| Thu 1 Apr 2010, 16:40 | | ZCI - Zambia Copper Investments - Provision of additional finance to African |
|
ZCI
ZAKK
ZCI - Zambia Copper Investments - Provision of additional finance to African
Copper Plc
Zambia Copper Investments Limited
(Bermudian registration number 661:1969)
(South African registration number 1970/000023/10)
JSE share code: ZCI ISIN: BMG988431240
Euronext share code: BMG988431240
("ZCI")
Provision of additional finance to African Copper Plc
ZCI is pleased to announce the arrangement of a US$10 million loan ("the ZCI
Loan") to its subsidiary, African Copper Plc ("ACU"). The monies will be used
at ACU`s Mowana mine in Botswana to fund the purchase of mobile crushing
capacity, the redesign of the Secondary and Tertiary circuit (the "Tertiary
Plant"), fund short term working capital requirements and commence further
exploration of its Matsitama prospect in Botswana.
Under the terms of the ZCI loan, ACU will receive US$10 million immediately,
at an interest rate of 6% per annum payable quarterly, to be repaid on or
before 31st March 2011 and may be renewed, subject to ZCI giving its written
consent to such renewal, prior to the repayment date. The ZCI Loan will be
secured under the existing ZCI Term Loan Facility which includes security over
ACU and all other ACU group companies` assets, including the Mowana Mine and a
guarantee by ACU.
Production at the Mowana mine has been adversely affected by low availability
of the Tertiary Plant caused by equipment breakdown and rain that has affected
the consistency of the processed ore and hindered the flow of material from
stockpiles. To mitigate these problems ACU placed orders with a rental company
for the temporary provision of mobile crushing capacity to bypass the Tertiary
Plant. Delivery was expected by late February 2010 but due to problems
experienced by the rental company in funding the necessary equipment, the
delivery was delayed and ACU has subsequently decided to purchase the mobile
crushers directly.
The ZCI Loan allows ACU to immediately purchase the mobile crushers and it
expects to have thesecrushers delivered, installed and running within three
weeks. At the same time ACU will be engagingconsultants to design and
implement the required changes to the Tertiary Plant. Production in March 2010
has continued to be adversely affected and the Tertiary Plant has been
recently shut down pending the installation of the mobile crushers.
ACU also plans further development expenditures including the construction of
the wet tailings facilityand a Dense Media Separation plant at the Mowana
mine. In addition, ACU is planning deep exploration drilling in and around the
Mowana mine and pre-stripping and mining contractor mobilisation at ACU`s
nearby Thakadu deposit which is expected to commence operations in May 2010.
Good progress continues to be made on the wet tailings facility at Mowana.
Drawings, scope and bill ofquantities for the project have been completed by
consultant engineers, Scott Wilson and the tendering process is underway. ACU
expects the adjudication of tenders and the award of contract to be completed
during April 2010 with commencement of construction in May. An Environmental
Management Plan for wet tailings disposal was submitted to the Botswana
Government DEA on 1 March 2010 and feedback is expected shortly.
At Thakadu, the Environmental Impact Assessment process is planned to be
completed in early April 2010 and ACU is expecting the mining licence by the
end of April for mining to start in May 2010. The road from Thakadu to Mowana
is currently being upgraded for the commencement of shipping ore.
It is anticipated that this proposed additional expenditure along with the
subsequent repayment of the ZCI Loan will be financed by a comprehensive
longer term project finance package that is currently being sourced.
Indicative term sheets have been received from a number of banks located in
Europe and South Africa.
Commenting, Jordan Soko, Interim CEO and director of ACU, said, "I believe
that we have now understood all of the issues to be resolved at Mowana and
identified solutions that can be quickly implemented. With the active support
- both financial and operational - of ZCI, we anticipate being able to
maximise production from our high quality assets and thus deliver value to all
of our investors."
Bermuda
1 April 2010
Sponsor: Bridge Capital Advisors (Pty) Limited
Date: 01/04/2010 16:40:01 Produced by the JSE SENS Department.
The SENS service is an information dissemination service administered by the
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or
implicitly, represent, warrant or in any way guarantee the truth, accuracy or
completeness of the information published on SENS. The JSE, their officers,
employees and agents accept no liability for (or in respect of) any direct,
indirect, incidental or consequential loss or damage of any kind or nature,
howsoever arising, from the use of SENS or the use of, or reliance on,
information disseminated through SENS.