Tue 18 Oct 2011, 15:39 EPS - Eastern Platinum Limited - Eastplats reports production results
EPS
EPS                                                                             
EPS - Eastern Platinum Limited - Eastplats reports production results           
for the quarter ended September 30, 2011                                        
EASTERN PLATINUM LIMITED                                                        
(Incorporated in Canada)                                                        
(Canadian Registration number BC0722783)                                        
(South African Registration number 2007/006318/10)                              
Share Code TSX: ELR ISIN: CA 2768551038                                         
Share Code AIM: ELR ISIN: CA 2768551038                                         
Share Code JSE: EPS ISIN: CA 2768551038                                         
October 18, 2011                                                                
Trading Symbol: ELR (TSX & AIM) EPS (JSE)                                       
NEWS RELEASE                                                                    
EASTPLATS REPORTS PRODUCTION RESULTS                                            
FOR THE QUARTER ENDED SEPTEMBER 30, 2011                                        
Eastern Platinum Limited ("Eastplats") reports operating results from the       
Crocodile River Mine ("CRM") for the third quarter ended September 30, 2011.    
Production statistics for the current quarter and historical quarters are as    
follows:                                                                        
                       Quarter ended                                            
Production statistics   Sep 30, 2011    June 20,   Mar 31,  Dec 31,  Sep 30,    
                                       2011       2011     2010     2010        
Ounces produced         26 955          20 528     25 387   32 752   37 798     
Run-of-mine tonnes      265 889         203 166    247 369  324 879  362 042    
hoisted                                                                         
Run-of-mine tonnes      261 280         201 986    245 500  327 872  357 219    
processed                                                                       
Development (meters)    3 976           3 562      4 219    3 501    3 299      
On-reef development     2 248           2 090      2 434    1 925    1 797      
(meters)                                                                        
Stoping units (square   40 594          31 828     44 674   53 044   50 892     
meters)                                                                         
Head grade              4.08            3.93       3.93     3.97     4.03       
(grams/tonne)                                                                   
Concentrator recovery   78%             76%        79%      78%      81%        
from ROM ore*                                                                   
Chrome dispatched       77 531          64 913     62 498   79 461   100 023    
(tonnes)                                                                        
*  Concentrator recovery has been rounded to the nearest percentage point.      
                             Increase (decrease)                                
Production statistics         Q3 2011 vs. Q2 2011     Q3 2011 vs. Q3 2010       
Ounces produced               6 427                   (10 843)                  
Run-of-mine tonnes hoisted    62 723                  (96 153)                  
Run-of-mine tonnes processed  59 294                  (95 939)                  
Development (meters)          414                     677                       
On-reef development (meters)  158                     451                       
Stoping units (square         8 766                   (10 298)                  
meters)                                                                         
Head grade (grams/tonne)      0.15                    0.05                      
Concentrator recovery from    2%                      (3%)                      
ROM ore*                                                                        
Chrome dispatched (tonnes)    12 618                  (22 492)                  
*    Concentrator recovery has been rounded to the nearest percentage point.    
Third quarter mining and production improved compared to the second quarter     
which was negatively impacted by labour issues related to the illegal           
underground sit-in followed by an unprotected strike in early May. Following the
settlement of the labour issues in late May, operations at the Zandfontein      
section have steadily and safely returned to levels achieved in late 2010.  At  
the Maroelabult section, 155 production workers were suspended in May following 
which JIC Mining was engaged on a fixed-term contract. Production build-up has  
progressed slower than anticipated as new crews were being integrated into the  
section throughout the third quarter.                                           
Concentrator recovery improved in the third quarter compared to the second      
quarter during which disruptions to the steady state operation of the mine and  
processing plant due to the illegal sit-in contributed to lower concentrator    
recoveries.  Head grade also improved compared to the second quarter as a result
of the increase in tonnage from stoping.                                        
Work at the 90,000 tonne-per-month Mareesburg/Kennedy`s Vale open-pit and       
concentrator project on the Eastern Limb is progressing on schedule.  Bulk      
earthworks commenced on site in July.  The completion of the terracing for the  
concentrator pad is advancing well and the Company anticipates that concrete    
work will start in November.  Much of the major mine and concentrator equipment 
is already in storage on site and the balance is on order.  Eskom power has been
connected to site and the main substation transformer has been shipped.         
Production start-up is on schedule for late 2012.                               
The qualified person having reviewed the operating results presented in this    
press release is Mr. Brian Montpellier, P.Eng.                                  
Eastplats will release its full second quarter results on Monday, November 14,  
2011.                                                                           
Total shares issued and outstanding: 908,187,807                                
For further information contact:                                                
Investor Relations                                                              
Website: www.eastplats.com                                                      
Email: info@eastplats.com                                                       
Tel: 1-(604)-685-6851, Fax: 1-(604)-685-6493                                    
NOMAD:                                                                          
Bhavesh Patel                                                                   
Canaccord Genuity Limited, London                                               
Tel: +44 20 7050 6500                                                           
JSE SPONSOR:                                                                    
Johan Fourie                                                                    
PSG Capital (Pty) Limited                                                       
Email: johanf@psgcapital.com                                                    
Tel: +27 21 887 9602                                                            
No stock exchange, securities commission or other regulatory authority has      
approved or disapproved the information contained herein.                       
Certain statements included herein constitute "forward-looking statements"      
within the meaning of applicable Canadian securities legislation. These forward-
looking statements are based on certain assumptions by Eastplats and as such are
not a guarantee of future performance. Actual results could differ materially   
from those expressed or implied in such forward-looking statements due to       
factors such as general economic and market conditions, increased costs of      
production and a decline in metal prices. Eastplats is under no obligation to   
update or revise any forward-looking statements, whether as a result of new     
information, future events or otherwise, except as required by applicable laws. 
Date: 18/10/2011 15:39:34 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.                                          
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: