Thu 12 Jan 2012, 16:24 PAM - Palabora Mining Company Limited - Fourth Quarter 2011 - operations
PAM
PAM                                                                             
PAM - Palabora Mining Company Limited - Fourth Quarter 2011 - operations        
overview and production statistics                                              
PALABORA MINING COMPANY LIMITED                                                 
(Incorporated in the Republic of South Africa)                                  
Registration number - 1956/002134/06                                            
JSE Code: PAM ISIN: ZAE000005245                                                
("Palabora" or "the Company")                                                   
FOURTH QUARTER 2011 - OPERATIONS OVERVIEW AND PRODUCTION STATISTICS             
Palabora is pleased to announce its Fourth Quarter and Full Year 2011           
operations overview and production statistics. New copper cathode produced      
reached 59,000 tonnes for the year, a 1.7% increase over 2010 and production    
of magnetite increased 14.6% to 3,429k tonnes in 2011 over 2, 993k tonnes in    
2010. Tony Lennox, Managing Director, commented, " Palabora has produced        
another solid year of operating results with copper production in-line with     
expectations and the continued growth of the magnetite operations to meet       
ever growing demand in Asia. As always safety of our people is our primary      
objective and we will continue to strive to meet our goal of zero harm"         
Copper production during the year was impacted by the successful replacement    
of both winder drums at the mine and the planned closure of the smelter to      
rebuild the reverb furnace during August. In addition, Palabora implemented     
improvements to its underground vehicle maintenance program which will begin    
to reflect positively on operations during 2012.  Reflecting on copper          
production, Tony said "lower output levels from the underground mine            
following the consolidation of the Load Haul and Dump (LHD) maintenance         
contracts have been resolved with production reaching expected levels during    
December".                                                                      
In an effort to meet the growing demand, Palabora commenced trucking of         
magnetite during December to the Maputo port in addition to the normal          
delivery of material by rail to Richards Bay and Maputo. Palabora will          
continue to truck magnetite to Maputo at an expected rate of between 40k and    
60k tonnes per month.  Additional improvements at the magnetite operation       
were put in place to debottleneck rail and truck loading capacity and to        
increase drying capacity towards the end of 2012.                               
                     4Q      1Q        2Q       3Q      4Q     Full     Full    
                                                               Year     Year    
2010    2011      2011     2011    2011     2010     2011    
Palabora mine                                                                   
Tonnes hoisted     2,838   2,601     2,715    3,024   2,403   11,236   10,743   
(`000 tonnes)                                                                   
Mined ore          2,452   2,523     2,623    2,969   2,434            10,549   
treated (`000                                                 11,003            
tonnes)                                                                         
Slag ore treated     386     322       341      164     411      654    1,238   
(`000 tonnes)                                                                   
Total Ore          3,126   2,845     2,964    3,133   2,845   11,657   11,787   
treated (`000                                                                   
tonnes)                                                                         
Underground ore     0.63              0.65     0.63    0.63     0.64     0.64   
grade: copper               0.66                                                
(%)                                                                             
Slag ore grade:     1.57    1.48      1.53     1.78    1.13     2.75     1.51   
copper (%)                                                                      
                   65.2    58.4      61.2     58.2   50.10    246.0    227.9    
Copper                                                                          
concentrates                                                                    
produced (`000                                                                  
tonnes)                                                                         
Average             29.5    29.5      30.7     31.2    29.9     30.3     30.3   
concentrate                                                                     
grade: copper                                                                   
(%)                                                                             
Copper in           19.3    17.3      18.7     18.2    14.9     74.6    69.14   
concentrates                                                                    
(`000 tonnes)                                                                   
Palabora                                                                        
smelter/refinery                                                                
New concentrate     62.1    62.3      62.6     45.4    60.4    240.8    230.7   
smelted on site                                                                 
(`000 tonnes)                                                                   
New copper          14.4    14.7      18.2     10.8    15.7     55.7     59.4   
anodes produced                                                                 
(`000 tonnes)                                                                   
Refined new         17.5    14.8      17.3     10.2    16.7     58.0     59.0   
copper produced                                                                 
(`000 tonnes)                                                                   
Joint product:                                                                  
Magnetite            695     880       820      744     985    2,993    3,429   
concentrate                                                                     
(`000 tonnes)                                                                   
By-products:                                                                    
Nickel contained      24      27        28       23       9       72       87   
in products                                                                     
(tonnes)                                                                        
4.3     1.3       0.4      3.0     0.6      9.9      5.3    
Copper sold as                                                                  
concentrate                                                                     
(`000 tonnes)                                                                   
Vermiculite                                                                     
plant                                                                           
Vermiculite           45                51       48      23      196      165   
produced (`000                43                                                
tonnes)                                                                         
Palabora, a member of the Rio Tinto Group of Companies, situated in the Ba-     
Phalaborwa area of Limpopo, operates a large block cave copper mine and         
smelter complex, mines and exports magnetite and operates a vermiculite         
mining and processing facility.                                                 
Total ore hoisted was 21% lower than the previous quarter and 15% lower than    
the corresponding period in 2010 due to lower LHD availability following the    
consolidation of the two LHD maintenance contracts. The LHD availability was    
resolved in December with production returning to expected levels. Total ore    
hoisted was 4% lower for 2011 compared to 2010 at 10.7mt mainly due to the      
replacement of the winder drums during the first and second quarter of 2011     
and unplanned maintenance on a crusher during the second quarter.               
Total ore treated decreased 9% from the previous quarter and corresponding      
period in 2010 due to lower underground throughput partly offset by increased   
quantities of slag material and surface copper stockpile material processed     
to compensate for the lower ore mined. Full year ore treated was 1% lower       
compared to 2010 mainly due to previously reported delays experienced on the    
scheduled girth gear replacement during the second quarter and the impact of    
the lower hoisting rates during the last quarter of 2011. Slag treated          
increased by 89% to 1.2mt to compensate for the lower underground ore supply.   
Copper concentrate produced was 23% and 14% lower than the corresponding        
period in 2010 and the previous quarter, respectively. Production was           
affected by lower underground throughput and the impact of lower recoveries     
from increased slag material processed. Full year copper concentrate was 7%     
lower compared to 2010 due to lower mined ore milled and the impact of lower    
recoveries from minor equipment failures and increased lower grade slag         
material.                                                                       
Copper in concentrate produced was 23% lower than the corresponding period in   
2010 and 18% lower than the previous quarter and in line with underground       
supply. Full year copper in concentrate was 7% lower compared to 2010 and in    
line with copper concentrate production.                                        
New concentrate smelted was 33% higher compared to the previous quarter due     
to the scheduled month long shutdown in August to rebuild the reverb furnace    
which occurs every five years. Concentrate inventory accumulated during the     
reverb rebuild project mitigated the impact of lower concentrate production.    
New anode production was 45% higher than the previous quarter following the     
reverb furnace rebuild during the previous quarter. Production increased 9%     
compared to the corresponding period in 2010 following improvements in          
operational efficiencies at the smelter implemented during the course of the    
year. Full year production was 7% higher than the previous year due to          
improvements in operational efficiencies and recovery rates at the smelter      
following initiatives undertaken from the end of 2010 and utilisation of        
prior period inventory.                                                         
Refined copper production was higher than the previous quarter due to           
utilisation of anode inventory and in line with new anode production during     
the quarter. Production for Q4 2010 was above anode production due to           
inventory utilisation. Full year refined copper production was 2% higher than   
the previous year and in line with new anode supply.                            
Magnetite fourth quarter production was aligned with improved logistical        
constraints on train availability as well as road trucking of magnetite to      
Maputo port which commenced in December. Full year magnetite production was     
15% higher than the previous year reflecting the easing of logistical           
constraints and the continued export demand.  Palabora will continue            
to match production with sales demand given the new transport initiatives.      
Vermiculite production was 51% lower and 48% lower than the previous quarter    
and the corresponding period of 2010 respectively as a result of a two-and-a-   
half week shutdown to repair the furnace refractory, a reduction in ore feed    
grades and excessive ore moisture due to rain. The production performance in    
the first quarter of 2012 is expected to improve as a result of the furnace     
refractory maintenance. Full year production was 16% lower than the previous    
year due to operational maintenance performed to improve safety, the impact     
of wet weather on ore feed in the first quarter and the impact of the furnace   
refractory maintenance in the fourth quarter.                                   
The above information has not been reviewed or reported on by the Company`s     
auditors.                                                                       
Phalaborwa                                                                      
12 January 2012                                                                 
Investor Relations Contact: Dikeledi Nakene, Palabora +27 15 780 2277           
Media Contact: Mike Mabasa, Palabora +27 15 780 2019                            
              Gugulakhe Lourie, Rio Tinto South Africa +27 11 911 9700          
Sponsor: One Capital                                                            
Date: 12/01/2012 16:24:01 Produced by the JSE SENS Department.                  
The SENS service is an information dissemination service administered by the    
JSE Limited (`JSE`). The JSE does not, whether expressly, tacitly or            
implicitly, represent, warrant or in any way guarantee the truth, accuracy or   
completeness of the information published on SENS. The JSE, their officers,     
employees and agents accept no liability for (or in respect of) any direct,     
indirect, incidental or consequential loss or damage of any kind or nature,     
howsoever arising, from the use of SENS or the use of, or reliance on,          
information disseminated through SENS.                                          
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: