E+Au)                                                                         
              $/oz         569        469        333      384    -              
Per PGE        R/oz         -          -          2,108    2,920  -             
(5E+Au)                                                                         
$/oz         540        446        282      331    -              
Production                                                                      
Underground    ton `000s    1,068      1,068      -        -      413           
Open Pit       ton `000s    -          -          3,952    4,574  -             
Total          ton `000s    1,068      1,068      3,952    4,574  413           
Plant Head     g/t PGM      3.59       3.61       0.63     0.72   2.48          
Recoveries     %            76         74         15       9      69            
Platinum       Ozs          51,079     44,016     8,393    5,269  19,799        
Palladium      Ozs          38,806     33,540     4,486    2,817  9,837         
Rhodium        Ozs          4,108      3,523      1,303    817    3,109         
Gold           Ozs          6,915      5,790      289      183    322           
Total PGM      Ozs          100,907    86,870     14,471   9,086  33,067        
(3E+Au)                                                                         
Iridium        Ozs          3,578      2,962      -        -      1,133         
Ruthenium      Ozs          1,841      1,535      2,315    1,453  5,422         
Total PGE      Ozs          106,326    91,367     16,786   10,539 39,622        
(5E+Au)                                                                         
Nickel         Tons         1,400      1,217      67       54     -             
Copper         Tons         1,146      995        30       16     -             
Aquarius Platinum Limited                                                       
Incorporated in Bermuda                                                         
Exempt company number 26290                                                     
Board of Directors                                                              
Nicholas Sibley          Non-executive Chairman                                 
Stuart Murray            Chief Executive Officer                                
David Dix                Non-executive                                          
Timothy Freshwater       Non-executive                                          
Edward Haslam            Non-executive                                          
Sir William Purves       Non-executive                                          
Kofi Morna               Non-executive                                          
Zwelakhe Mankazana       Non-executive                                          
Audit/Risk Committee                                                            
Sir William Purves  (Chairman)                                                  
David Dix                                                                       
Edward Haslam                                                                   
Nicholas Sibley                                                                 
Remuneration/Succession Planning Committee                                      
Edward Haslam (Chairman)                                                        
David Dix                                                                       
Zwelakhe Mankazana                                                              
Nicholas Sibley                                                                 
Nomination Committee                                                            
The full Board comprises the Nomination Committee                               
Company Secretary                                                               
Willi Boehm                                                                     
AQPSA Management                                                                
Stuart Murray            Executive Chairman                                     
Hugo Holl                Managing Director                                      
Helene Nolte             Director: Finance                                      
Hulme Scholes            Commercial Director                                    
Anton Lubbe              Operations Director: West                              
Anton Wheeler            Operations Director: East                              
Graham Ferreira          General Manager: Group Admin & Company Secretary       
Mkhululi Duka            General Manager: Group Human Resources & Transformation
Abraham van Ghent        General Manager: Kroondal                              
Wessel Phumo             General Manager: Marikana                              
Gabriel de Wet           General Manager: Engineering                           
Augustine Simbanegevi    General Manager: Everest                               
Anthony Joubert          General Manager: Blue Ridge                            
ACS (SA) Management                                                             
Paul Smith               Director: New Business                                 
Mimosa Mine Management                                                          
Winston Chitando         Managing Director                                      
Herbert Mashanyare       Technical Director                                     
Peter Chimboza           Operations Director                                    
Fungai Makoni            Finance Executive & Company Secretary                  
Issued Capital                                                                  
At 31 December 2009, the Company had in issue:  462,491,685 fully paid common   
shares and 1,628,240 unlisted options.                                          
Substantial Shareholders 31       Number of     Percentage                      
December 2009                     Shares                                        
Savannah Consortium               68,658,728    14,85%                          
HSBC Custody Nominees (Australia  39,410,836    8.52%                           
Limited)                                                                        
JP Morgan Nominees Australia      28,149,935    6.09%                           
Limited                                                                         
Trading Information                                                             
ISIN number BMG0440M1284                                                        
ADR ISIN number US03840M2089                                                    
Convertible Bond ISIN number XS0470482067                                       
Broker (LSE) (Joint)  Broker (ASX)         Sponsor (JSE)                        
Liberum Capital       Euroz Securities     RAND MERCHANT BANK (A division       
Limited               Level 14, The        of FirstRand Limited)                
City Point, 1         Quadrant             cnr Rivonia Road & Fredman           
Ropemaker Street,     1 William Street,    Drive                                
London, EC2Y 9HT      Perth WA 6000        Sandton 2196                         
Telephone: +44 (0)    Telephone: +61 (0)8  Telephone:                           
20 3100 2000          9488 1400            +27 (0)11 282 8000                   

Bank of America                                                                 
Merrill Lynch                                                                   
2 King Edward St                                                                
London, EC1A 1HQ                                                                
Telephone: +44 (0)20                                                            
7628 1000                                                                       
Aquarius Platinum (South Africa) (Proprietary) Ltd                              
100% Owned                                                                      
(Incorporated in the Republic of South Africa)                                  
Registration Number 2000/000341/07                                              
1st Floor, Building 5, Harrowdene Office Park, Western Service Road, Woodmead   
2191, South AfricaPostal Address:  PO Box 76575, Wendywood, 2144, South Africa  
Telephone:     +27 (0)11 656 1140                                               
Facsimile:              +27 (0)11 802 0990                                      
Aquarius Platinum Corporate Services Pty Ltd                                    
100% Owned                                                                      
(Incorporated in Australia)                                                     
ACN 094 425 555                                                                 
Level 4, Suite 5, South Shore Centre, 85 The Esplanade, South Perth, WA 6151,   
Australia                                                                       
Postal Address PO Box 485, South Perth, WA 6151, Australia                      
Telephone:     +61 (0)8 9367 5211                                               
Facsimile:     +61 (0)8 9367 5233                                               
Email:         info@aquariusplatinum.com                                        
Glossary                                                                        
A$             Australian Dollar                                                
Aquarius       Aquarius Platinum Limited                                        
ABET           Adult Basic Education Training programme                         
APS            Aquarius Platinum Corporate Services Pty Ltd                     
AQPSA          Aquarius Platinum (South Africa) Pty Ltd                         
ACS (SA)       Aquarius Platinum (SA) (Corporate Services) (Pty) Limited        
BEE            Black Economic Empowerment                                       
CTRP Chromite Ore Tailings Retreatment Operation. Consortium comprising Aquarius
Platinum (SA) (Corporate Services) (Pty) Limited (ASACS), Ivanhoe Nickel and    
Platinum Limited and Sylvania South Africa (Pty) Ltd (SLVSA).                   
DIFR Disabling Injury Incidence Rate - being the number of lost-time injuries   
expressed as a rate per 1,000,000 man-hours worked                              
DIIR Disabling Injury Incidence Rate - being the number of lost-time injuries   
expressed as a rate per 200,000 man-hours worked                                
DME  South African Government Department of Minerals and Energy Affairs         
Dollar or $    United States Dollar                                             
EMPR           Environmental Management Programme Report                        
Everest        Everest Platinum Mine                                            
Great Dyke Reef     A PGE bearing layer within the Great Dyke Complex in        
Zimbabwe                                                                        
g/t  Grams per tonne, measurement unit of grade (1g/t = 1 part per million)     
JORC code Australasian code for reporting of Mineral Resources and Ore Reserves 
JSE            JSE Securities Exchange South Africa                             
Kroondal       Kroondal Platinum Mine or P&SA1 at Kroondal                      
LHD            Load Haul Dump machine                                           
Marikana       Marikana Platinum Mine or P&SA2 at Marikana                      
Mimosa         Mimosa Mining Company (Private) Limited                          
MRC            Murray & Roberts Cementation                                     
nm             Not measured                                                     
NOSA           National Occupational Safety Association                         
NUM            South African National Union of Mineworkers                      
PGE(s) (6E)    Platinum Group Elements plus Gold.  Five metallic elements       
commonly found together which constitute the platinoids (excluding Os (osmium)).
These are Pt (platinum), Pd (palladium), Rh (rhodium), Ru (ruthenium), Ir       
(iridium) plus Au (gold)                                                        
PGM(s) (4E)    Platinum Group Metals plus Gold.  Aquarius reports the PGMs as   
comprising Pt+Pd+Rh plus Au (gold) with the Pt, Pd and Rh being the most        
economic platinoids in the UG2 Reef                                             
P&SA1     Pooling & Sharing Agreement between AQPSA and RPM Ltd on Kroondal     
P&SA2     Pooling & Sharing Agreement between AQPSA and RPM Ltd on Marikana     
PMR            Platinum Mile Resources Pty Ltd                                  
R              South African Rand                                               
Ridge          Ridge Mining plc                                                 
ROM  Run of Mine.  The ore from mining which is fed to the concentrator plant.  
This is usually a mixture of UG2 ore and waste.                                 
RPM            Rustenburg Platinum Mines Limited                                
SavCon    The Savannah Consortium - the principal Black Empowerment Investor in 
Aquarius Platinum                                                               
TKO            TKO Investment Holdings Limited                                  
Ton            1 Metric tonne (1,000kg)                                         
UG2 Reef  A PGE bearing chromite layer within the Critical Zone of the Bushveld 
Complex                                                                         
For further information please visit www.aquariusplatinum.com or contact:       
In Australia                                                                    
Willi Boehm                                                                     
+61 (0) 8 9367 5211                                                             
In the United Kingdom and South Africa                                          
Gavin Mackay                                                                    
gavin.mackay@aquariusplatinum.com                                               
+ 44 7909 547 042                                                               
Date: 11/02/2010 10:14:03 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: