Not logged in
  Home   Markets   Shares   Funds   Portfolio   Toolbox   Charting   Alerts   Directory   
 Admin   

Tue 15 Jun 2010, 17:12 NHM - Northam Platinum Limited - Northam advises revised operating parameters
NHM
NHM                                                                             
NHM - Northam Platinum Limited - Northam advises revised operating parameters   
for its Booysendal project                                                      
NORTHAM PLATINUM LIMITED                                                        
(Registration number 1977/003282/06                                             
(Incorporated in the Republic of South Africa)                                  
JSE Code: NHM           ISIN: ZAE000030912                                      
("Northam" or "the group")                                                      
Northam advises revised operating parameters for its Booysendal project         
The management of Northam advises that it has completed an optimisation exercise
on the Booysendal feasibility study, released to the market in the fourth       
quarter of the 2009 calendar year.  Following approval by the board of directors
of Northam, preparatory work is proceeding on creating access and other         
infrastructural installations at the company`s 100% owned Booysendal asset on   
the eastern limb of the Bushveld Complex, which contains a resource of more than
100 million ounces (3PGM+AU).                                                   
The purpose of the optimisation study was to determine whether further value    
could be extracted from the first phase of the Booysendal project.  The results 
indicate that:                                                                  
    -    the start-up of production could be accelerated;                       
-    the mining layout could support a higher rate of production; and       
    -    this would result in lower unit operating costs.                       
On surface, the concentrator plant layout has been optimised to take account of 
the higher run of mine (ROM) production, resulting in a more efficient process  
flow and a smaller environmental footprint. Commenting on the results of the    
optimisation process, Northam chief executive Glyn Lewis said today, "The value 
engineering process has been a more than useful exercise, with results yielding 
an enhanced return on a more robust project than we had initially envisaged."   
The optimisation study included a review and update of initial capital          
expenditure estimates.  The total project capital expenditure has increased from
R3.1 billion (June 2009 money terms) to R3.6 billion (March 2010 money terms)   
reflecting the effects of inflationary increases on the one hand, and on the    
other, the firmer estimates for a larger operation.  Overall, the total capital 
expenditure estimate is slightly more efficient per unit of designed production 
(both in terms of tonnes milled and production ounces per annum (3PGM+Au)).     
The acceleration of production build-up follows on the rescheduling of          
construction: preparatory work is currently in progress to start the            
establishment of the on-reef boxcut in the first half of F2011. The remainder of
the work, including the reverse decline adit, bulk earthworks for the           
concentrator and offices, permanent access ways and pipelines, will start as    
soon as the environmental permitting is obtained.                               
Mill throughput to the plant will increase to 150 000 tonnes per month (187 500 
ROM tonnes through the DMS), an increase of 25%.  For a graphic representation  
of the build-up of production see the Northam website - www.northam.co.za       
Power supply and energy efficiency measures                                     
The revised mine design and higher rate of production are, at full capacity,    
expected to result in electricity consumption exceeding the ESKOM approved 20MVA
during peak demand periods.                                                     
These requirements will be fulfilled by self-generation of power on site (5MVA) 
during peak demand times. This will continue until ESKOM is able to supply      
additional power - currently estimated to be by 2015.                           
The revised design also makes provision for an energy management system and the 
introduction of energy recovery strategies. Orepass capacity is being improved  
which will minimise the requirement for decline conveyors to run during peak    
shift times.  In addition, cycle efficiencies and optimised equipment selection 
will maximise output in each section, and at the same time reduce the number of 
sections required to operate.                                                   
In summary                                                                      
                                       Optimisation case   Feasibility case     
Design capacity (ROM tpm)               187 500             150 000             
PGM ounces per annum (3PGM+Au)          162 000             130 000             
First concentrate                       Jan 2013            May 2013            
Total cash costs (ROM R/t)              364                 404                 
Total cash costs (milled R/t)           455                 505                 
Capital expenditure                                                             
Establishment of mine (R million)       2 034               1 369               
Concentrator (Rm)                       1 125               1 009               
Other  (Rm)                            465                 668                  
Total (R million)                       3 624               3 046               
Funding                                                                         
With capital expenditure requirements for Booysendal peaking in mid 2012,       
Northam remains confident that the development of the Booysendal mine can be    
funded from a combination of internal retentions and debt instruments.  Progress
has been made in exploring various options in this regard.                      
Distributed by:                                                                 
Russell & Associates, Johannesburg                                              
Tel: +27 (0)11 880 3924                                                         
Fax: +27 (0)11 880 3788                                                         
Johannesburg                                                                    
15 June 2010                                                                    
Sponsor                                                                         
Barnard Jacobs Mellet Corporate Finance (Pty) Limited                           
Date: 15/06/2010 17:12:02 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.                                          
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: