Wed 14 Apr 2010, 16:40 PAM - Palabora Mining Company - First Quarter 2010 - Operations Overview And
PAM
PAM                                                                             
PAM - Palabora Mining Company - First Quarter 2010 - Operations Overview And    
                                  Production Statistics                         
PALABORA MINING COMPANY LIMITED                                                 
(Incorporated in the Republic of South Africa)                                  
Registration number - 1956/002134/06                                            
JSE Code: PAM        ISIN: ZAE000005245                                         
("Palabora" or "the Company")                                                   
FIRST QUARTER 2010 - OPERATIONS OVERVIEW AND PRODUCTION STATISTICS              
                        1Q        2Q        3Q       4Q        1Q       FULL    
                        2009      2009      2009     2009               YEAR    
                                                         2010     2009          
Palabora mine:                                                                  
Tonnes hoisted (`000     2,966     3,009     2,978    2,585     2,839    11,538 
tonnes)                                                                         
Ore treated (`000        2,789     2,940     2,792    2,809     2,784    11,330 
tonnes)                                                                         
Average ore grade:       0.68      0.68      0.66     0.67      0.66     0.67   
copper (%)                                                                      
Copper concentrates      67.1      76.1      61.8     65.8      61.8     270.8  
produced (`000 tonnes)                                                          
Average concentrate      30.5      29.9      31.1     30.5      29.8     30.5   
grade: copper (%)                                                               
Copper in concentrates   20.5      22.7      19.3     20.1      18.4     82.6   
(`000 tonnes)                                                                   
Palabora                                                                        
smelter/refinery:                                                               
New concentrate smelted  72.8      68.0      58.5     67.3      57.7     266.6  
on site (`000 tonnes)                                                           
New copper anodes        20.2      18.9      12.5     14.3      12.4     65.9   
produced (`000 tonnes)                                                          
Refined new copper       21.0      19.5      13.8     15.1      12.2     69.4   
produced (`000 tonnes)                                                          
By-products:                                                                    
Magnetite concentrate    772       617       758.7    697.2     754.1    2,845  
(`000 tonnes)                                                                   
Nickel contained in      21        33        29       11.4      18.5     94.4   
products (tonnes)                                                               
Copper sold as           0         2.1       3.9      4.5       2.5      10.5   
concentrate (`000                                                               
tonnes)                                                                         
Vermiculite plant:                                                              
Vermiculite produced     52        46        48.      50        54       196    
(`000 tonnes)                                                                   
Palabora, a member of the Rio Tinto Group of Companies, situated in the Ba-     
Phalaborwa area of Limpopo, operates a large block cave copper mine smelter     
complex and 241 million tonne magnetite stockpile.                              
Production from the underground mine averaged 31,542 tonnes on a daily basis for
the quarter.  Production during the quarter was 9% higher than the previous     
quarter and slightly lower than the corresponding period in 2009.               
In total, 2,838,805 tonnes of ore was hoisted during the quarter with a copper  
grade of 0.66%. Average copper head grade was relatively unchanged from the last
quarter but 2% lower than the corresponding period in 2009.                     
Ore treated was slightly lower on a sequential basis due to lower auto mill run 
rates as a result of a higher proportion of dolerite in the ore mined and       
remained in line with the corresponding period in 2009.                         
The Copper concentrate production was 6% lower sequentially and 8% lower than   
the corresponding period in 2009 due to a combination of lower mill throughput  
and lower head grade in reprocessed smelter secondary material.                 
The copper in concentrate production was 8% lower sequentially and 10% lower    
than the corresponding period in 2009 mainly due to a combination of lower      
milling rates, concentrate grade and reprocessing of lower grade smelter        
secondary material.                                                             
New concentrate smelted was 14% lower sequentially and 21% lower than the       
corresponding period in 2009 due to reverbratory furnace low feed rates as      
result of downtime at the furnace bath and low Wolff crane availability. Process
improvement and technical consultants were engaged during the quarter to address
these issues.  As a result work has commenced on recovering the reverb furnace  
bath which is expected to result in increased throughput performance during the 
second quarter of 2010. In addition, the Wolff crane was removed from service to
perform a refurbishment exercise and will be returned to production in April.   
Both of these actions are expected to improve operational performance and output
during the second quarter of 2010.                                              
Magnetite                                                                       
Magnetite production was consistent with the ramp-up in processing of reclaim   
tonnage and placement of additional low grade magnetite in the market. Iron     
oxide (56%) contributed 20% of total production whilst coarse magnetite (65%)   
contributed 80%.                                                                
Vermiculite Operations                                                          
Vermiculite production was 8% higher sequentially due to an additional amount of
stockpile material that was decontaminated to meet the upswing in market demand.
The above information has not been reviewed or reported on by the Company`s     
auditors.                                                                       
Phalaborwa                                                                      
14 April 2010                                                                   
Sponsor:                                                                        
Barnard Jacobs Mellet Corporate Finance (Proprietary) Limited                   
Date: 14/04/2010 16:40:01 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: