Thu 29 Apr 2010, 7:43 FSE - Firestone Energy Limited - Quarterly Activities Report For The Period to
FSE
FSE                                                                             
FSE - Firestone Energy Limited - Quarterly Activities Report For The Period to  
31 March 2010                                                                   
FIRESTONE ENERGY LIMITED                                                        
(formerly Centralian Minerals Limited)                                          
(Registration number: ABN 058 436 794)                                          
(SA company registration number: 200/023973/10                                  
Share code on the JSE: FSE                                                      
Share code on the ASX: FSE                                                      
ISIN: AU000000FSE6                                                              
("FSE" or "the Company")                                                        
Quarterly Activities Report For The Period to 31 March 2010                     
The Board of Firestone Energy Limited (ASX:FSE) is pleased to provide           
Shareholders with its Quarterly Activities Report for the 3 month period ended  
31 March 2010.                                                                  
HIGHLIGHTS                                                                      
OPERATIONAL                                                                     
    The Pre-Feasibility Study Report was received in late December 2009.  The   
    review of this report was finalised in early February 2010, with the aim    
    of prioritising activities required for the Bankable Feasibility Study      
(BFS).  The study has identified the first phase mining project area,       
    which is being estimated to produce just over 100mt over 20 years at low    
    stripping ratios.                                                           
    The Company continued to participate fully in the Eskom RFP process (Pre-   
qualification process for potential future coal supply agreements).  As a   
    consequence of these interactions the next phase of drilling has been       
    tailored to satisfy specific qualitative and technical queries including    
    a 3t sample for boiler combustion tests.                                    
EXPLORATION                                                                     
    Updated resource statement includes 97mt of measured, 500mt of indicated    
    and 734mt of inferred resources on the Smitspan property which              
    encompasses the entire Phase 1 project area referred to above.              
The next phase of drilling includes large diameter (123mm and 165mm)        
    holes for geotechnical, hydro-geological and coal processing testwork.      
    Upon completion the additional information will allow for the objectives    
    of the BFS to be met with regard to increased confidence levels and         
reduced tolerances on capex/opex estimations, as well as provide the        
    specific technical and qualitative analysis referred to above.              
CORPORATE                                                                       
    During the period it was decided that the best mechanism for increasing     
shareholder value would be via a competitive process to attract and         
    secure an appropriate partner to develop its substantial Waterberg          
    Project. Firestone has therefore embarked on a process to invite selected   
    companies to submit proposals to become a cornerstone investor. BBY         
Limited has been appointed as Corporate Advisor to the process and has a    
    strong track record of securing funding and cornerstone investors for       
    Australian and international resource companies.                            
OVERVIEW                                                                        
Pre-Feasibility Study                                                           
As stated earlier the drilling programme has been designed to be able to        
respond to specific customer requirements and ensure that the technical         
understanding of the resource and confidence therein is at a high level.        
During the quarter the Preliminary Feasibility Study (PFS) report on the        
Waterberg Coal JV Project report was reviewed.  The BFS activities are being    
prioritised to meet the required confidence and tolerance levels of the         
project.                                                                        
Environmental and Socio-Economic Impact Assessment                              
During the quarter, Firestone Energy continued with the finalisation of its     
drafts of Environmental Management Plan and Social and Labour Plan Impact       
Assessment (SEIA) documentation in accordance with Department of Mineral        
Resources requirements.  During the first quarter of 2010, stakeholder          
meetings to discuss and receive questions on the SEIA will be held at the       
Lephalale Local Municipality and Waterberg District Municipality.               
Mining Right Application                                                        
The Company finalised the social and labour plan studies as part of finalising  
the environmental management plan documentation.   The Mining Right             
Application and associated social and labour plan is scheduled for submission   
during May 2010.                                                                
Business Development                                                        
    Firestone Energy continues to engage in extensive market and business       
    development activities with the objective of identifying and                
    communicating with potential customers.  Further exploratory drilling has   
been planned in response to potential metallurgical coal demand.            
    The Company is participating in working committees with potential key       
    strategic alliance partners, including emerging miners, to explore          
    synergies and address constraints of accessing competitively priced rail    
and port infrastructure.                                                    
    For further information please contact:                                     
    Information in this report that relates to exploration results, coal        
    resources or reserves on the properties Smitspan 306LQ, Hooikraal 315LQ,    
Minnasvlakte 258LQ and Massenberg 305LQ is based on information compiled    
    by Ms Catherine Telfer who is employed by Venmyn Rand (Pty) Ltd and is a    
    member of The Australian Institute of Mining and Metallurgy and The South   
    African Institute of Mining and Metallurgy. Ms Telfer has sufficient        
experience which is relevant to the style of mineralisation and type of     
    deposit under consideration and to the activity which she is undertaking    
    to qualify as a Competent Person as defined in the 2004 Edition of the      
    "Australasian Code for the Reporting of Exploration Results, Mineral        
Resources and Ore Reserves". Ms Telfer consents to the inclusion in the     
    report of the matters based on her information in the form and context in   
    which it appears                                                            
    For further information please contact:                                     
John Wallington                                                             
    Managing Director                                                           
    +61 (08) 9381-2755                                                          
    About Firestone Energy                                                      
Firestone Energy is an independent Australian exploration company focused   
    on developing coal projects in South Africa. The company is currently       
    exploring the richly endowed Waterberg coal field in the Limpopo Province   
    of South Africa.                                                            
The Company is committed to value-added growth through becoming an          
    independent coal and energy producer at its projects in South Africa.       
The Company has entered into three joint ventures with Sekoko Resources, a      
South African black empowerment company (BEE) and Sekoko has two directors on   
the Board of Firestone Energy.                                                  
Corporate Details                                                               
ASX: FSE                                                                        
JSE: FSE                                                                        
Issued Capital:                                                                 
2,331 million ordinary shares                                                   
Major Shareholders:                                                             
Sekoko Resources (Pty) Ltd                                                      
Colbern Fiduciary Nominees Ltd                                                  
Bell Potter Nominees Ltd                                                        
Directors and Officers:                                                         
Non Executive Directors:                                                        
John Dreyer (Chairman)                                                          
Timothy Tebeila (Deputy Chairman)                                               
Amanda Matthee                                                                  
Colin McIntyre                                                                  
Managing Director                                                               
John Wallington                                                                 
Company Secretary                                                               
Rance Dorrington                                                                
Contact:                                                                        
Level 1, 63 Hay Street                                                          
Subiaco, Western Australia 6008                                                 
Tel: +61 (0)8 9381 2755                                                         
Web: www.firestoneenergy.com.au                                                 
Pretoria                                                                        
29 April 2010                                                                   
Sponsor and Corporate Advisor                                                   
River Group                                                                     
Date: 29/04/2010 07:43:01 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: