Tue 13 Jul 2010, 14:02 PAM - Palabora Mining Company Limited - Second Quarter 2010 - Operations
PAM
PAM                                                                             
PAM - Palabora Mining Company Limited - Second Quarter 2010 - Operations        
Overview And Production Statistics                                              
PALABORA MINING COMPANY LIMITED                                                 
(Incorporated in the Republic of South Africa)                                  
Registration number - 1956/002134/06                                            
JSE Code: PAM        ISIN: ZAE000005245                                         
("Palabora" or "the Company")                                                   
SECOND QUARTER 2010 - OPERATIONS OVERVIEW AND PRODUCTION STATISTICS             
                                                                                
                           2Q     3Q      4Q      1Q      2Q     1H        1H   
                         2009   2009    2009    2010    2010   2009      2010   
Palabora mine                                                                   
Tonnes hoisted (`000                           2,839   2,748  5,975     5,587   
tonnes)                  3,009  2,978   2,585                                   
Ore treated (`000       2,940  2,792   2,809   2,784   2,861  5,729     5,645   
tonnes)                                                                         
                         0.68   0.66    0.67    0.66    0.64   0.68      0.65   
Average ore grade:                                                              
copper (%)                                                                      
76.1   61.8    65.8    61.8    57.9  143.2     119.7   
Copper concentrates                                                             
produced                                                                        
(`000 tonnes)                                                                   
29.9   31.1    30.5    29.8   31.09   30.2      30.4   
Average concentrate                                                             
grade:                                                                          
copper (%)                                                                      
22.7   19.3    20.1    18.4   18.00   43.2      36.4   
Copper in                                                                       
concentrates (`000                                                              
tonnes)                                                                         
Palabora                                                                        
smelter/refinery                                                                
New concentrate           68.0   58.5    67.3    57.7    59.6  140.8     117.3  
smelted on site (`000                                                           
tonnes)                                                                         
                         18.9   12.5    14.3    12.4    14.7  39.10      27.1   
New copper anodes                                                               
produced                                                                        
(`000 tonnes)                                                                   
                         19.5   13.8    15.1    12.0    13.8   40.5      25.8   
Refined new copper                                                              
produced                                                                        
(`000 tonnes)                                                                   
By-products:                                                                    
Magnetite concentrate      617  758.7   697.2   754.1   780.4  1,389   1,534.5  
(`000 tonnes)                                                                   
Nickel contained            33     29    11.4    18.5    14.7     54     33.20  
(tonnes)                                                                        
Copper sold as             2.1    3.9     4.5     2.5     2.6    2.1       5.1  
concentrate (`000                                                               
tonnes)                                                                         
Vermiculite plant                                                               
Vermiculite produced        46     48      50      54      46     98       100  
(`000 tonnes)                                                                   
Palabora, a member of the Rio Tinto Group of Companies, situated in the Ba-     
Phalaborwa area of Limpopo, operates a large block cave copper mine and smelter 
complex.                                                                        
Daily production from the underground mine averaged 30,196 tonnes for the       
quarter ended 30 June 2010. The production during the quarter was 3% lower than 
the previous quarter and 9% lower than the corresponding period in 2009, mainly 
due to Winder repairs and low availability of Long Haul Dumps ("LHD").          
Preventative maintenance is ongoing and winder drum replacement is scheduled for
early 2011.                                                                     
In total, 2,747,862 tonnes of ore were hoisted during the quarter with a copper 
grade of 0.64%. Average concentrate grade was 4% higher than the previous       
quarter and the corresponding period in 2009 due to higher proportion of high   
grade slag reprocessed and discontinuance of toll milling of marginal ore which 
was yielding lower concentrate grade.                                           
Ore treated was 3% higher than the previous quarter and 3% lower than the       
corresponding period in 2009. This was affected by lower underground production 
due to the Winder repairs and the LHD`s availability.                           
Copper concentrate production was 6% lower than the previous quarter and 24%    
lower than the corresponding period in 2009. This was mainly due to a           
combination of a 44% increase in concentrate inventory of copper thickeners and 
a 90% drop in toll milling concentrate. The increase in inventory resulted from 
the processing of a higher tonnage of slag and an increase in the fineness of   
the feed to the filter plant which reduced the throughput of the rotary drier   
due to high feed moisture. The drop in toll milling concentrate was caused by   
the changeover to toll milling of non-copper bearing ore.                       
Copper in concentrate was 2% lower than the previous quarter and 21% lower than 
the corresponding period in 2009, mainly due to similar reasons as copper       
concentrate production above.                                                   
The new concentrate smelted was 3% higher sequentially and 12% lower than the   
corresponding period in 2009. This was mainly due to maintenance and replacement
of the Wolff cranes and rebuild of the reverb bath.                             
New anode production was 19% higher sequentially and 22% lower than the         
corresponding period in 2009. The year on year variance was due to low feed     
rates at the reverbratory furnace as a result of downtime at the furnace bath   
and maintenance and replacement of the Wolff cranes. Process improvement and    
technical consultants were engaged during the first quarter to address these    
issues. As a result the Wolff cranes and the furnace bath came into full        
operation during the second quarter. Normal production levels are expected in   
the next quarter.                                                               
Magnetite                                                                       
Magnetite production was 4% higher sequentially and 27% higher than the         
corresponding period in 2009, as a result of increased stockpile reclaims. The  
Transnet rail strike impacted shipments of magnetite reducing sales by 120,000  
tonnes in June 2010.                                                            
Vermiculite Operations                                                          
Vermiculite production was 15% lower sequentially due to furnace related        
production challenges.                                                          
The above information has not been reviewed or reported on by the Company`s     
auditors.                                                                       
Phalaborwa                                                                      
13 July 2010                                                                    
Sponsor:                                                                        
Barnard Jacobs Mellet Corporate Finance (Proprietary) Limited                   
Date: 13/07/2010 14:02:01 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.                                          
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: