Thu 21 Jul 2011, 8:00 LON - Lonmin Plc - Third quarter 2011 production report & interim management
LON
LOLMI                                                                           
LON - Lonmin Plc - Third quarter 2011 production report & interim management    
statement                                                                       
Lonmin Plc (Incorporated in England and Wales)                                  
(Registered in the Republic of South Africa under registration number           
1969/000015/10)                                                                 
JSE code: LON                                                                   
Issuer Code: LOLMI & ISIN: GB0031192486 ("Lonmin")                              
21 July 2011                                                                    
Lonmin Plc                                                                      
Third Quarter 2011 Production Report                                            
& Interim Management Statement                                                  
Lonmin Plc, the world`s third largest Platinum producer, today announces its    
production results for the three and nine months to 30 June 2011and interim     
management statement (unaudited).                                               
Overview                                                                        
During the third quarter, momentum of the business was impacted by two          
fatalities in April and the illegal industrial stoppage in May at the Karee     
operations. We have since made good progress in restoring production and expect 
to be back to normal operating levels by August. Considerable progress has been 
made with the safety initiatives we embarked on. We continue to intensify our   
focus on these initiatives and our LTIFR has fallen during the quarter from     
5.4 at the half year to 5.1 as at 30 June 2011.                                 
Year to date, our underground tonnage mined and milled is up on the comparable  
prior year period and our metals in concentrate has also increased.             
Third Quarter Production                                                        
Mining                                                                          
Our underground operations at Marikana produced 2.4 million tonnes during the   
third quarter of the 2011 financial year, a decrease of 8.1% from the third     
quarter of the 2010 financial year. The decrease was across all the underground 
mining operations. The overall reduction at Karee of 7.2%, when compared to     
prior year quarter was due to the unprotected industrial action which resulted  
in a loss of 258,000 tonnes of production.  Production at Westerns, Middelkraal 
and Easterns combined decreased by 8.5% against the prior year as challenging   
ground conditions and mechanical breakdowns at Saffy and Hossy persisted and    
the planned decline at Newman continued. The impact of Section 54 shut downs    
was 132,000 tonnes in lost production during the quarter, mainly at our K3 and  
E1 shafts where we experienced fatalities in April 2011. This compares to a     
loss in production during the same period last year of around 109,000 tonnes.   
Management induced safety stoppages, particularly following the fatalities      
in April resulted in 44,000 tonnes of lost production.                          
Production at our Merensky opencast operations increased by 53.1% from the      
prior year period as opencast production was ramping up at that time.           
Overall, tonnes mined of 2.5 million for the quarter, reflected a decrease of   
168,000 tonnes, equivalent to a 6.2% reduction against the prior year.          
Concentrators, Smelting and Refining                                            
Total tonnes milled in the quarter were flat year on year at 2.8 million with   
the contribution from opencast contributing an additional 50,000 tonnes         
offsetting the slightly reduced underground tonnes milled.                      
Underground milled head grade was down 0.13 grammes per tonne, or 2.7% to       
4.48 grammes per tonne (5PGE+Au) when compared to 4.60 grammes per tonne in the 
prior year period. This reflects the continued increase in the proportion of    
Merensky ore in the underground ore mix and lower grade ore at our UG2          
operations. The overall milled head grade was 4.37 grammes per tonne, a         
decline of 3.9% when compared to the prior year period as it includes the       
impact of increased contribution from the lower grade opencast ore.             
Underground and overall concentrator recoveries were broadly flat when compared 
with the prior year period reflecting a high performing and stable operating    
environment at our concentrators. The opencast concentrator recoveries improved 
by 2.0 percentage points                                                        
Platinum in concentrate from the Marikana operations and overall total Platinum 
in concentrate was 158,490 and 164,212 ounces, respectively, a 3.0% and 3.2 %   
decrease over the prior year quarter.                                           
Total refined production for the third quarter was up 81.4% at 166,832 Platinum 
ounces, when compared to the prior year period which was impacted by the down   
time of the Number One Furnace during the prior year quarter.                   
Sales and Pricing                                                               
Platinum sales of 160,499 ounces were 74.5% higher than the prior year quarter, 
as a result of the lower production in the prior year, resulting from the       
Number One Furnace outage.                                                      
The US Dollar price basket, at US$1,303, was 11.1% higher than the prior year   
quarter but 2.2 % lower than the second quarter. The corresponding Rand basket  
price was however 0.1% lower than the prior year and 5.2% weaker when compared  
to the second quarter.                                                          
Nine Month Production                                                           
Total tonnes mined during the first nine months of the 2011 financial year      
were 8.4 million tonnes, an increase of 0.5 million tonnes or 6.3% from the     
prior year period. This is firstly due to a significant increase in production  
at the Karee operations in the first two quarters, which resulted in an increase
of 7.2% when compared to the prior year period. Secondly, Easterns increased    
its production by 98,000 tonnes when compared against the prior year period and 
the opencast operations contributed an additional 0.4 million tonnes. These     
increases were partly offset by the fall in production at Westerns as Newman    
continues to decline, together with mechanical breakdown and ground condition   
challenges at Middelkraal`s Hossy and Saffy shafts, which have impacted ramp    
up production. Section 54 shut downs during the nine month period resulted in   
a loss of around 201,000 tonnes. This compares to around 258,000 tonnes for     
the same period last year.                                                      
Total tonnes milled during the nine months of the 2011 financial year increased 
by 10.9% to 8.8 million tonnes when compared to the same period in the prior    
year as a result of milling opencast stockpiles and an increase in mining       
production. The total milled head grade however, fell by 6.4% to 4.35 grammes   
per tonne (5PGE+Au) when compared to the prior year period. This is as a result 
of the fall in underground head grade and the increase of lower grade Merensky  
ore, some of which is from opencast mining. Overall concentrator recoveries     
improved in the nine month period to 85.2% from 84.6% in the prior year period, 
with marked improvements in the opencast recoveries. The concentrators produced 
a total of 519,075 saleable ounces of Platinum in concentrate in the nine       
months, representing a 5.6% year on year increase.                              
Total refined production in the nine months of the 2011 financial year was      
483,665 Platinum ounces and 982,387 PGM ounces, an increase of 26.0% and        
25.7% respectively when compared to the prior year period. The increase         
reflects the impact of the Number One Furnace incidents in the prior year       
period.                                                                         
Final metal sales for the nine months were 478,804 ounces of Platinum and       
973,695 ounces of PGMs, an increase of 24.7% and 23.9% respectively, year on    
year.                                                                           
Outlook                                                                         
Since the resumption of normal operations at Karee we have made steady progress 
giving us confidence that absent further safety stoppages and external strike   
actions impacting our operations, we will achieve our adjusted full year        
guidance of sales of around 720,000 Platinum ounces for the current financial   
year. As described in our Guidance Update on 10 June 2011, unit costs were      
negatively impacted by the Karee disruption. We are now able to clarify the     
impact of the resultant reduced production on our unit costs and are            
consequently increasing our guidance from an annual increase of around 8%       
to around an 11% increase in unit costs for the full year.                      
ENQUIRIES:                                                                      
Investors / Analysts:                                                           
Tanya Chikanza                          +44 (0) 207 201 6007                    
Head of Investor Relations                                                      
Media:                                                                          
Cardew Group                                 +44 (0) 207 930 0777               
Rupert Pittman / Emma Crawshaw                                                  
Financial Dynamics                           +27 (0) 11 214 2402                
Dani Cohen / Sue Vey                                                            
                                      3        3          9       9             
                                      months   months     months  months        
to 30    to 30      to 30   to 30         
                                      June     June       June    June          
                                      2011     2010       2011    2010          
Tonnes    Marikana     Karee1    kt    901      971        3,115   2,907        
mined                                                                           
                      Westerns  kt    794      852        2,519   2,696         
                      1                                                         
                      Middelkr  kt    436      496        1,355   1,362         
aal1                                                      
                      Easterns  kt    246      265        860     762           
                      1                                                         
                      Undergro  kt    2,376    2,584      7,849   7,726         
und                                                       
                      Opencast  kt    129      84         465     91            
                      Total     kt    2,505    2,668      8,314   7,817         
         Pandora      Undergro  kt    38       43         121     120           
attributabl  und                                                       
         e2                                                                     
         Lonmin       Undergro  kt    2,414    2,626      7,970   7,846         
                      und                                                       
Platinum     Opencast  kt    129      84         465     91            
                      Total     kt    2,543    2,711      8,434   7,937         
                      % UG2     %     74.1%    76.0%      72.9%   77.0%         
                                                                                
Tonnes    Marikana     Undergro  kt    2,560    2,614      7,835   7,513        
milled3                und                                                      
                      Opencast  kt    118      68         668     129           
                      Total     kt    2,678    2,682      8,503   7,642         
Pandora4     Undergro  kt    92       99         268     265           
                      und                                                       
         Lonmin       Undergro  kt    2,652    2,712      8,103   7,779         
         Platinum     und                                                       
Head      g/    4.48     4.60       4.53    4.69          
                      grade5    t                                               
                      Recovery  %     85.0%    85.1%      85.4%   84.7%         
                      rate6                                                     
Opencast  kt    118      68         668     129           
                      Head      g/    2.07     2.51       2.17    2.25          
                      grade5    t                                               
                      Recovery  %     80.9%    78.9%      81.6%   63.8%         
rate6                                                     
                      Total     kt    2,770    2,780      8,771   7,908         
                      Head      g/    4.37                4.35    4.65          
                      grade5    t              4.55                             
Recovery  %     84.9%    85.0%      85.2%   84.6%         
                      rate6                                                     
                                       3       3          9       9             
                                       months  months     months  months        
to 30   to 30      to 30   to 30         
                                       June    June       June    June          
                                       2011    2010       2011    2010          
Metals    Marikana    Platinum    oz    158,490 163,311    502,279 473,914      
in                                                                              
concentr                                                                        
ate7                                                                            
                     Palladium   oz    73,553  76,922     234,971 222,097       
Gold        oz    3,875   4,067      13,008  10,557        
                     Rhodium     oz    20,940  22,350     65,923  66,152        
                     Ruthenium   oz    33,164  35,259     104,255 102,152       
                     Iridium     oz    7,088   7,683      22,652  22,318        
Total PGMs  oz    297,110 309,592    943,088 897,190       
                     Nickel8     MT    762     809        2,567   2,085         
                     Copper8     MT    479     493        1,626   1,288         
         Pandora4    Platinum    oz    5,722   6,303      16,796  17,564        
Palladium   oz    2,683   2,991      7,862   8,267         
                     Gold        oz    39      44         115     121           
                     Rhodium     oz    868     987        2,557   2,769         
                     Ruthenium   oz    1,386   1,533      4,040   4,225         
Iridium     oz    226     257        664     712           
                     Total PGMs  oz    10,924  12,113     32,035  33,658        
                     Nickel8     MT    9       10         27      27            
                     Copper8     MT    5       6          15      15            
Lonmin      Platinum    oz    164,212 169,614    519,075 491,478       
         Platinum                                                               
                     Palladium   oz    76,236  79,913     242,833 230,364       
                     Gold        oz    3,913   4,110      13,123  10,678        
Rhodium     oz    21,808  23,336     68,480  68,920        
                     Ruthenium   oz    34,551  36,792     108,295 106,377       
                     Iridium     oz    7,314   7,941      23,316  23,030        
                     Total PGMs  oz    308,034 321,706    975,123 930,848       
Nickel8     MT    771     819        2,594   2,111         
                     Copper8     MT    485     499        1,641   1,303         
                                    3 months 3 months    9 months   9 months    
                                    to 30    to 30       to 30      to 30       
June     June        June       June        
                                    2011 -   2010 -      2011 -     2010 -      
                                    Act      Act         Act        Act         
Refined  Lonmin      Platinum  oz    166,021  91,928      446,999    383,670    
product  refined                                                                
ion      Metal                                                                  
        production                                                              
                    Palladiu  oz    76,086   57,230      214,473    207,522     
m                                                           
                    Gold      oz    4,291    3,080       10,955     10,517      
                    Rhodium   oz    14,560   16,823      53,084     59,769      
                    Rutheniu  oz    37,183   19,621      109,589    92,370      
m                                                           
                    Iridium   oz    1,641    3,899       15,052     24,321      
                    Total     oz    299,782  192,581     850,153    778,169     
                    PGMs                                                        
Toll        Platinum  oz    812      25          36,665     204         
        refined                                                                 
        Metal                                                                   
        production                                                              
Palladiu  oz    449      26          49,084     89          
                    m                                                           
                    Gold      oz    13       -           2,879      -           
                    Rhodium   oz    130      1           14,022     810         
Rutheniu  oz    408      1,242       24,408     1,754       
                    m                                                           
                    Iridium   oz    86       360         5,177      360         
                    Total     oz    1,898    1,654       132,235    3,216       
PGMs                                                        
        Total       Platinum  oz    166,832  91,952      483,665    383,873     
        refined                                                                 
        PGMs                                                                    
Palladiu  oz    76,535   57,256      263,557    207,611     
                    m                                                           
                    Gold      oz    4,303    3,080       13,833     10,517      
                    Rhodium   oz    14,690   16,824      67,106     60,578      
Rutheniu  oz    37,591   20,864      133,997    94,124      
                    m                                                           
                    Iridium   oz    1,727    4,259       20,229     24,681      
                    Total     oz    301,679  194,234     982,387    781,385     
PGMs                                                        
        Base        Nickel9   MT    914      560         3,027      2,110       
        metals                                                                  
                    Copper9   MT    560      274         1,775      1,178       

Sales    Lonmin      Platinum  oz    160,499  91,952      478,804    383,874    
        Platinum                                                                
                    Palladiu  oz    64,573   54,113      254,104    204,468     
m                                                           
                    Gold      oz    3,812    2,718       12,449     10,131      
                    Rhodium   oz    14,547   16,146      69,353     63,447      
                    Rutheniu  oz    43,008   22,348      134,781    98,219      
m                                                           
                    Iridium   oz    7,700    5,231       24,203     25,898      
                    Total     oz    294,138  192,507     973,695    786,036     
                    PGMs                                                        
Nickel9   MT    890      410         3,001      1,795       
                    Copper9   MT    486      282         1,563      1,288       
                    Chrome9   MT    173,608  166,697     415,354    506,224     
                                     3        3         9        9              
months   months    months   months         
                                     to 30    to 30     to 30    to 30          
                                     June     June      June     June           
                                     2011 -   2010 -    2011 -   2010 -         
Act      Act       Act      Act            
Average  Platinum              $/o    1,764    1,595     1,772    1,514         
prices                         z                                                
        Palladium             $/o    754      481       755      422            
z                                                 
        Gold                  $/o    1,524    1,136     1,247    1,128          
                              z                                                 
        Rhodium               $/o    2,082    2,592     2,290    2,398          
z                                                 
        Ruthenium             $/o    172      214       170      168            
                              z                                                 
        Iridium               $/o    1,023    614       898      460            
z                                                 
        $ basket excl. by-    $/o    1,303    1,172     1,294    1,093          
        product revenue11     z                                                 
        R basket excl. by-    R/o    8,872    8,884     8,954    8,203          
product revenue11     z                                                 
        R basket incl. by-    R/o    9,533    9,328     9,593    8,594          
        product revenue12     z                                                 
        Nickel9               $/M    21,677   22,002    22,074   17,249         
T                                                 
        Copper9               $/M    8,927    7,244     8,784    6,598          
                              T                                                 
        Chrome9               $/M    36       2         30       2              
T                                                 
                                                                                
Exchang  Average rate for      R/$                                              
eRates   period13                     6.77     7.53      6.85     7.49          
Closing               R/$                                               
        rate                         6.76     7.66      6.76     7.66           
                                                                                
Notes:                                                                          
1      The management structure in mining is comprised of four business         
      units. Karee includes the shafts K3, 1B and 4B and will also              
      include K4 once production commences. Westerns comprises Rowland,         
      Newman and ore purchases from W1. Middelkraal represents Hossy and        
Saffy. Easterns includes E1, E2 and E3.                                   
2      Pandora attributable tonnes mined includes Lonmin`s share (42.5%)        
      of the total tonnes mined on the Pandora joint venture.                   
3      Tonnes milled excludes slag milling.                                     
4      Lonmin purchases 100% of the ore produced by the Pandora joint           
      venture for onward processing which is included in downstream             
      operating statistics.                                                     
5      Head grade is the grammes per tonne (5PGE + Au) value contained in       
the tonnes milled and fed into the concentrator from the mines            
      (excludes slag milled).                                                   
6      Recovery rate in the concentrators is the total content produced         
      divided by the total content milled (excluding slag).                     
7      Metals in concentrate include metal derived from slag processing         
      and have been calculated at industry standard downstream                  
      processing losses to present produced saleable ounces.                    
8      Corresponds to contained base metals in concentrate.                     
9      Nickel is produced and sold as nickel sulphate crystals or               
      solution and the volumes shown correspond to contained metal.             
      Copper is produced as refined product but typically at LME grade          
      C. Chrome is produced in the form of chromite concentrate and             
volumes shown are in the form of chromite.                                
10     Concentrate and other sales have been adjusted to a saleable ounce       
      basis using industry standard recovery rates.                             
11     Basket price of PGMs is based on the revenue generated in Rand and       
Dollar from the actual PGMs (5PGE + Au) sold in the period based          
      on the appropriate Rand / Dollar exchange rate applicable for each        
      sales transaction.                                                        
12     As per note 11 but including revenue from base metals.                   
13     Exchange rates are calculated using the market average daily             
      closing rate over the course of the period.                               
Date: 21/07/2011 08:00:45 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.                                          
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: