Not logged in
  Home   Markets   Shares   Funds   Portfolio   Toolbox   Charting   Alerts   Directory   
 Admin   

Fri 29 Jul 2011, 7:26 CZA - Coal of Africa Limited - Report for the quarter ended 30 June 2011
CZA
CZA                                                                             
CZA - Coal of Africa Limited - Report for the quarter ended 30 June 2011        
Coal of Africa Limited                                                          
(previously "GVM Metals Limited")                                               
(Incorporated and registered in Australia)                                      
(Registration number ABN 008 905 388)                                           
ISIN AU000000CZA6                                                               
JSE/ASX/AIM share code: CZA                                                     
("CoAL or the "Company")                                                        
REPORT FOR THE QUARTER ENDED 30 JUNE 2011                                       
Coal of Africa Limited provides its operational report for the quarter ended    
30 June 2011. A copy of this report is available on the Company`s website,      
www.coalofafrica.com.                                                           
Highlights                                                                      
-    Washing of the Makhado coking coal project ("Makhado Project") bulk        
    sample completed at Exxaro Resources Limited`s ("Exxaro") Tshikondeni       
Colliery.                                                                   
-    1,256,825 tonnes (Q3: 1,229,584 tonnes) of run of mine ("ROM") and         
    664,865 tonnes (Q3: 717,367 tonnes) of export quality coal produced at      
    the Woestalleen and Mooiplaats thermal collieries.                          
-    Sales of Export coal increased to 492,781 tonnes in the June 2011 quarter  
    from 198,347 tonnes in the March 2011 quarter, due to increased             
    operational performance on the Maputo Rail Corridor and additional          
    throughput capacity at the Matola Terminal in Maputo, Mozambique.           
-    Transitioning the Group`s Mooiplaats thermal coal colliery ("Mooiplaats    
    Colliery") from a contract mining operation to an owner-managed             
    operation.                                                                  
-    Appointment of Mr Wayne Koonin as Financial Director.                      
-    Total cash balance and available facilities at the end of the quarter of   
    A$34.88 million.                                                            
Post quarter highlights                                                         
In early July 2011, the South African Department of Environmental Affairs       
("DEA") granted authorisation for rectification at the Vele Colliery in terms   
of Section 24G of the National Environmental Management Act (Act No. 107 of     
1998) as amended ("NEMA"). The authorisation contains specific conditions       
which the Company will be required to fulfil due to the uniqueness of the       
area. Completion of the construction and commissioning phase of the plant and   
mine is expected to take place within six to nine months from the restart in    
August 2011 and is ultimately intended to ramp up to an initial production      
profile of 1 million tonnes per annum.                                          
Commenting today, Mr John Wallington, Chief Executive Officer of CoAL said:     
"The increased throughput at the Matola Terminal combined with mining and rail  
improvements, resulted in a significant increase in export coal sales during    
the quarter."                                                                   
"At the Mooiplaats Colliery, we have taken an important step in the             
development cycle of the mine by transitioning from an outsource contractor to  
an owner operated mine. As a result of this change, approximately 300           
employees previously employed by the contractor are now employed directly by    
Mooiplaats. The handover process has gone extremely well and we are confident   
that the expected operational and cost efficiencies will be realized."          
"During the quarter, significant progress was made on issues relating to the    
Vele Colliery. Importantly, following several months of intensive interaction   
and work with the various government departments, the Integrated Water Use      
Licence ("IWUL") was granted on 4 April 2011 and the Environmental              
Authorisation on 5 July 2011. However, as anticipated and with reference to     
the announcement released earlier today, on 28 July 2011, the NGO coalition     
has filed an appeal with the Minister of Environmental and Water Affairs        
against the granting of the IWUL. The Company has the right to file an appeal   
with the Minister to apply discretion in the matter to allow mining to          
continue and for the appeal to be heard in the normal course of events. We are  
in the process of assessing the appeal by the action groups and preparing the   
necessary submission to the Minister on an urgent basis."                       
"CoAL is committed to continue working closely with the various government      
departments, ensuring compliance with legislation as well as specific           
requirements stipulated by government in granting authorisation to recommence   
operations. Further announcements in this regard will be made in due course."   
QUARTERLY COMMENTARY                                                            
Woestalleen Colliery - Witbank Coalfield (100%)                                 
The outstanding safety record at the Zonnebloem colliery was sustained during   
the quarter with the site not recording a single lost time injury since its     
start-up in 2008. One lost time injury was recorded at the Woestalleen mines    
and processing plant ("Woestalleen Colliery") during the quarter and            
Management`s focus on safety remains a priority.                                
Production of ROM coal at Woestalleen`s open cast mines increased by 7%         
compared to the previous quarter, yielding 970,220 tonnes (Q3: 909,994 tonnes)  
of coal. Quarter on quarter production at the Zonnebloem colliery was up 30%    
with 955,872 ROM tonnes mined (Q3: 735,674 ROM tonnes). The Hartogshoop North   
colliery was mined out in the quarter yielding 14,348 ROM tonnes (Q3: 161,027   
ROM tonnes) and the Klipbank colliery, mined out in the previous quarter        
yielded zero ROM tonnes (Q3: 13,293 ROM tonnes).                                
The Woestalleen wash plant produced 503,625 saleable tonnes (Q3: 505,894        
saleable tonnes) of export quality coal. The plant produced a further 73,265    
saleable tonnes (Q3: 88,081 saleable tonnes) of lower grade product for Eskom,  
the South African electricity utility.                                          
An overall yield of 64.5% (Q3: 64.2%) was marginally lower than the previous    
quarter.                                                                        
Mooiplaats Colliery - Ermelo Coalfield (100%)                                   
Safety continues to be a focus at the Mooiplaats Colliery, where four lost      
time injuries were reported at the mine during the June 2011 quarter.           
Coal production for the three months decreased by 10.3%, from 319,590 ROM       
tonnes in the previous quarter, to 286,605 ROM tonnes in the June quarter. The  
decrease was primarily due to the transfer of mining operations from a          
contractor miner to CoAL as the operator. The transition to an owner managed    
mine will enable direct management of the operation and improve the overall     
performance of the mine. As part of this process, employees previously          
employed by the contractor, were transferred to the direct employ of the mine.  
All mining equipment was previously purchased and remains the property of the   
mine, thereby minimising disruptions during the transitional phase. Steps are   
underway to open the fifth underground section during the last quarter of this  
year, with all the necessary capital expenditure having already been incurred.  
Coal processed during the three months declined from 413,111 ROM tonnes in the  
March quarter, including 121,426 purchased ROM tonnes, to 321,105 ROM tonnes    
in the June quarter, including 31,274 purchased ROM tonnes.  A total of         
161,240 tonnes (Q3: 211,473 tonnes) of  export quality coal was produced and    
44,348 tonnes (Q3: 66,907 tonnes) of the lower grade product for Eskom.         
The overall yield of 64.0% (Q3: 67.4%) was lower quarter on quarter due to the  
high level of contamination mined by the contractor.                            
Subsequent to quarter end, following the switch from contract mining, the       
decline in production has been reversed along with an improvement in the        
contamination levels. Management continue to monitor the situation closely to   
ensure that the improvement in operational performance continues.               
Marketing and Logistics                                                         
Additional rail capacity created by Transnet Freight Rail earlier in the year   
supported the significant increase of export sales through the Matola           
Terminal. The purchase of 42,774 tonnes of third party coal and the completion  
of the port expansion contributed in the increase of export sales by 148% from  
198,347 tonnes in the March 2011 quarter to 492,781 tonnes in the June 2011     
quarter.                                                                        
In the June 2011 quarter, Woestalleen sold 264,813 tonnes (Q3: 356,986 tonnes)  
and Mooiplaats Colliery sold 63,233 tonnes (Q3: 61,155 tonnes) to domestic      
customers and Woestalleen Colliery sold 39,460 tonnes (Q3: 66,543) and          
Mooiplaats Colliery sold 69,242 tonnes (Q3: 52,649 tonnes) of lower grade coal  
to Eskom.                                                                       
Summary tables (tonnes)                                                         
Woestalleen     Mooiplaats       Total                
June 2011 quarter                                                               
ROM production             970,220         286,605          1,256,825           
                                                                                
ROM coal purchased         -               31,274           31,274              
                                                                                
Total coal processed       894,605         321,105          1,215,710           
                                                                                
Overall Yield              64.5%           64.0%            64.4%               
                                                                                
Total coal produced        576,890         205,588          782,478             
Export coal                503,625         161,240          664,865             
Middlings coal             73,265          44,348           117,613             
                                                                                
Saleable coal purchased    -               40,298           40,298              
                                                                                
Total coal sales           304,273         625,256          929,529             
Export                     -               492,781          492,781             
                                                                                
Inland                     264,813         63,233           328,046             
Eskom                      39,460          69,242           108,702             
                                                                                
Vele Coking Coal Project                                                        
As announced previously, the development phase of the Vele Colliery is near     
completion. No activity was undertaken at the colliery during the quarter as a  
result of the Compliance Notice served on the Company by the DEA in August      
2010.                                                                           
CoAL applied for an Integrated Water Use Licence ("IWUL") in November 2009 and  
had been liaising with the Department of Water Affairs ("DWA") to progress the  
application. During the quarter the DWA granted the IWUL, completing a          
significant outstanding requirement for commencement of operations at the       
colliery.                                                                       
The rectification papers previously submitted in terms of Section 24G of NEMA   
resulted in the Company being required to pay a ZAR9.25 million (A$1.26         
million) administrative fine to the DEA. The payment of the fine was a pre-     
condition to enable the DEA to adjudicate the application for rectification     
relating to the environmental authorisation for the Vele Colliery.              
This authorisation was granted on 5 July 2011, and contractors are being        
mobilised to recommence with the completion of the construction of mining and   
coal processing infrastructure at the mine site. As previously announced, the   
Company expects to bring Vele into production within six to nine months of the  
restart date. The construction activities, commissioning of the plant and       
recommencing production are being planned and implemented. At the time          
operations were halted in August 2010, work was 95% complete.                   
Due to the temperate climate and that no wet commissioning of the plant had     
taken place, there has been limited degradation to the plant and                
infrastructure whilst the mine was dormant. Upon recommencing activities, a     
full assessment will take place and the necessary steps implemented to address  
any issues that require remediation. The natural ingress of water into the pit  
over the past year requires dewatering prior to the recommencement of mining    
activities.                                                                     
On 28 July 2011, the Integrated Water Use Licence ("IWUL") for the Vele         
Colliery has been suspended in terms of Section 148(2) (b) of the South Africa  
National Water Act, No, 36 of 1998, due to an appeal to the Water Tribunal      
submitted by an NGO coalition. The appeal automatically suspends the licence    
unless the Minister of Water Affairs directs otherwise. In the interim, the     
Company is therefore unable to continue with activities at the Vele Colliery    
that require water use, however in anticipation of recommencing operations,     
the planning in relation to other construction and mining activities that do    
not require the use of water are ongoing.                                       
CoAL has the right to and is in the process of preparing an urgent appeal to    
the Minister requesting that the IWUL remains in full force and effect in this  
interim period and until the final conclusion of the appeal. If the Company is  
successful in its representation to the Minister the Company will be able to    
continue all activities, including the water uses per the IWUL.                 
Makhado Coking Coal Project                                                     
During the quarter, independent experts continued with the baseline social and  
environmental studies required for the Makhado Project New Order Mining Right   
("NOMR") application that was lodged with the DMR in January 2011.              
Consultation processes with interested and affected parties continued during    
the period. These will form part of the extensive economic, social and          
environmental impact studies required for the NOMR. The studies will result in  
the formulation of a detailed Environmental Management Programme for the        
Makhado Project.                                                                
The processing of the Makhado Project bulk sample at Exxaro`s Tshikondeni       
Colliery was completed during the quarter.  Samples of the washed product have  
been sent to ArcelorMittal South Africa`s ("AMSA") Vanderbijlpark facility for  
testing.                                                                        
The results of the tests are expected to facilitate the finalisation of the     
terms and conditions related to volumes and pricing for the proposed off-take   
agreement between CoAL and AMSA, as well as the finalisation of the Makhado     
Project Definitive Feasibility Study. Additional coking coal samples are being  
analysed at the Company`s Polokwane laboratory and further trial samples are    
being sent to potential export customers.                                       
The Definitive Feasibility Study is at an advanced stage and is expected to be  
tabled for consideration by the Board before calendar year end. Construction    
is anticipated to commence in mid 2012.                                         
Corporate Activity                                                              
Financial Director Appointment                                                  
During the quarter, CoAL announced the appointment of Mr Wayne Koonin as        
Financial Director. Mr Koonin has extensive international experience working    
in the financial role at Board level in exploration, development and operating  
mining companies, including coal. Mr Koonin has most recently been the Chief    
Financial Officer of Platmin Limited, a platinum mining company listed on the   
Toronto Stock Exchange, AIM and the JSE.                                        
Cash and Available Facilities                                                   
At 30 June 2011, total cash on hand and call deposits was A$34.88 million (31   
March 2011 : A$25.113 million) and undrawn loan facilities and standby credit   
arrangements was A$26.41 million (31 March 2011 : A$36.913 million). Quarter    
on quarter, total cash and available facilities remained in line with           
management expectations.                                                        
Authorised by                                                                   
John Wallington                                                                 
Chief Executive Officer                                                         
29 July 2011                                                                    
Johannesburg                                                                    
JSE Sponsor                                                                     
Macquarie First South Advisers (Pty) Ltd                                        
For more information contact:                                                   
John Wallington                                                                 
Chief Executive Officer                                                         
Coal of Africa                                                                  
+27 11 575 7423                                                                 
Wayne Koonin                                                                    
Finance Director                                                                
Coal of Africa                                                                  
+27 11 575 4363                                                                 
Shannon Coates                                                                  
Company Secretary                                                               
Coal of Africa                                                                  
+61 893 226 776                                                                 
Chris Sim/Romil Patel                                                           
Nominated Adviser                                                               
Evolution Securities                                                            
+44 20 7071 4300                                                                
Jos Simson/Emily Fenton                                                         
Financial PR                                                                    
Tavistock                                                                       
+44 207 920 3150                                                                
Melanie de Nysschen/ Annerie Britz/ Yvette Labuschagne                          
JSE Sponsor                                                                     
Macquarie                                                                       
+27 11 583 2000                                                                 
www.coalofafrica.com                                                            
About CoAL:                                                                     
CoAL is an AIM/ASX/JSE listed coal mining and development company operating in  
South Africa. CoAL`s key projects include the Vele Colliery (coking coal), the  
Makhado Project (coking coal) and the Mooiplaats and Woestalleen Collieries     
(both thermal coal).                                                            
The Mooiplaats Colliery commenced production in 2008 and is currently ramping   
up to produce 2 million tonnes per annum ("Mtpa"). CoAL`s Vele Colliery and     
Makhado Project are expected to start production in the first half of 2012 and  
the first half of 2013 respectively. These operations are targeted to           
collectively produce an initial 1Mtpa ramping up to a combined annual output    
of 10Mtpa of coking coal.                                                       
In 2010, CoAL completed the ZAR467m acquisition of NuCoal Mining (Pty) Limited  
("NuCoal"), a thermal coal producer with assets in South Africa in close        
proximity to CoAL`s Mooiplaats Colliery. NuCoal owns the Woestalleen Colliery,  
which has a number of off-take contracts in place and processes approximately   
2.5Mtpa of saleable coal for domestic and export markets. The Woestalleen       
Colliery also incorporates two beneficiation plants with a total processing     
capacity of 350,000 run of mine feed tonnes per month.                          
In November 2010, CoAL agreed to acquire the Chapudi coal project and several   
other coal exploration properties in the Soutpansberg coal basin in South       
Africa from the previous owners, including Rio Tinto. When completed, the       
acquisition of these projects will significantly extend the scale and scope of  
certain of CoAL`s existing projects in the region and will more than double     
the resource of the existing Makhado Project.                                   
Date: 29/07/2011 07:26:01 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.                                          
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: