Thu 12 Jul 2012, 13:30 Village Main Reef GM Co - Village production performance for June 2012 quarter
VIL
Village production performance for June 2012 quarter

VILLAGE MAIN REEF LIMITED
(Incorporated in the Republic of South Africa)
(formerly known as Village Main Reef Gold Mining Company (1934) Limited)
 (Registration number 1934/0057034/06)
 Share Code: VIL ISIN: ZAE000154761
        ("Village")



                             VILLAGE PRODUCTION PERFORMANCE FOR JUNE 2012 QUARTER

Village today announces that a total of 46 424oz of gold and 1 436 tons of antimony were produced during the June 2012 quarter. Gold production
for the quarter, on a like for like basis, excluding gold produced by Blyvooruitzicht Mine (Blyvoor) was 0.73% (or 289oz) lower than the gold
production achieved during the March 2012 quarter. Blyvoor, which was accounted for from the 1st June 2012, contributed 6 944 oz of gold for the
month of June 2012. Antimony production was 58% (or 527 tons) higher than the production achieved during the March 2012 quarter.

Production at all the operations were negatively impacted by a number of safety related stoppages during the quarter. In total safety related stoppages
resulted in a loss of 53 production days, which impacted gold production by a total loss of 107 kg and antimony production by 86 tons. The loss of
production and the impact of winter electricity tariffs have had a negative impact on the notional cash cost per kg although absolute costs at the
operations were well controlled. The higher winter electricity tariffs added some R30 million to the costs of all the operations in the group during
June 2012, with approximately R11 million of this being attributed to Blyvoor.

Gold production at Tau Lekoa was 27 585oz which was similar to gold production during the March 2012 quarter. The business optimisation project
at Tau Lekoa continued to yield positive results.

Gold production at Buffelsfontein was 9 227oz, which was 5% (or 514oz) lower than the March 2012 quarter. Although Buffelsfontein managed to
improve gold grades mined, this did not translate to higher gold production. Production volumes at Buffelsfontein were negatively impacted due to
safety stoppages which resulted from a fire at No. 7 shaft as well as stoppages related to seismic activity at the mine.

Cons Murch mine delivered a significant improvement in production with a 22% increase in gold to 2668 oz and a 58% improvement in antimony to
1436 tons. The increase in production was due to better grade control and the successful commissioning of additional trackless machinery. Cons
Murch continued its capital expenditure program, focused on the improvement of plant recoveries and the acquisition of mechanised equipment, with
a total capital spent of R17.1 million during the quarter.

The table below provides more information of the production achieved at each of the Village mines during the June 2012 quarter versus the March
2012 quarter.

                                                                                            Jun-12                  Mar-12
                                                                                           quarter                  quarter                 % change

                      Tau Lekoa  gold oz                                                   27 585                    27 842                down    1%

                      Buffelsfontein  gold oz                                               9 227                     9 741                down    5%

                      Blyvoor - gold oz (Jun 12)                                             6 944                           -              up 100%

                      Cons Murch  gold oz                                                   2 668                     2 186                up   22%

                      Cons Murch  antimony tons                                             1 436                       909                up   58%

                      Total Village Gold oz                                                 46 424                    39 769                up   17%

                      Total Antimony tons                                                    1 436                       909                up   58%


                      Unaudited Notional Cash Cost/Kg
                                                                                            Jun-12                  Mar-12
                                                                                           quarter                  quarter                 % change

                      Tau Lekoa                                                            275 744                  264 395             up           4%

                      Buffelsfontein                                                       638 241                  519 422             up       23%

                      Blyvoor (June 12)                                                    449 494                           -          up       100%

                      Cons Murch (cost per ton)                                              1 470                     1 255            up       17%



Village joint CEO Marius Saaiman commented: We are very pleased that Part A of our acquisition of Blyvoor concluded successfully. We achieved
stable production at all of our gold operations and the benefit of the optimisation program at Tau Lekoa is being realised as costs are reducing and
volumes increasing. We were especially pleased with the performance at Cons Murch where the drive to mechanize has positively impacted
production volumes.

Operational and financial details for the June 2012 quarter will be provided in the June 2012 Quarterly Report, which is expected to be released on
SENS towards the end of August 2012.


12 July 2012


Sponsor                                                                      
Java Capital

Media and Investor Relations
Vesta
Date: 12/07/2012 01:30:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: