Not logged in
  Home   Markets   Shares   Funds   Portfolio   Toolbox   Charting   Alerts   Directory   
 Admin   

Fri 19 Feb 2010, 7:29 SIM - Simmers Report For The Quarter Ended 31 December 2009 (Q3 Fy2010)
SIM
SIIF                                                                            
SIM - Simmers Report For The Quarter Ended 31 December 2009 (Q3 Fy2010)         
Simmer & Jack Mines, Limited                                                    
(Incorporated in the Republic of South Africa)                                  
(Registration number 1924/007778/06)                                            
Share code: SIM                                                                 
ISIN Code: ZAE000006722                                                         
("Simmers" or the "company")                                                    
SIMMERS REPORT FOR THE QUARTER ENDED 31 DECEMBER 2009 (Q3 FY2010)               
SALIENT FEATURES                                                                
Post quarter-end resolution of shareholder dispute and appointment of           
independent board                                                               
Management roles for Simmer and Jack Mines Limited (Simmers) and First Uranium  
Corporation Limited (First Uranium) separated                                   
Cash operating profit of ZAR8 million compared to loss of ZAR29 million in Q2   
FY2010                                                                          
Produced 903 kilograms (kg) down from 1,036 kg in Q2 FY2010                     
Total cash costs decreased by 17% to ZAR230 million (Q2 FY2010: ZAR276 million) 
Revenue down 3% to ZAR238 million (Q2 FY2010: ZAR247 million)                   
Cash and cash equivalents of ZAR739 million which excludes the ZAR160 million   
credit loan facility granted to First Uranium) (ZAR787 million in Q2 FY2010)    
OPERATIONAL DEVELOPMENTS                                                        
At Buffelsfontein Gold Mine (Buffelsfontein):                                   
-    Gold production of 838.13 kg in line with guidance                         
-    Rationalisation process successfully completed                             
-    Total cash costs decreased by 16%                                          
-    Production from surface sources up 37%                                     
-    Underground grade up 9%                                                    
-    Five shaft rehabilitation project completed within budget                  
-    Opening-up and development operations to access the 77-level haulage pillar
has commenced                                                                   
At Tau Lekoa Mine (Tau Lekoa):                                                  
-    Period for completion of acquisition extended by six months                
to September 2010                                                               
-    Production exceeded Simmers` planned forecasts                             
-    Simmers` team in place and shadow-managing operations in anticipation of   
taking ownership of Tau Lekoa                                                   
-    Investigations of economic potential of Weltevreden ongoing                
-    De-watering of Weltevreden twin-decline 70% complete                       
-    Underground infrastructure revealed to be in good condition                
44 of 46 drill holes completed;                                                 
-    Phase 1 of the pre-feasibility study to be re-defined following results of 
the drill programme                                                             
-    Pre-feasibility study for Weltevreden project due in Q1 FY2011             
At Transvaal Gold Mining Estates (TGME):                                        
-    Excellent safety performance                                               
-    Total cash costs down by 21%                                               
-    Production from surface operations only                                    
-    Heavy and sustained rainfall impacts on leaching and operations            
-    Gold production down 11% to 65 kg                                          
POST PERIOD-END:                                                                
New, independent board with strong mining skills appointed at general meeting of
shareholders on Monday, 1 February 2010                                         
First meeting of new board held on Tuesday, 2 February 2010:                    
-    Vusi Khanyile appointed chairman                                           
-    Bernard Swanepoel appointed deputy chairman                                
-    Deon van der Mescht appointed Chief Executive Officer (CEO)                
-    Investment committee appointed to focus on optimising Simmers` investment  
in First Uranium                                                                
-    Buffelsfontein confident of showing a return to profitability in the last  
month of the fourth quarter (March 2010), following the successful completion of
the restructuring process                                                       
-    Renewed engagement with AngloGold Ashanti Limited (AngloGold Ashanti) and  
the Department of Mineral Resources (DMR) to expedite transfer of Tau Lekoa     
mining right                                                                    
-    Future of TGME under review                                                
STATEMENT BY THE CHIEF EXECUTIVE OFFICER                                        
The long running dispute with Simmers` largest shareholder and black economic   
empowerment (BEE) partner, Vulisango Holdings (Pty) Limited (Vulisango), has    
been resolved. On Monday, 1 February 2010, shareholders voted overwhelmingly in 
favour of a new board that had been agreed upon between Simmers and its two     
largest shareholders, Vulisango and Rand Merchant Bank (RMB). The board is      
independent, in line with the guidelines of the King Code of Corporate          
Governance III, and comprises significant mining expertise as well as valuable  
experience in the management of a public company.                               
This is welcome news for allSimmers stakeholders, notably Simmers` employees who
are keen to see management resume their focus on operational issues. The        
shareholder dispute has had an extremely negative effect on employee morale.    
Now that it has been resolved, my focus as the newly appointed CEO will be on   
improving internal communications, recognising and rewarding excellence within  
the organisation, and ensuring that staff are focused on delivering on our      
commitments to shareholders. Creating an environment in which people can excel  
and that will result in the achievement of goals, and ultimately the creation of
value for all stakeholders, will be a major part of my role as CEO. This means  
going back to basics and addressing core values around safety and well-being,   
costs and revenue. To address previous management inaccuracies which have       
created a perception of over- promising and under-delivery, we are in the       
process of reviewing the guidance protocol. All updated mine plans are          
currentlyundergoing a review process at mine level, prior to sign-off by the    
executive committee and the board to ensure the requisite buy-in and commitment 
to execution of plans. These updated technical reports will form the basis of   
our production guidance going forward. We have also instituted very specific    
operational changes in order to support and assist our senior production        
managers to meet their targets. This includes the establishment of a division to
handle the technical and support services required to run a mine successfully.  
Despite a challenging period there were some positive developments. Costs are   
going in the right direction and the focus at operational level is finally      
beginning to shift from tonnage to grade in our bid to mine profitable ounces,  
even if it means producing less gold. Buffelsfontein, which currently produces  
around 92% of Simmers` gold, will see a return to profitability in March 2010,  
barring unforeseen glitches.                                                    
Following the first board meeting of the new Simmers board on Tuesday, 2        
February 2010, the board formed an investment committee headed by deputy        
chairman, Bernard Swanepoel, to review Simmers` holding in First Uranium in the 
light of First Uranium`s recent disclosures on the Securities Exchange News     
Service SENS regarding the change to its production and capital schedule. The   
disclosures followed the withdrawal of its environmental permit to build a      
tailings storage facility (TSF) at its Mine Waste Solutions project (MWS). The  
investment committee is assessing the impact of the latest developments and will
advise the board accordingly. Simmers is willing and able to participate in the 
recapitalisation of First Uranium, subject to the value proposition being       
proven.                                                                         
At Tau Lekoa, we have reached agreement with AngloGold Ashanti to extend the    
interim contract period to September 2010 in order to accommodate any further   
delay in the permitting process. The terms of the acquisition agreement         
stipulate that any cash profit earned in the interim period will be deductable  
from the purchase price of ZAR600 million. The estimated cash profit for the    
2009 calendar year is expected to be in the region of ZAR100 million. This cash 
profit will continue to accumulate until the acquisition is completed.          
The integration of Tau Lekoa into Buffelsfontein continues as planned and       
Simmers, in co-operation with AngloGold Ashanti, will continue to shadow-manage 
operations at Tau Lekoa until the acquisition is completed.                     
At TGME results have been disappointing. The time has come to review the future 
of this operation in light of the ongoing financial losses incurred and the     
capital required to realise the prospective potential of TGME.  The operation is
consuming a disproportionate amount of management time and resources in relation
to its size. We therefore intend embarking on a consultative process in terms of
section 189a of the Labour Relations Act, 66 of 1995, to further restructure and
down-size this operation. This will allow us to focus on regional consolidation 
in the North West Province which is where we believe the best returns on our    
investment are to be found.                                                     
SALIENT FEATURES                                                                
Table 1 - Summary of group salient features                                     
Quarter                  Simmers                       YTD                      
Q3 FY2010   Q2 FY2010    Detail              Unit      FY2010       FY2009      
903         1,036        Gold produced       kg        2,965        2,978       
694,161     583,212      Tonnes milled       t         1,825,628    1,624,941   
263,761     238,248      Revenue             ZAR/kg    248,466      230,210     
254,972     266,345      Total cash costs    ZAR/kg    260,648      232,102     
321,937     323,777      Notional cash       ZAR/kg    311,785      265,198     
expenditure                                             
332         473          Total cash costs    ZAR/t     423          425         
7,939       (29,103)     Cash operating      ZAR`000   (36,120)     (5,636)     
                        profit/(loss)                                           
FINANCIAL OVERVIEW                                                              
Financial results for the year to date FY2009 and the year to date FY2010 are   
not comparable given the change in relationship between Simmers and First       
Uranium from that of a subsidiary to an associate company which took place at   
the end of Q4 FY2009. This change in accounting disclosure affects all the line 
items in the Statement of Comprehensive Income and Statement of Financial       
Position.                                                                       
As expected, total gold production was down 13% from 33,301 ounces (oz)         
(1,036kg) to 29,040 oz (903 kg) in Q3 FY2010. This was as a consequence of the  
shaft rationalisation process at Buffelsfontein and the shift in focus to       
profitable ounces. This translated into gold revenue of ZAR238 million, compared
to ZAR247 million in the previous quarter. Unit cash costs declined 4% from     
ZAR266,345/kg to ZAR254,972/kg.                                                 
The bottom-line loss before taxation narrowed by 25% from ZAR147 million for Q3 
FY2010 to ZAR110 million for the period under review. Costs were reduced by     
ZAR45.6 million, due to decreased gold production and a decrease in unit costs. 
Dealing with our two operations separately, at Buffelsfontein revenue was down  
4% from ZAR229 million to ZAR221 million as a result in a reduction in ounces.  
The ZAR26 million operating loss in Q2 FY2010 was converted into an operating   
profit of ZAR7 million in Q3 FY2010 on the back of the stronger ZAR/kg gold     
price and a 16% decrease in total cash costs, from ZAR248 million in Q2 FY2010  
to ZAR208 million.  The ZAR40 million reduction in total cash costs was         
partially the result of a 38% drop in electricity costs. In addition the        
rationalisation programme achieved real costs savings in labour, consumables,   
contractors and suspending production from unprofitable areas. These measures,  
combined with the higher volumes from the high grade Number 5 shaft improved    
underground grades by 9%.                                                       
Gold revenue for TGME decreased quarter-on-quarter from ZAR17.3 million to      
ZAR17.2 million due to a volume decrease of 8 kg as a result of the suspension  
of underground operations during July 2009 which was mitigated by an 11%        
increase in the ZAR/kg gold price. The reduced volumes created a revenue        
variance of ZAR2 million, quarter-on-quarter, and the increased gold price had a
positive effect of ZAR1.9 million on total revenue.                             
Overall gold production showed no significant change year-on-year at a total of 
95,335 ounces (oz) (2,965kg). Due to an improved exchange rate, gold revenue was
up 7% from ZAR686 million to ZAR737 million. Total cash costs rose 17% from     
ZAR691 million to ZAR773 million. The cash operating loss widened from          
ZAR6 million to ZAR36 million.                                                  
As at 31 December 2009, Simmers reported total assets of ZAR4.1 billion, total  
liabilities of ZAR561 million, shareholders` equity of ZAR3.5 billion and cash  
and cash equivalents of ZAR739 million, compared to ZAR787 million at the end of
Q2 FY2010. Cash and cash equivalents exclude the ZAR160 million facility to     
First Uranium which was granted by Simmers to First Uranium in Q2 FY2010.       
OPERATIONAL REVIEW                                                              
Safety                                                                          
It is with regret that Buffelsfontein reported the death of one employee during 
the quarter. Mr Simphiwe Mbotho of Bizana in the Eastern Cape died on 16        
November 2009 following injuries sustained by a falling rock on 4 November 2009.
Simmers remains committed to zero harm and to upholding the safest possible     
working environment. Our greatest sympathies are with the family and friends of 
Mr Mbotho.                                                                      
Buffelsfontein                                                                  
Buffelsfontein produced 26,947 oz (838 kg) in Q3 FY2010; a 13% decrease on the  
30,961 oz (963 kg) of gold produced in Q2 FY2010. The rationalisation process   
initiated at the end of August 2009, was completed in the third quarter and cost
savings have been achieved. As expected, production fell by 13% quarter-on-     
quarter due to reduced tonnage as part of the shaft rationalisation programme   
aimed at reducing total cash costs by suspending production from unprofitable   
areas. In total, Buffelsfontein produced 26,947 oz (838 kg) of gold compared to 
30,961 oz (963 kg) produced in Q2 FY2010.                                       
TGME                                                                            
At TGME gold production was down 255 oz (7.9 kg) quarter-on-quarter due to the  
suspension of underground operations in Q2 FY2010, and abnormally high rain fall
during November 2009 and the first half of December 2009. This resulted in      
dilution of the leach pad solution and interruptions to the tramming and        
crushing operations in the plant.                                               
At Elandsdrift Heap Leach Pad (HLP) production increased by 286 oz (8.9 kg) from
599 oz (18.6kg) to 885 oz (27.5kg) but was below forecast by 305 oz (9.5kg) due 
to the dilution effect of the excessive rain. The top of the HLP has been       
covered with a high-density polyethylene (HDPE) lining to divert excess rain    
from the pad.                                                                   
Gold production from the rock dumps and other sources increased by 276 oz       
(8.6kg) from 932 oz (29kg) to 1,208 oz (37.6 kg) but was 643 oz (20kg) below    
guidance. This was due to the excessive rain which resulted in 14 days lost     
where no screening could be done at the sites, five days where no tramming of   
the screened material could be done and numerous plant stoppages.               
Weltevreden                                                                     
Simmers earlier announced a multi-staged approach to the development of the     
Weltevreden resource with the aim of progressively funding development from     
internal cash resources.                                                        
During Q3, all assay results for phase one of the Weltevreden scoping study were
subjected to internal resource modelling by Simmers, which reduced the mineable 
area within phase one by 70%. As a result, the scoping study has been revised   
from positive to negative for the area initially deemed to comprise phase one.  
A total of 44 of the 46 drill holes planned for the entire Weltevreden project  
had been completed by the end of Q3. The remaining two drill holes will be      
completed in the current quarter and assay results for the remaining holes      
outside of the area defined as phase one are expected towards the middle of Q4. 
Once all results are received, the Weltevreden mineral resource will be         
remodelled and trade-offs conducted to determine the optimal method of accessing
the economic mineral resources.                                                 
It is anticipated that a pre-feasibility report on the entire Weltevreden       
project (comprising various phases) will be completed by the end of Q1 FY2011.  
Depending on the outcome, the pre-feasibility report will be followed by a      
definitive feasibility report.                                                  
Table 2 - Simmers` selected financial information                               
Simmers                               Q3 FY2010     Q2 FY2010      Variance Q3  
                                                                  v Q2          
Selected financial information        ZAR`000       ZAR`000        %            
                                                                                
Statement of comprehensive income                                               
                                                                                
Revenue                               238,240       246,774        (3%)         
Total cash cost                       (230,301)     (275,877)      17%)         
Production-related depreciation       (11,142)      (10,936)       (2%)         
Operating profit/(loss) from mining                                             
activities                            (3,204)       (40,039)       92%          
Non-production related depreciation   (1,515)       (1,508)        (0%)         
Other income                          2,787         1,842          51%          
Restructuring costs                   (4,770)       (3,089)        (54%)        
Share option costs                    (6,129)       (9,118)        33%          
General administrative and overhead                                             
expenditure                           (27,267)      (26,792)       (2%)         
(Loss) from operations before                                                   
interest and taxation                 (40,098)      (78,704)       49%          
Fair value adjustments & impairments                                            
133           482            72%           
Share in profit/(losses) from                                                   
associate investments                 (101,670)     (97,563)       (4%)         
Finance income & dividends            36,770        32,149         (14%)        
Finance charges                       (5,298)       (3,208)        (65%)        
Profit/(loss) before taxation         (110,164)     (146,844)      25%          
                                                                                
Statement of financial position                                                 

Total assets                          4,099,423     4,200,722      (2%)         
Cash and cash equivalents             738,675       787,423        (6%)         
Investments in and loans to                                                     
associates                            2,166,296     2,245,833      (4%)         
Current liabilities                   (130,767)     (158,833)      18%          
Non-current liabilities               (430,646)     (430,916)      0%           
Total equity                          (3,538,010)   (3,610,974)    (2%)         

(Continued)                                                                     
Simmers                                             YTD FY2010    YTD FY2009    
                                                   ZAR`000       ZAR`000        
Selected financial information                                                  
                                                                                
Statement of comprehensive income                                               
                                                                                
Revenue                                             736,768       964,580       
Total cash cost                                     (772,887)     (896,827)     
Production-related depreciation                     (32,274)      (20,993)      
Operating profit/(loss) from mining activities      (68,394)      46,761        
Non-production related depreciation                 (4,358)       (7,506)       
Other income                                        7,626         10,244        
Restructuring costs                                 (7,859)       -             
Share option costs                                  (24,232)      (101,155)     
General administrative and overhead expenditure     (71,908)      (164,050)     
(Loss) from operations before interest and          (169,125)     (215,705)     
taxation                                                                        
Fair value adjustments & impairments                1,096         (4,232)       
Share in profit/(losses) from associate             (147,200)     -             
investments                                                                     
Finance income & dividends                          127,839       52,225        
Finance charges                                     (46,731)      (123,302)     
Profit/(loss) before taxation                       (234,121)     (291,015)     
                                                                                
Statement of financial position                                                 
                                                                                
Total assets                                        4,099,423     4,470,194     
Cash and cash equivalents                           738,675       430,411       
Investments in and loans to associates              2,166,296     -             
Current liabilities                                 (130,767)     (716,839)     
Non-current liabilities                             (430,646)     (1,647,979)   
Total equity                                        (3,538,010)   (2,105,377)   
                                                                                
* Cash and cash equivalents exclude the ZAR160 million facility by Simmers to   
First Uranium but includes the ZAR450 million which is restricted cash against  
the guarantee in favour of AngloGold Ashanti for the purchase of Tau Lekoa.     
Table 3 - Simmers` quarterly group variance analysis                            
Revenue variance                                                                
Period             kg                  Price ZAR/kg        Revenue ZAR`000      
Q3 FY 2010         903                 263,761             238,240              
Q2 FY 2010         1,036               238,245             246,774              
Total              (133)               25,514              (8,534)              

Period             Volume variance     Price variance      Revenue variance     
                  R`000               R`000               R`000                 
Q3 v Q2            (34,961)            26,427              (8,534)              
(Continued)                                                                     
Cash cost variance                                                              
Period          kg              Cost ZAR/kg     Cash cost       Total           
                                                               variance         
ZAR`000         ZAR`000          
Q3 FY 2010      903             254,972         230,301         7,939           
Q2 FY 2010      1,036           266,342         275,877         (29,103)        
Total           (133)           (11,370)        (45,576)        37,042          

Period          Volume          Unit cost       Cost variance   Total           
               variance        variance                        variance         
               ZAR`000         ZAR`000         ZAR`000         ZAR`000          
Q3 v Q2         (33,799)        (11,777)        (45,576)        37,042          
* Total cash costs are costs directly related to the physical activities of     
producing gold and include mining costs, administrative costs; royalties, on-   
mine drilling expenditures that are related to production and other direct      
costs. Sales of by-product metals are deducted from the above in computing cash 
costs. Cash costs exclude depreciation, depletion and amortisation, corporate   
general and administrative expense, exploration costs, interest costs, and pre- 
feasibility costs and accruals for mine reclamation but include central costs   
such as human resources, technical services etc.                                
BUFFELSFONTEIN GOLD MINES LIMITED (BGM or Buffelsfontein)                       
Buffelsfontein is a wholly-owned subsidiary of Simmers, located in the          
Klerksdorp Goldfield of the Witwatersrand basin, some 160 kilometres (km) south-
west of Johannesburg and exploits the Vaal Reef conglomerate for its gold       
production. The current focus is on the regional integration of Tau Lekoa into  
Buffelsfontein.                                                                 
Table 4 - Summary of Buffelsfontein salient features                            
BGM                         UNIT        Q3 FY2010    Q2 FY2010    Variance Q3   
                                                                 v Q2           
Gold produced               Kg          838          963          (13%)         
Tonnes milled               t           677,991      579,171      17%           

Revenue                     ZAR`000     220,994      229,434      (4%)          
Total cash costs            ZAR`000     208,455      248,134      16%           
Capex                       ZAR`000     44,412       36,695       (21%)         
Notional cash expenditure   ZAR`000     252,866      284,829      11%           
                                                                                
Revenue                     ZAR/kg      263,676      238,252      11%           
Toatal cash costs           ZAR/kg      248,714      257,670      3%            
Capex                       ZAR/kg      52,989       38,105       (39%)         
Notional cash expenditure   ZAR/kg      301,703      295,775      (2%)          
(Continued)                                                                     
BGM                              UNIT           YTD FY2010       YTD FY2009     
Gold produced                    Kg             2,721            2,758          
Tonnes milled                    t              1,791,824        1,584,588      
                                                                                
Revenue                          ZAR`000        676,035          633,764        
Total cash costs                 ZAR`000        685,057          604,576        
Capex                            ZAR`000        100,512          65,065         
Notional cash expenditure        ZAR`000        785,569          669,641        
                                                                                
Revenue                          ZAR/kg         248,462          229,813        
Toatal cash costs                ZAR/kg         251,778          219,230        
Capex                            ZAR/kg         36,941           23,594         
Notional cash expenditure        ZAR/kg         288,719          242,823        
Table 5 - Summary of salient production metrics for Buffelsfontein              
BGM                              Unit    Q3 FY2010     Q2 FY2010    Variance    
                                                                   Q3 v Q2      
Face length (Ave)                m       1,354         1,694        (20%)       
Face advance (Ave)               m       10            11           (9%)        
Stoping m2 broken                m2      40,966        56,137       (27%)       
Development                      m       1,031         1,734        (41%)       
Opening-up (All)                 m       2,854         5,208        (45%)       

Tonnes milled           U/G      t       178,488       243,396      (27%)       
Yield per tonne         U/G      g/t     3.74          3.45         9%          
Gold produced           U/G      kg      668           839          (20%)       
oz      21,483        26,966       (20%)        
                                                                                
Tonnes milled           Surf     t       499,503       335,775      49%         
Yield per tonne         Surf     g/t     0.34          0.37         (8%)        
Gold produced           Surf     kg      170           124          37%         
                                oz      5,463         3,994        37%          
                                                                                
Total tonnes milled              t       677,991       579,171      17%         
Total yield per tonne            g/t     1.24          1.66         (26%)       
Total gold produced              kg      838           963          (13%)       
                                oz      26,947        30,961       (13%)        
(Continued)                                                                     
BGM                                        Unit      YTD FY2010    YTD FY2009   
Face length (Ave)                          m         1,579         1,771        
Face advance (Ave)                         m         10.42         9.39         
Stoping m2 broken                          m2        148,332       149,708      
Development                                m         4,579         5,273        
Opening-up (All)                           m         11,906        15,588       
                                                                                
Tonnes milled              U/G             t         638,099       657,353      
Yield per tonne            U/G             g/t       3.61          3.61         
Gold produced              U/G             kg        2,305         2,371        
                                          oz        74,108        76,229        
                                                                                
Tonnes milled              Surf            t         1,153,725     927,235      
Yield per tonne            Surf            g/t       0.36          0.42         
Gold produced              Surf            kg        416           387          
                                          oz        13,370        12,442        

Total tonnes milled                        t         1,791,824     1,584,588    
Total yield per tonne                      g/t       1.52          1.74         
Total gold produced                        kg        2,721         2,758        
oz        87,478        88,672        
Further costs savings are expected to be achieved once Tau Lekoa is integrated  
into Buffelsfontein. This was expected to have taken place by 1 January 2010,   
but has been deferred due to the transfer of the mining right not yet having    
been approved by the DMR. The cut-off date provided for in the acquisition      
agreement has therefore been extended by mutual agreement until 30 September    
2010, to allow sufficient time for the mining right transfer to take place.     
As part of the shaft rationalisation process aimed at reducing overhead costs,  
the Numbers 9 and 12 shafts were closed and activities previously associated    
with these shafts are now routed via Number 10 shaft. In Q3 FY2010, the low-    
grade Number 8 shaft was put on care-and-maintenance and low-grade areas of the 
Number 7 shaft were closed. These measures, combined with the higher volumes    
from the high grade Number 5 shaft, improved underground grades by 9%.          
The shaft rationalisation process reduced underground tonnage quarter-on-quarter
by 27%, resulting in a 20% decrease in gold recovered from underground.         
The 49% increase in tonnage milled from surface sources and the 37% increase in 
gold recovered is as a direct result of the mini float project which was        
commissioned in the second quarter. However, a drop in grade in the Number 10   
shaft waste rock dump reduced the recovered surface grade by 8%.                
Buffelsfontein capital projects                                                 
The highlight of the third quarter was the completion of the rehabilitation     
project to restore the high grade Number 5 shaft to full operational capacity.  
The final leg of the three-phase project which commenced in July 2008, was      
completed at the end of October 2009, with the completion of the Number 5 shaft 
ore-handling project, which introduced an efficient ore-handling system and the 
commissioning of the Number 5A sub-vertical shaft refrigeration project in      
September 2009.                                                                 
The Number 7 box on 29 level has since been installed and commissioned and the  
development of the 72 level X/belt winze is nearing completion. This will       
accelerate opening-up operations towards the 72-level North ore reserve         
extension.                                                                      
Following the commissioning of the refrigeration plant, the opening-up and      
development operations on 77-level to access the 77-level haulage pillar has    
commenced.                                                                      
Financials                                                                      
Q3 FY2010 v Q2 FY2010                                                           
Buffelsfontein produced 26,947 oz (838 kg) in Q3 FY2010, a 13% decrease on the  
30,961 oz (963 kg) of gold produced in Q2 FY2010. Revenue was down 4% from      
ZAR229 million to ZAR221 million.  Of the ZAR8.4 million decrease in revenue,   
ZAR32.9 million is due to decreased volumes (4,014 oz or 124.86 kg less gold    
produced in Q3 FY2010) while ZAR24.5 million was due to a 10.7% increase in the 
South African rand gold price per kilogram.                                     
Table 6 - Quarter variance analysis for Buffelsfontein                          
Revenue variance                                                                
Period             kg                  Price ZAR/kg        Revenue ZAR`000      
Q3 FY 2010         838                 263,676             220,994              
Q2 FY 2010         963                 238,252             229,434              
Total              (125)               25,424              (8,440)              

Period             Volume variance     Price variance      Revenue variance     
                  ZAR`000             ZAR`000             ZAR`000               
Q3 v Q2            (32,923)            24,483              (8,440)              
(Continued)                                                                     
Cash cost variance                                                              
Period         kg              Cost ZAR/kg     Cash cost       Total            
                                                              variance          
ZAR`000         ZAR`000           
Q3 FY 2010     838             248,714         208,455         12,540           
Q2 FY 2010     963             257,670         248,134         (18,700)         
Total          (125)           (8,956)         (39,679)        31,240           

Period         Volume          Unit cost       Cost variance   Total            
              variance        variance                        variance          
              ZAR`000         ZAR`000         ZAR`000         ZAR`000           
Q3 v Q2        (31,055)        (8,625)         (39,679)        31,240           
The ZAR19 million cash operating loss in Q2 FY2010 was converted into a cash    
operating profit of ZAR13 million in Q3 FY2010 on the back of the stronger      
ZAR/kg gold price (ZAR263,676/kg v ZAR238,252/kg) and a 16% decrease in total   
cash costs, from ZAR248 million (US$1,024/oz) in Q2 FY2010 to ZAR208 million    
(US$1,029/oz).  The ZAR40 million reduction in total cash costs was partially   
the result of a ZAR18 million or 38% drop in electricity costs following Eskom`s
switch from higher winter rates at the end of Q2 to its summer rates and,       
partially as a result of the rationalisation programme which achieved the       
following costs savings:                                                        
a ZAR20 million decrease in labour costs (17.5%);                               
consumables cut by ZAR5.4 million or 11%; and                                   
contractor costs cut by ZAR8.3 million or 23% (mainly as a result of the mini   
float project that made the screening of material associated with the Number 10 
waste rock dump superfluous).                                                   
The lower expenditure was partially offset by the decrease in gold inventory    
from 1,217 oz (37.85 kg) in Q2 to 635 oz (19.74 kg) at the end of Q3 FY2010 by  
ZAR1.3 million.                                                                 
Buffelsfontein`s capital expenditure increased from ZAR37 million in Q2 FY2010  
to ZAR44 million in Q3 FY2010. The main additions to fixed assets include       
ZAR19 million for the integration of Tau Lekoa, ZAR11.7 million expenses        
capitalised on the Weltevreden project, ZAR3.8 million for development and      
opening-up to increase flexibility of mineable face length, ZAR1.8 million      
toward the refurbishment of Number 5 shaft with a further ZAR1.2 million on     
Number 5 shaft refrigeration plant, ZAR1 million on compressor repairs, and     
ZAR3.2 million on the mini float and mini float B bank project to optimise the  
plant to its fullest capacity to be able to treat 240,000 tonnes per month.     
Year-to-date FY2010 v year-to-date FY2009                                       
Underground production declined marginally from 88,663 oz (2,758 kg) to         
87,478 oz (2,721 kg) due to a 11% and 1% decrease in face length and stoping    
square meters (m2) broken respectively. Recovered yield however, was up by 9%.  
Table 7 - Statement of Comprehensive Income for Buffelsfontein                  
BGM                                     Q3 FY2010    Q2 FY2010     Variance     
                                                                  Q3 v Q2       
Selected Financial information          ZAR`000      ZAR`000       %            
Statement of comprehensive income                                               
Revenue                                 220,994      229,434       (4%)         
Total cash cost                         (208,455)    (248,134)     16%          
Production-related depreciation         (5,684)      (7,349)       23%          
Operating profit/(loss) from mining                                             
activities                              6,855        (26,049)      126%         
Other income                            2,782        1,834         52%          
Restructuring costs                     (4,025)      (57)          (6964%)      
Share option costs                      (2,321)      (3,588)       35%          
General administrative and overhead                                             
expenditure                             (6,970)      (7,220)       3%           
(Loss) from operations before interest                                          
and taxation                            (3,678)      (35,079)      90%          
Fair value adjustments & impairments    133          482           72%          
Finance income & dividends              3,266        3,265         0%           
Finance charges                         8,978        (8,231)       209%         
Profit/(loss) before taxation           8,698        (39,563)      122%         

                                                                                
(Continued)                                                                     
BGM                                                YTD FY2010    YTD FY2009     
Selected financial information                     ZAR`000       ZAR`000        
Statement of comprehensive income                                               
Revenue                                            676,035       633,764        
Total cash cost                                    (685,057)     (604,576)      
Production-related depreciation                    (19,637)      (13,093)       
Operating profit/(loss) from mining activities     (28,659)      16,095         
Other income                                       6,140         4,339          
Restructuring costs                                (4,082)       -              
Share option costs                                 (9,284)       (17,324)       
General administrative and overhead expenditure    (24,161)      (23,404)       
(Loss) from operations before interest and                                      
taxation                                           (60,046)      (20,295)       
Fair value adjustments & impairments               1,096         -              
Finance income & dividends                         9,780         15,282         
Finance charges                                    45,517        (38,689)       
Profit/(loss) before taxation                      (3,652)       (43,702)       
Buffelsfontein generated gold revenues of ZAR676 million for the nine months    
ended December 2009 compared to ZAR634 million for the equivalent period in the 
previous financial year. The ZAR42 million increase in revenue was a direct     
result of an 8% improvement in the ZAR/kg gold price to the value of            
ZAR51.5 million, which was offset by ZAR9.2 million due to the lower gold       
production.                                                                     
Total cash costs increased by 13% from ZAR605 million (US$801/oz) for the nine  
months in FY2009 to ZAR685 million (US$985/oz). This ZAR80 million increase is  
as a result of higher unit costs which were affected by two increases in the    
cost of electricity: a 13.3% annual increase effective as of 1 January 2009 and 
a 31.3% increase on the standard tariff with effect from 1 July 2009. In        
addition, the two year wage increase concluded with organised labour increased  
the labour bill by ZAR28 million for the nine month period.                     
As a result of year-to-date cash costs rising from ZAR605 million to            
ZAR685 million and revenue increasing from ZAR634 million to ZAR676 million,    
Buffelsfontein`s operating loss from mining activities widened from a profit of 
ZAR16 million to a loss of ZAR29 million for the year-to-date. The current      
rationalisation programme is designed to reverse this loss-making situation.    
Table 8 - Year-to-date variance analysis for Buffelsfontein                     
Revenue variance                                                                
Period                kg                Price ZAR/kg      Revenue ZAR`000       
FY2010 YTD            2,721             248,462           676,035               
FY2009 YTD            2,758             229,791           633,764               
Total                 (37)              18,671            42,271                

Period                Volume variance   Price variance    Revenue variance      
                     ZAR`000           ZAR`000           ZAR`000                
FY2010 v FY2009       (9,223)           51,493            42,271                
(Continued)                                                                     
Cash cost variance                                                              
Period         kg             Cost ZAR/kg     Cash cost        Total variance   
                                             ZAR`000          ZAR`000           
Q3 FY 2010     2,721          251,778         685,057          (9,022)          
Q2 FY 2010     2,758          219,208         604,576          29,188           
Total          (37)           32,570          80,481           (38,210)         
                                                                                
Period         Volume         Unit cost       Cost variance    Total variance   
              variance       variance        ZAR`000          ZAR`000           
              ZAR`000        ZAR`000                                            
Q3 v Q2        (9,346)        89,827          80,481           (38,210)         
Outlook Q4 FY2010                                                               
In Q4 FY2010, Buffelsfontein expects to produce between 23,800 oz (740kg) and   
25,700 oz (800kg) at average cash costs of around US$1,090/oz and ZAR270,000/kg,
assuming an average exchange rate of ZAR7.70 to the US$, assuming the           
integration of Tau Lekoa does not take place in the fourth quarter.             
TAU LEKOA MINE (Tau Lekoa)                                                      
On 17 February 2009, Simmers announced the acquisition of AngloGold Ashanti`s   
Tau Lekoa mine near Orkney in the North West Province. At the time, it was      
anticipated that the earliest effective date for the completion of the          
acquisition would be on or about 1 January 2010. However, the acquisition       
agreement did contemplate a possible cut-off date of 31 March 2010 which could  
be extended by agreement between Simmers and AngloGold Ashanti.                 
As at 31 December 2009, all suspensive conditions to the acquisition save for   
the approval of the DMR for the transfer of the applicable mining rights had    
been fulfilled. The application for the transfer was submitted to the DMR during
Q2 FY2010 and DMR approval is now expected to occur during 2010.                
As a consequence, the parties have mutually agreed to extend the agreement to 30
September 2010, in order to accommodate any further delay in the permitting     
process.                                                                        
The integration of Tau Lekoa into Buffelsfontein is expected to reduce total    
costs at Tau Lekoa by approximately 20%, which equates to around ZAR100 million 
per annum.                                                                      
An updated life of mine (LOM) plan for the project has been completed and is    
undergoing independent verification and a peer review process, whereupon it will
be published.                                                                   
In addition to providing substantial free cash inflow to Buffelsfontein over the
next three years, the acquisition also includes the Weltevreden resource, a     
shallow, up-dip extension of Tau Lekoa lying between 80 and 300 metres below    
surface. Development of this 2.3 million ounce resource will significantly      
extend the life of the Tau Lekoa operation to 2024.                             
Production update                                                               
Tau Lekoa exceeded production expectations and declared 33,565 oz (1,044kg) of  
gold for the quarter. For the next quarter (Q4 FY2010), Tau Lekoa expects to    
produce between 30,000 oz (933kg) and 32,500oz (1,020kg). Upon the integration  
of Tau Lekoa with Buffelsfontein, cash costs are expected to be between         
ZAR180,995/kg and ZAR200,000/kg                                                 
Tau Lekoa capital projects                                                      
Weltevreden                                                                     
Simmers earlier announced a multi-staged approach to the development of the     
Weltevreden resource with the aim of progressively funding development from     
internal cash resources.                                                        
Phase one of the project was selected on the basis that the area under          
consideration did not require additional deepening of the decline and could     
provide access to the Ventersdorp Contact Reef (VCR) along a strike length of   
4,000 metres (m) from 160 m below surface to 300 m below surface. Additionally, 
95% of the mineable area within phase one contained the higher grade Middle     
Terrace Conglomerate (MTC) facies.                                              
Drilling programme                                                              
A scoping study using the AngloGold Ashanti mineral resources, geological       
structure and sedimentological facies models for Weltevreden, indicated that the
area had economic potential. Since the majority of the Weltevreden mineral      
resource was classified as an indicated three resource by AngloGold Ashanti, the
mineral resources had to be upgraded to a more acceptable measured or indicated 
resource level.  As part of the due diligence process, a 46 hole surface        
exploration programme was initiated at the end of Q2 FY2010 with the intention  
of reducing the gaps in the existing surface drill hole footprint and upgrading 
the level of confidence in the mineral resources. The area defined as phase one 
had a total of 19 surface drill holes within its limits.                        
During Q3 FY2010, all assay results for phase one were subjected to internal    
resource modelling by Simmers, which reduced the mineable area within phase one 
by 70%. As a result, the scoping study has been revised from positive to        
negative for the area initially deemed to comprise phase one.                   
Forty four of the 46 drill holes planned for the entire Weltevreden project had 
been completed by the end of Q3FY2010. The remaining two drill holes will be    
completed in the current quarter and assay results for the remaining holes      
outside of the area defined as phase one are expected towards the middle of Q4  
FY2010. Once all results have been received, the Weltevreden mineral resource   
will be remodelled and trade-offs conducted to determine the optimal method of  
accessing the economic mineral resources.                                       
The pre-feasibility report for phase one, which was due for release in the      
middle of Q3, will therefore be delayed until completion of the surface drilling
program and the completion of a South African Mineral Resource Committee        
(SAMREC) and National Instrument 43-101 (NI 43-101) compliant technical report  
on the updated mineral resources of the Weltevreden project.                    
It is anticipated that a pre-feasibility report on the entire Weltevreden       
project (comprising various phases) will be completed by the end of Q1 FY2011.  
Depending on the outcome, the pre-feasibility report will be followed by a      
definitive feasibility report.                                                  
Dewatering programme                                                            
Two hundred mega-litres of water were removed from the flooded twin decline     
system in Q3 FY2010. By the end of December 2009, the water level had dropped to
50m below Lateral Number 12, which equates to 70% of the decline system.  Weekly
water sampling to assess pH, electrical conductivity and total dissolved solids,
was conducted and showed no anomalies.                                          
With dewatering came the need to increase safety procedures. A baseline risk    
assessment was completed for the Weltevreden project and an issue based risk    
assessment was conducted to operate an load haul dump (LHD) and Landcruiser down
to Lateral Number 8. Gas testing equipment and a lamp room (with tester) were   
commissioned while two surface 45 kilowatt fans were installed on top of the up-
cast ventilation shaft. Two ventilation doors have been installed in the raw    
decline and two "physicals audits" were also conducted.                         
With the removal of the reeds and mud from the portal entrance, the crew were   
able to clean and wash the portal area of all mud and dirt. Security gates were 
installed and the Banksman`s cabin erected at the entrance to the portal.       
TRANSVAAL GOLD MINING ESTATES LIMITED (TGME)                                    
Overview                                                                        
TGME is situated in the Sabie/Pilgrim`s Rest goldfield of Mpumalanga,           
approximately 450 km north-east of Johannesburg. The current project area       
extends over a distance of approximately 70 km north-south and 25 km east-west  
and more than 40,000 hectares (ha) of new order prospecting rights (NOPR) and   
10,800 ha of new order mining rights (NOMR) have been secured. In FY2009, it    
accounted for 7% of Simmers` gold production.                                   
Table 9 - Summary of TGME salient features                                      
TGME                        Unit      Q3 FY2010    Q2 FY2010     Variance Q3    
v Q2            
Gold produced               kg        65           73            (11%)          
Tonnes milled               t         -            4,041         (100%)         
                                                                                
Revenue                     ZAR`000   17,245       17,340        (1%)           
Total cash costs            ZAR`000   21,846       27,743        21%            
Capex                       ZAR`000   16,074       22,792        29%            
Notional cash expenditure   ZAR`000   37,920       50,535        25%            

Revenue                     ZAR/kg    264,861      238,194       11%            
Toatal cash costs           ZAR/kg    335,529      381,103       12%            
Capex                       ZAR/kg    246,875      313,094       21%            
Notional cash expenditure   ZAR/kg    582,403      694,197       16%            
(Continued)                                                                     
TGME                                Unit        YTD FY2010     YTD FY2009       
Gold produced                       kg          244            221              
Tonnes milled                       t           33,804         40,353           
                                                                                
Revenue                             ZAR`000     60,733         51,914           
Total cash costs                    ZAR`000     87,830         86,737           
Capex                               ZAR`000     51,125         33,511           
Notional cash expenditure           ZAR`000     138,955        120,248          
                                                                                
Revenue                             ZAR/kg      248,518        235,161          
Toatal cash costs                   ZAR/kg      359,402        392,904          
Capex                               ZAR/kg      209,202        151,800          
Notional cash expenditure           ZAR/kg      568,604        544,704          
Table 10 - Summary of salient production metrics for TGME                       
TGME                             Unit    Q3 FY2010   Q2 FY2010     Variance     
                                                                  Q3 v Q2       
Face length (Ave)                m       -           283           (100%)       
Face advance (Ave)               m       -           5.40          (100%)       
Stoping m2 broken                m2      -           1,537         (100%)       
Development                      m       40          245           (84%)        
                                                                                
Tonnes milled           U/G      t       -           4,041         (100%)       
Yield per tonne         U/G      g/t     -           6.23          (100)%       
Gold produced           U/G      kg      -           25            (100%)       
                                oz      -           809           (100%)        
                                                                                
Gold produced           HLP      kg      28          19            48%          
                                oz      884         599           48%           
Gold produced           Other    kg      38          29            30%          
                                oz      1,209       932           30%           

Total gold produced              kg      65          73            (11%)        
                                oz      2,093       2,341         (11%)         
(Continued)                                                                     
TGME                                    Unit       YTD FY2010    YTD FY2009     
Face length (Ave)                       m          591           319            
Face advance (Ave)                      m          13.55         6.60           
Stoping m2 broken                       m2         8,007         19,095         
Development                             m          988           778            
                                                                                
Tonnes milled                  U/G      t          17,634        40,353         
Yield per tonne                U/G      g/t        5.87          5.01           
Gold produced                  U/G      kg         104           202            
                                       oz         3,330         6,498           
                                                                                
Gold produced                  HLP      kg         74            19             
oz         2,385.91      610.00          
Gold produced                  Other    kg         67            -              
                                       oz         2,141.24      -               
                                                                                
Total gold produced                     kg         244           221            
                                       oz         7,857         7,108           
Production summary                                                              
Gold production was down 255 oz (7.9kg) quarter-on-quarter due to the suspension
of underground operations in Q2 FY2010 and abnormally high rain fall during     
November 2009 and the first half of December 2009. This resulted in dilution of 
the leach pad solution and interruptions to the tramming and crushing operations
in the plant.                                                                   
At Elandsdrift HLP production increased by 286 oz (8.9kg) from 599 oz (18.6kg)  
to 885 oz (27.5kg) but was below forecast by 305 oz (9.5kg) due to the dilution 
effect of the excessive rain. The top of the HLP has been covered with a HDPE   
lining to divert excess rain from the pad.                                      
Gold production from the rock dumps and other sources increased by 276  oz      
(8.6kg) from 932  oz (29kg) to 1,208  oz (37.6 kg) but was 643 oz (20kg) below  
guidance. This was due to the excessive rain which resulted in 14 days lost     
where no screening could be done at the sites, five days where no tramming of   
the screened material could be done and numerous plant stoppages.               
The valuation of numerous rock dumps has been completed which resulted in a     
number of commercially viable resources being identified.                       
Table 11 - Quarterly variance analysis for TGME                                 
Revenue variance                                                                
Period            kg                  Price ZAR/kg        Revenue ZAR`000       
Q3 FY 2010        65                  264,861             17,245                
Q2 FY 2010        73                  238,151             17,340                
Total             8                   (26,710)            95                    
                                                                                
Period            Volume variance     Price variance      Revenue variance      
                 ZAR`000             ZAR`000             ZAR`000                
Q3 v Q2           2,039               (1,945)             95                    
(Continued)                                                                     
Period         kg              Cost ZAR/kg    Cash cost        Total variance   
                                             ZAR`000          ZAR`000           
Q3 FY 2010     65              335,529        21,846           (4,601)          
Q2 FY 2010     73              381,035        27,743           (10,403)         
Total          8               45,506         5,897            (5,802)          
                                                                                
Period         Volume          Unit cost      Cost variance    Total variance   
              variance        variance                        ZAR`000           
              ZAR`000         ZAR`000        ZAR`000                            
Q3 v Q2        2,584           3,313          5,897            (5,802)          
Financials                                                                      
Q3 FY2010 v Q2 FY2010                                                           
Gold revenue for TGME decreased quarter-on-quarter by 1% from ZAR17.3 million to
ZAR17.2 million due to a volume decrease of 8 kg as a result of the suspension  
of underground operations during July 2009, mitigated by an 11% increase in the 
ZAR/kg gold price.                                                              
The reduced volumes created a revenue variance of ZAR2 million, quarter-on-     
quarter and the increased gold price had a positive effect of ZAR1.9 million on 
total revenue.                                                                  
Table 12 - Statement of comprehensive income for TGME                           
TGME                                    Q3 FY2010    Q2 FY2010    Variance Q3   
                                                                 v Q2           
Selected Financial information          ZAR`000      ZAR`000      %             
Statement of comprehensive income                                               
Revenue                                 17,245       17,340       (1%)          
Total cash cost                         (21,846)     (27,743)     21%)          
Production-related depreciation         (5,458)      (3,587)      (52%)         
Operating profit/(loss) from mining     (10,059)     (13,991)     28%           
activities                                                                      
Other income                            591          526          12%           
Restructuring costs                     (745)        (3,032)      75%           
Share option costs                      (357)        (843)        58%           
General administrative and overhead     (1,573)      (2,440)      36%           
expenditure                                                                     
(Loss) from operations before interest  (12,144)     (19,780)     39%           
and taxation                                                                    
Fair value adjustments & impairments    -            -            0%            
Finance income & dividends              8            11           (28%)         
Finance charges                         (235)        (121)        (94%)         
Profit/(loss) before taxation           (12,371)     (19,890)     (38%)         
(Continued)                                                                     
TGME                                              YTD FY2010       YTD FY2009   
Selected Financial information                    ZAR`000          ZAR`000      
Statement of comprehensive income                                               
Revenue                                           60,733           51,914       
Total cash cost                                   (87,830)         (87,236)     
Production-related depreciation                   (12,637)         (7,297)      
Operating profit/(loss) from mining activities    (39,735)         (42,619)     
Other income                                      2,495            1,115        
Restructuring costs                               (3,777)          -            
Share option costs                                (2,146)          (4,657)      
General administrative and overhead expenditure   (7,136)          (11,113)     
(Loss) from operations before interest and        (50,299)         (57,274)     
taxation                                                                        
Fair value adjustments & impairments              -                (17)         
Finance income & dividends                        38               129          
Finance charges                                   (564)            -            
Profit/(loss) before taxation                     (50,825)         (57,162)     
Quarter-on-quarter, total cash costs reduced 21% from ZAR27.7 million in Q2     
FY2010, to ZAR21.8 million in Q3 FY2010.  Labour costs reduced by 39% due to the
rationalisation of TGME , stores and major items reduced by 12%, oxygen reduced 
by 16%, cyanide reduced by 37% and steel balls reduced by 67% due to procurement
of cheaper material. Electricity decreased by 36%. Cash cost/kg reduced quarter-
on-quarter by 12% from ZAR381,103/kg in Q2 FY2010 to ZAR335,529/kg in Q3 FY2010.
TGME`s loss before taxation narrowed from ZAR20 million in Q2 FY2010 to         
ZAR12.4 million in Q3 FY2010.                                                   
Capital expenditure decreased from ZAR22.7 million in Q2 FY2010 to ZAR16 million
in Q3 FY2010 due to the closure of the underground development.                 
Year-to-date FY2010 v year-to-date FY2009                                       
Revenue increased 17% for the first nine months of FY2010 compared to the first 
nine months FY2009 due to an increase of 759 oz (23.6 kg) in gold produced. The 
volume variance resulted in an increase of ZAR8 million in revenue and the      
increase in the price of gold on average from ZAR235,161/kg to ZAR248,518/kg    
resulted in an increase of ZAR3 million in revenue.                             
Total cash costs increased by 1% (ZAR1 million) as a result of an increase in   
volume (ZAR8.4 million) and a decrease in costs of ZAR7.8 million which was     
driven by cheaper production costs relating to surface operations.              
Capital expenditure for the first nine months of FY2010 amounted to             
ZAR51 million (FY2009: ZAR33 million), of which approximately a third relates to
the development of the Frankfort B block.                                       
Outlook Q4 FY2010                                                               
Heavy rainfall continues to impede surface operations and will thus result in a 
much lower than anticipated gold output for the fourth quarter with             
correspondingly higher unit costs. Additionally, TGME has temporarily stopped   
irrigating the Elandsdrift HLP in order to allow the pad to drain the excess    
rain water.                                                                     
While TGME represents significant option value in the form of extensive         
prospecting rights, the continued drain on the company`s cash flow, combined    
with the capital required to realise the prospective potential of this asset,   
has put the future of this asset under review. Accordingly, Simmers is intending
to embark on a consultative process in terms of section 189a of the Labour      
Relations Act, 66 of 1995 to further restructure and down-size this operation.  
Operational summary                                                             
          Period     Parameter   US$/oz     ZAR/kg      Parameter   ZAR/US$     
FY2010     Q3         Gold price  1,101      266,149     Exchange    7.52       
                     (LBMA)                             rate                    
          Q2                     960        241,594                 7.83        
          YTD                    994        254,124                 7.95        
FY2009     YTD                    857        234,530                 8.51       
Operating results                                             Simmers total     
Ore milled/treated (`000 tonnes)          FY2010    Q3        694,161           
                                                   Q2        583,212            
YTD       1,825,628          
                                         FY2009    YTD       1,624,941          
Yield (g/t)                               FY2010    Q3        1.30              
                                                   Q2        1.78               
YTD       1.62               
                                         FY2009    YTD       1.83               
Gold sold (kg)                            FY2010    Q3        903               
                                                   Q2        1,036              
YTD       2,965              
                                         FY2009    YTD       2,978              
Gold sold (oz)                            FY2010    Q3        29,040            
                                                   Q2        33,301             
YTD       95,335             
                                         FY2009    YTD       95,761             
Revenue (ZAR/kg declared)                 FY2010    Q3        263,761           
                                                   Q2        238,248            
YTD       248,466            
                                         FY2009    YTD       230,210            
Revenue (U$/oz declared)                  FY2010    Q3        1,091             
                                                   Q2        947                
YTD       972                
                                         FY2009    YTD       841                
Total cash costs(ZAR/kg declared)         FY2010    Q3        254,972           
                                                   Q2        266,345            
YTD       260,648            
                                         FY2009    YTD       232,102            
Total cash costs(US$/oz declared)         FY2010    Q3        1,054             
                                                   Q2        1,058              
YTD       1,020              
                                         FY2009    YTD       848                
Total cash costs(ZAR/t ore)               FY2010    Q3        332               
                                                   Q2        473                
YTD       423                
                                         FY2009    YTD       425                
Capital expenditure(ZAR/kg declared)      FY2010    Q3        66,965            
                                                   Q2        57,432             
YTD       51,138             
                                         FY2009    YTD       33,096             
Notional cash cost(ZAR/kg declared)       FY2010    Q3        321,937           
                                                   Q2        323,777            
YTD       311,785            
                                         FY2009    YTD       265,198            
(Continued)                                                                     
Operating results                           BGM                                 
Total         Surface     U/G        
                                                         total       total      
Ore milled/treated (`000                                                        
tonnes)                    FY2010    Q3     677,991       499,503     178,488   
Q2     579,171       335,775     243,396    
                                    YTD    1,791,824     1,153,725   638,099    
                          FY2009    YTD    1,584,588     927,235     657,353    
Yield (g/t)                FY2010    Q3     1.24          0.34        3.74      
Q2     1.66          0.37        3.44       
                                    YTD    1.52          0.36        3.61       
                          FY2009    YTD    1.74          0.42        3.61       
Gold sold (kg)             FY2010    Q3     838           170         668       
Q2     963           124         839        
                                    YTD    2,721         416         2,305      
                          FY2009    YTD    2,758         387         2,371      
Gold sold (oz)             FY2010    Q3     26,947        5,463       21,483    
Q2     30,961        3,994       26,966     
                                    YTD    87,478        13,370      74,108     
                          FY2009    YTD    88,663        12,450      76,214     
Revenue (ZAR/kg declared)                                                       
FY2010    Q3     263,676       264,064     263,577    
                                    Q2     238,252       238,441     230,988    
                                    YTD    248,462       251,080     169,087    
                          FY2009    YTD    229,813       230,994     229,888    
Revenue (U$/oz declared)   FY2010    Q3     1,090         1,092       1,090     
                                    Q2     947           948         918        
                                    YTD    972           982         661        
                          FY2009    YTD    840           844         840        
Total cash costs(ZAR/kg                                                         
declared)                  FY2010    Q3     248,714       139,646     276,451   
                                    Q2     257,670       167,490     264,539    
                                    YTD    251,778       156,764     186,418    
FY2009    YTD    219,230       140,074     232,160    
Total cash costs(US$/oz                                                         
declared)                  FY2010    Q3     1,029         577         1,143     
                                    Q2     1,024         666         1,051      
YTD    985           613         729        
                          FY2009    YTD    801           512         848        
Total cash costs(ZAR/t                                                          
ore)                       FY2010    Q3     307           48          1,035     
Q2     428           62          912        
                                    YTD    382           57          673        
                          FY2009    YTD    382           58          837        
Capital expenditure                                                             
(ZAR/kg declared)          FY2010    Q3     52,989        22,714      12,072    
                                    Q2     38,105        23,023      23,140     
                                    YTD    36,941        24,195      17,515     
                          FY2009    YTD    23,594        17,835      21,992     
Notional cash cost(ZAR/kg                                                       
declared)                  FY2010    Q3     301,703       162,361     288,523   
                                    Q2     295,775       190,513     287,679    
                                    YTD    288,719       180,960     203,933    
FY2009    YTD    242,823       157,909     254,152    
(Continued)                                                                     
Operating results                                               TGME total      
Ore milled/treated (`000 tonnes)                FY2010   Q3     16,170          
Q2     4,041            
                                                        YTD    33,804           
                                               FY2009   YTD    40,353           
Yield (g/t)                                     FY2010   Q3     4.03            
Q2     18.01            
                                                        YTD    7.23             
                                               FY2009   YTD    5.47             
Gold sold (kg)                                  FY2010   Q3     65              
Q2     73               
                                                        YTD    244              
                                               FY2009   YTD    221              
Gold sold (oz)                                  FY2010   Q3     2,093           
Q2     2,340            
                                                        YTD    7,857            
                                               FY2009   YTD    7,098            
Revenue (ZAR/kg declared)                       FY2010   Q3     264,861         
Q2     238,194          
                                                        YTD    248,518          
                                               FY2009   YTD    235,161          
Revenue (U$/oz declared)                        FY2010   Q3     1,095           
Q2     947              
                                                        YTD    972              
                                               FY2009   YTD    859              
Total cash costs(ZAR/kg declared)               FY2010   Q3     335,529         
Q2     381,103          
                                                        YTD    359,402          
                                               FY2009   YTD    392,904          
Total cash costs(US$/oz declared)               FY2010   Q3     1,388           
Q2     1,514            
                                                        YTD    1,406            
                                               FY2009   YTD    1,435            
Total cash costs(ZAR/t ore)                     FY2010   Q3     1,351           
Q2     6,865            
                                                        YTD    2,598            
                                               FY2009   YTD    2,149            
Capital expenditure(ZAR/kg declared)            FY2010   Q3     246,875         
Q2     313,094          
                                                        YTD    209,202          
                                               FY2009   YTD    151,800          
Notional cash cost(ZAR/kg declared)             FY2010   Q3     582,403         
Q2     694,197          
                                                        YTD    568,604          
                                               FY2009   YTD    544,704          
Financial results                                               Simmers total   
Revenue                                         FY2010   Q3     238,240         
                                                        Q2     246,774          
                                                        YTD    736,768          
                                               FY2009   YTD    685,677          
Total cash costs                                FY2010   Q3     230,301         
                                                        Q2     275,877          
                                                        YTD    772,887          
                                               FY2009   YTD    691,313          
Operating profit/(loss) before non-cash                                         
production related expenses                     FY2010   Q3     7,939           
                                                        Q2     (29,103)         
                                                        YTD    (36,120)         
FY2009   YTD    (5,636)          
Capital expenditure (ZAR `000)                  FY2010   Q3     60,486          
                                                        Q2     59,487           
                                                        YTD    151,636          
FY2009   YTD    98,576           
Cash flow (after capital expenditure)           FY2010   Q3     (52,547)        
                                                        Q2     (88,590)         
                                                        YTD    (187,756)        
FY2009   YTD    (104,211)        
Continued                                                                       
Financial results                           BGM                                 
                                           Total        Surface   U/G total     
total                   
Revenue                    FY2010     Q3    220,994      44,872    176,122      
                                     Q2    229,434      29,624    193,741       
                                     YTD   676,035      104,415   389,749       
FY2009     YTD   633,764      89,447    544,950       
Total cash costs           FY2010     Q3    208,455      23,730    184,725      
                                     Q2    248,134      20,809    221,882       
                                     YTD   685,057      65,193    429,697       
FY2009     YTD   604,576      54,240    550,336       
Operating profit/(loss)                                                         
before non-cash production                                                      
related expenses                                                                
FY2010     Q3    12,540       21,142    (8,603)       
                                     Q2    (18,700)     8,815     (28,141)      
                                     YTD   (9,022)      39,222    (39,948)      
                          FY2009     YTD   29,187       35,206    (5,386)       
Capital expenditure (ZAR                                                        
`000)                      FY2010     Q3    44,412       3,860     8,066        
                                     Q2    36,695       2,860     19,409        
                                     YTD   100,512      10,062    40,373        
FY2009     YTD   65,065       6,906     52,133        
Cash flow (after capital                                                        
expenditure)               FY2010     Q3    (31,872)     17,282    (16,669)     
                                     Q2    (55,395)     5,955     (47,550)      
YTD   (109,543)    29,160    (80,321)      
                          FY2009     YTD   (35,877)     28,300    (57,518)      
(Continued)                                                                     
Financial results                                             TGME total        
Revenue                                      FY2010   Q3      17,245            
                                                     Q2      17,340             
                                                     YTD     60,733             
                                            FY2009   YTD     51,914             
Total cash costs                             FY2010   Q3      21,846            
                                                     Q2      27,743             
                                                     YTD     87,830             
                                            FY2009   YTD     86,737             
Operating profit/(loss) before non-cash                                         
production related expenses                  FY2010   Q3      (4,601)           
                                                     Q2      (10,403)           
                                                     YTD     (27,098)           
FY2009   YTD     (34,823)           
Capital expenditure (ZAR `000)               FY2010   Q3      16,074            
                                                     Q2      22,792             
                                                     YTD     51,125             
FY2009   YTD     33,511             
Cash flow (after capital expenditure)        FY2010   Q3      (20,675)          
                                                     Q2      (33,196)           
                                                     YTD     (78,222)           
FY2009   YTD     (68,334)           
Transvaal Gold Mining Estates: An underground and heap leach gold operation in  
Mpumalanga. Buffelsfontein Gold Mine: An underground and surface gold operation 
at Stilfontein.                                                                 
* Note: BGM total figure includes on-mine services costs, which are excluded    
from the surface and underground cost.                                          
CONFERENCE CALL:                                                                
A conference call with executive management to discuss the third quarter results
will commence at 3pm Central African time (CAT) and 8 am Eastern Standard time  
(EST) today, Friday, 19 February 2010. This will be followed by a question and  
answer (Q&A) session.                                                           
The dial in for call participants are as follows:                               
Johannesburg (Telkom):           011 535 3600                                   
South Africa Toll-free:          0 800 200 648                                  
UK Toll-free:                    0 800 917 7042                                 
Australia Toll-free:             1 800 350 100                                  
Canada Toll-free:                1 866 605 3852                                 
USA Toll-free:                   1 800 860 2442                                 
Other:                           +27 11 535 3600                                
                                                                                
Playback numbers:                playback code 2544#                            
Johannesburg:                    011 305 2030                                   
UK Toll-free:                    0 808 234 6771                                 
AU Toll-free:                    1 800 091 250                                  
USA:                             1 412 317 0088                                 
Other:                           +27 11 305 2030                                
Forward-looking Information                                                     
This shareholders report and financial statements for the quarter ended         
31 December 2009 contain certain forward-looking statements.  Forward-looking   
statements include but are not limited to those with respect to the price of    
uranium and gold, the estimation of mineral resources and reserves, the         
realization of mineral reserve estimates, the timing and amount of estimated    
future production, costs of production, capital expenditures, costs and timing  
of development of new deposits, success of exploration activities, permitting   
time lines, currency fluctuations, requirements for additional capital,         
government regulation of mining operations, environmental risks, unanticipated  
reclamation expenses, title disputes or claims and limitations on insurance     
coverage and the timing and possible outcome of pending litigation.  In certain 
cases, forward-looking statements can be identified by the use of words such as 
"plans", "expects" or "does not expect", "is expected", "budget", "scheduled",  
"estimates", "forecasts", "intends", "anticipates", or "does not anticipate", or
"believes" or variations of such words and phrases, or state that certain       
actions, events or results "may", "could", "would", "might" or "will" be taken, 
occur or be achieved.  Forward-looking statements involve known and unknown     
risks, uncertainties and other factors which may cause the actual results,      
performance or achievements of Simmers to be materially different from any      
future results, performance or achievement expressed or implied by the forward- 
looking statements.  Such risks and uncertainties include, among others, the    
actual results of current exploration activities, conclusions of economic       
evaluations, changes in project parameters as plans continue to be refined,     
possible variations in grade and ore densities or recovery rates, failure of    
plant, equipment or processes to operate as anticipated, accidents, labour      
disputes or other risks of the mining industry, delays in obtaining government  
approvals or financing or in completion of development or construction          
activities, risks relating to the integration of acquisitions, to international 
operations, to prices of uranium and gold.  Although Simmers has attempted to   
identify important factors that could cause actual actions, events or results to
differ materially from those described in forward-looking statements, there may 
be other factors that cause actions, events or results not to be as anticipated,
estimated or intended.  It is important to note, that: (i) unless otherwise     
indicated, forward-looking statements indicate the Group`s` expectations as at  
15 February 2009; (ii) actual results may differ materially from the Group`s    
expectations if known and unknown risks or uncertainties affect its business, or
if estimates or assumptions prove inaccurate; (iii) the Group  cannot guarantee 
that any forward-looking statement will materialize and, accordingly, readers   
are cautioned not to place undue reliance on these forward-looking statements;  
and (iv) the Group disclaims any intention and assumes no obligation to update  
or revise any forward-looking statement even if new information becomes         
available, as a result of future events or for any other reason.                
For further information please contact:                                         
Nick Goodwin                        Simmers investor relations executive        
Mobile                              +27 83 629 8605                             
Email                               nick@simmers.co.za                          
                                                                                
Gail Strauss                        Simmers Group communications                
Mobile                              +27 82 936 8481                             
Email                               gail@simmers.co.za                          
                                                                                
Byron Kennedy/ Marina Bidoli        Brunswick                                   
                                   +27 11 502 7400                              

Melanie de Nysschen/ Thembeka       Macquarie First South Advisers              
Mgoduso                             +27 11 583 2000                             
                                                                                
Johannesburg                                                                    
19 February 2010                                                                
MACQUARIE FIRST SOUTH ADVISERS (PTY) LIMITED                                    
Sponsor and Corporate adviser                                                   
Date: 19/02/2010 07:29:01 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: