BHP BILLITON EXPLORATION AND DEVELOPMENT report for the QUARTER ENDED 31 MARCH  
2010                                                                            
This report covers the Group`s exploration and development activities for the   
quarter ended 31 March 2010. Unless otherwise stated, BHP Billiton`s interest in
the projects referred to in this report is 100 per cent and references to       
project schedules are based on calendar years. This report, together with the   
Production Report, represents the Interim Management Statement for the purposes 
of the UK Listing Authority`s Disclosure and Transparency Rules. There have been
no significant changes to the financial position of the Group in the quarter    
ended 31 March 2010.                                                            
Development                                                                     
During the March 2010 quarter the Pyrenees project (oil and gas), offshore      
Western Australia, achieved first production on schedule and within budget. This
project will not be reported in future Exploration and Development Reports.     
Project And      Share    Initial      Production          Quarterly            
Ownership        Of       Production   Capacity (100%)     Progress             
                Approved Target Date                                            
                 Capex                                                          
                US$M                                                            
Petroleum                                                                       
Projects                                                                        
Pyrenees         1,200    H1 CY10      96,000 barrels of   First production     
(Australia)                            oil and 60 million  announced, on        
71.43%                                 cubic feet gas per  schedule. See News   
Oil/Gas                                day                 Release dated 1 March
                                                         2010.                  
Angostura Gas    180      H1 CY11      280 million cubic   On schedule and      
Phase II                               feet gas per day    budget. Installation 
(Trinidad and                                              campaign has         
Tobago)                                                    commenced. Topsides  
45%                                                        fabrication          
Gas                                                        continues. The       
                                                         overall project is     
                                                         50% complete.          
Bass Strait      500      CY11         10,000 bpd          Schedule and budget  
Kipper                                 condensate and      under review         
(Australia)                            processing          following advice from
32.5% - 50%                            capacity of 80      operator. West Tuna  
Gas/Gas Liquids                        million cubic feet  platform retrofit    
gas per day         work continuing. The  
                                                         overall project is     
                                                         33% complete.          
Bass Strait      625      CY11         11,000 bpd          Schedule and budget  
Turrum                                 condensate and      under review         
(Australia)                            processing          following advice from
50%                                    capacity of 200     operator. Platform   
Gas/Gas Liquids                        million cubic feet  fabrication          
gas per day         continues. The        
                                                         overall project is     
                                                         29% complete.          
North West       245      CY11         Replacement vessel  On schedule and      
Shelf CWLH Life                        with capacity of    budget. Floating     
Extension                              60,000 bpd oil      Production Storage   
(Australia)                                                and Offtake (FPSO)   
16.67%                                                     conversion continues.
Oil                                                        The overall project  
                                                         is 76% complete.       
North West       850      CY12         2,500 million       On schedule and      
Shelf North                            cubic feet gas per  budget. Jacket       
Rankin B Gas                           day                 fabrication          
Compression                                                continuing ahead of  
(Australia)                                                schedule. The overall
16.67%                                                     project is 46%       
LNG                                                        complete.            
Minerals                                                                        
Projects                                                                        
Worsley          1,900    H1 CY11      1.1 million tpa of  On schedule and      
Efficiency &                           additional alumina  budget.  Engineering 
Growth                                                     is essentially       
(Australia)                                                complete.            
86%                                                        Construction is 19%  
Alumina                                                    complete. The overall
                                                         project is 38%         
                                                         complete.              
Antamina         435      Q4 CY11      Increases ore       On schedule and      
Expansion                              processing          budget. Engineering  
(Peru)                                 capacity to         is 58% complete.     
33.75%                                 130,000 tpd         Construction         
Copper                                                     commenced during the 
quarter. The overall   
                                                         project is 11%         
                                                         complete.              
Iron Ore         4,800    H2 CY11      50 million tpa      On schedule and      
(Western                               additional iron     budget. Engineering  
Australia)                             ore system          is 93% complete.     
RGP5                                   capacity            Construction is now  
85%                                                        41% complete. The    
Iron Ore                                                   overall project is   
                                                         46% complete.          
Douglas-         975      Mid CY10     10 million tpa      On schedule and      
Middelburg                             export thermal      budget. The overall  
Optimisation                           coal and 8.5        project is 96%       
(South Africa)                         million tpa         complete.            
100%                                   domestic thermal                         
Energy Coal                            coal (sustains                           
current output)                           
Newcastle Third  390      Mid CY10     30 million tpa      On schedule and      
Port Project                           export coal         budget. First vessel 
(Australia)                            loading facility    successfully loaded  
35.5%                                                      in March 2010. The   
Energy Coal                                                overall project is   
                                                         97% complete.          
MAC20 Project    260      H1 CY11      Increases saleable  On schedule and      
(Australia)                            thermal coal        budget. Engineering  
100%                                   production by       is 90% complete.     
Energy Coal                            approximately 3.5   Construction is 50%  
                                      million tpa         complete. The overall 
project is 65%         
                                                         complete.              
Minerals Exploration                                                            
Grassroots exploration continued on copper targets in Chile and Zambia; nickel  
targets in Australia; manganese targets in Gabon; and diamond targets in Canada.
Exploration for iron ore, coal, bauxite and manganese was undertaken in a number
of regions including Australia, South America, Russia and West Africa.          
During the quarter, the announced acquisitions of United Minerals Corporation NL
and Athabasca Potash Inc. were completed. In addition, BHP Billiton entered into
binding agreements with a subsidiary of PT Adaro Energy TBK (Adaro) to create a 
new joint venture for the Indonesian Coal Project (ICP). Subject to approvals,  
Adaro will acquire a 25 per cent interest in the ICP joint venture.             
For the nine months ended ended 31 March 2010, BHP Billiton spent US$346 million
on minerals exploration, of which US$315 million was expensed.                  
Additional Information                                                          
Following requests for information from the U.S Securities and Exchange         
Commission as a part of an informal investigation relating primarily to certain 
terminated exploration projects, the Company has disclosed to relevant          
authorities evidence that it has uncovered regarding possible violations of     
applicable anti-corruption laws involving interactions with government          
officials. The Company is conducting an internal investigation, which is        
continuing, and is cooperating with the relevant authorities. It is not possible
at this time to predict the scope or duration of the investigation or its likely
outcome.                                                                        
Petroleum Exploration                                                           
Exploration and appraisal wells drilled during the quarter or in the process of 
drilling as at 31 March 2010.                                                   
Well           Location                BHP Billiton Equity     Status           
Double         Green Canyon Gulf of    70% BHP Billiton        Drilling ahead   
Mountain-1     Mexico                  (operator)                               
             GC 555                                                             
Firefox-1      Green Canyon Gulf of    50% BHP Billiton        Drilling ahead   
Mexico                  (operator)                                 
             GC 817                                                             
Bel Air-1      Liverpool Bay           46.1% BHP Billiton      Drilling ahead   
             110/13b                 (operator)                                 
Cerah-1        Sabah                   60% BHP Billiton        Plugged &        
             Block N                 (operator)              abandoned          
                                                             Dry hole           
SE Remora-1    Gippsland Basin         50% BHP Billiton        Plugged &        
Australia               (Exxon operator)        abandoned          
             VIC/RL4                                         Hydrocarbons       
                                                             encountered        
Knotty Head-2  Green Canyon Gulf of    25% BHP Billiton(Nexen  Suspended        
Mexico GC 512           operator)               Hydrocarbons       
                                                             encountered        
Deep Blue-1    Green Canyon Gulf of    31.875% BHP Billiton    Drilling ahead   
             Mexico                  (Noble operator)                           
GC 723                                                             
Wolverine-1    Laurentian Basin        45% BHP Billiton        Drilling ahead   
             Canada                  (CoP operator)                             
             E.L. 1087R                                                         
Banduria-1     Sandakan Basin          25% BHP Billiton        Plugged &        
             Philippines             (Exxon operator)        abandoned          
             SC-56                                           Dry hole           
Petroleum exploration expenditure for the nine months ended 31 March 2010 was   
US$587 million, of which US$206 million was expensed.                           
****                                                                            
Further information on BHP Billiton can be found on our website:                
www.bhpbilliton.com                                                             
Australia                                                                       
Amanda Buckley, Media Relations                                                 
Tel: +61 3 9609 2209 Mobile: +61 419 801 349                                    
email: Amanda.Buckley@bhpbilliton.com                                           
Fiona Martin, Media Relations                                                   
Tel: +61 3 9609 2211 Mobile: +61 427 777 908                                    
email: Fiona.Martin@bhpbilliton.com                                             
Leng Lau, Investor Relations                                                    
Tel: +61 3 9609 4202 Mobile: +61 403 533 706                                    
email: Leng.Y.Lau@bhpbilliton.com                                               
United Kingdom & South Africa                                                   
Andre Liebenberg, Investor Relations                                            
Tel: +44 20 7802 4131 Mobile: +44 7920 236 974                                  
email: Andre.Liebenberg@bhpbilliton.com                                         
Illtud Harri, Media Relations                                                   
Tel: +44 20 7802 4195 Mobile: +44 7920 237 246                                  
email: Illtud.Harri@bhpbilliton.com                                             
Americas                                                                        
Scott Espenshade, Investor Relations                                            
Tel: +1 713 599 6431 Mobile: +1 713 208 8565                                    
email: Scott.Espenshade@bhpbilliton.com                                         
Ruban Yogarajah, Media Relations                                                
Tel: US +1 713 966 2907 or UK +44 20 7802 4033                                  
Mobile: UK +44 7827 082 022                                                     
email: Ruban.Yogarajah@bhpbilliton.com                                          
BHP Billiton Limited ABN 49 004 028 077                                         
Registered in Australia                                                         
Registered Office: 180 Lonsdale Street                                          
Melbourne Victoria 3000 Australia                                               
Tel +61 1300 55 4757 Fax +61 3 9609 3015                                        
BHP Billiton Plc Registration number 3196209                                    
Registered in England and Wales                                                 
Registered Office: Neathouse Place                                              
London SW1V 1BH United Kingdom                                                  
Tel +44 20 7802 4000 Fax +44 20 7802 4111                                       
A member of the BHP Billiton group which is headquartered in Australia          
Date: 21/04/2010 07:06:02 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: