Tue 27 Aug 2002, 0:00 Messina Limited - News Release
Messina Limited - News Release                                                  
MESSINA LIMITED                                                                 
(Incorporated in the Republic of South Africa)                                  
(Registration Number: 1950/035912/06)                                           
Share Code: MES    ISIN: ZAE 000004438                                          
News Release                                                                    
Johannesburg, 27 August 2002                                                    
SRK Completes Positive Phase 2 Feasibility Study for Messina Platinum           
Phase 2 Resource Increases by 12 Percent to 6.3 Million Ounces                  
Messina Limited announced today the successful completion of the Bankable       
Feasibility Study for the Messina Phase 2 Project on the Doornvlei property by  
SRK Consulting, a leading international engineering consulting group. The       
Doornvlei property is 100 percent owned by Messina Limited, which in turn is    
70.4 percent owned by SouthernEra Resources Limited.                            
Doornvlei is located on the Bushveld Igneous Complex, a geological formation    
well known for its production of Platinum Group Metals (PGM`s) as well as       
chromite ores.  The project is located about 12 kilometres to the east of       
Messina`s 100 percent owned Voorspoed Mine, which is currently under development
and in early production, and immediately adjacent to the newly acquired Dwaalkop
property. The PGM reefs are continuous over these three properties - Voorspoed  
(Phase 1), Doornvlei (Phase 2) and Dwaalkop.                                    
The Bankable Feasibility Study estimates an after tax internal rate of return   
(IRR) of 22.6 percent with a net present value (NPV) of US$73.3 million at a 10 
percent discount rate for the Messina Phase 2 Project. The expected annual      
average production rate is approximately 173,000 ounces of 5PGM+Au at an average
estimated operating cost of US$172 per ounce over the life of mine, gross before
nickel and copper by-product credits. The metal splits for the two reefs are as 
follows:                                                                        
ELEMENTS              MEREKNSKY REEF        UG2 REEF                            
Platinum              53.7%                 39.5%                               
Palladium             27.4%                 36.9%                               
Rhodium                 2.8%                  6.2%                              
Iridium                 1.4%                  2.5%                              
Ruthenium               6.9%                13.0%                               
Gold                    7.8%                  1.8%                              
Platinum / Palladium  1.96: 1               1.07: 1                             
Ratio                                                                           
Platinum / Rhodium    19.18: 1              6.37: 1                             
Ratio                                                                           
The peak capital requirement for the project is US$84.7 million, which is       
estimated will be paid back approximately 5 years after production start-up. The
expected operating mine life is 23 years with full production of 120,000 tonnes 
per month to be achieved by mid-2005 following a 24 month construction period.  
Messina CEO Patrick Evans stated: "We are proving, step by step, that the       
Messina Project in its various phases will make Messina one of the world`s      
leading and most profitable producers of PGM`s. Once we have achieved full      
production from Phase 2, PGM production from Messina will total approximately   
400,000 ounces per year at a cash production cost of approximately $100 per     
ounce."                                                                         
At an annual production rate of 173,000 ounces, average annual revenues (net of 
smelter and refining charges) are estimated at US$64.7 million based on an      
average price of $374 per ounce of 5PGM`s+Au. Metal prices used for the Bankable
Feasibility were based on London Metal Prices at August 16, 2002. The following 
table summarises the metal prices and expected annual metal output.             
Metals                Feasibility Prices    Annual Output                       
Platinum              $556 per ounce        76,800 ounces                       
Palladium             $320 per ounce        58,200 ounces                       
Rhodium               $740 per ounce          8,700 ounces                      
Iridium               $280 per ounce          3,700 ounces                      
Ruthenium             $125 per ounce        18,900 ounces                       
Gold                  $312 per ounce          6,700 ounces                      
Nickel                $6650 per tonne         1,670 tonnes                      
Copper                $1473 per tonne         1,000 tonnes                      
South African-based operating and capital cost estimates were converted at an   
exchange rate of R10.5 = US$1.00 for 2002, increasing to R11= US$1.00 by the end
of 2003 and this rate was maintained over the remainder of the project life.    
The previous Phase 2 resource estimate was 15.180 million tonnes at a grade of  
5.81 grams per tonne of 5PGE+Au (2.83 million ounces) in the Indicated category,
plus an additional 15.030 million tonnes grading 5.80 grams per tonne (2.80     
million ounces) in the Inferred category. As part of the Bankable Feasibility   
Study, SRK re-estimated the Phase 2 resource using the histogram method, which  
assigns a global mining grade and width.  The mining widths selected, excluding 
dilution, were 1.05 metres for the Merensky Reef and 2.0 metres for the UG2.    
Although the reefs outcrop at surface on Phase 2, the resource tonnage has been 
estimated from 100 metres below surface to 1 000 metres and by applying a bulk  
density of 3.2 tonnes per cubic metre for the Merensky reef and 3.8 tonnes per  
cubic metre for the UG2 reef.                                                   
SRK has applied a 25 percent geological loss for both reefs at Phase 2, in close
concordance with common industry practice. Incorporating the abovementioned     
mining widths, SRK estimates the Merensky resource is 11.89 million tonnes at a 
grade of 4.47 grams per tonne  (5PGM+Au). The corresponding UG2 values are 26.9 
million tonnes at 5.35 grams per tonne. This 6.3 million ounce resource, at an  
average grade of 5.08 grams per tonne, has been placed in the Indicated category
in terms of South Africa`s SAMREC Code of reporting of mineral resources and    
mineral reserves, which conforms to the requirements of Canada`s National       
Instrument 43-101 and the equivalent United Kingdom code for reserve and        
resource classification. Comparing the SRK resource to the previous estimate,   
total 5PGM+Au resources have increased by 12 percent.                           
SRK has estimated a mining reserve by discounting the new resource tonnage for  
mining layout losses and diluting the resource grade. The mining layout calls   
for an extraction of 78 percent, including shaft pillars. Dilution has been     
added at 0.20 metres to the stoping width for both reefs giving 19 percent and  
10 percent dilution for the Merensky and UG2 reefs respectively.  Further       
tonnage increases at the expense of grade have been included to account for all 
development dilution.  The effects of all these additions resulting from        
dilution and subtractions for pillars is to lower the resource tonnage by 21.4  
percent for Merensky reef and 29.5 percent for the UG2.                         
Accordingly, the reserves for Phase 2 are 11.12 million tonnes at 3.69 grams per
tonne for the Merensky reef and 20.85 million tonnes at 4.81 grams per tonne for
the UG2. This total reserve of 4.5 million ounces at an average diluted grade of
4.42 grams per tonne has been classified in the Probable Reserve category. The  
Independent Competent Person in respect of the Phase 2 reserve and resource     
statement is Dr. Anthony Martin, B.Sc., D.Phil. of SRK Consulting.              
Both the Merensky and UG2 reefs will be mined at a combined rate of 120 000     
tonnes per month. The sublevel open stoping mining method has been proposed, as 
it is the safest and most practical for this environment. A total of 11.12      
million Merensky and 20.85 million UG2 reef tonnes will be mined over a life of 
25 years, resulting in a total production tonnage of 31.97 million tonnes.      
The development strategy is to first access the ore bodies by means of two      
decline ramp systems, each of which will cater for one half of the 3.7-kilometre
strike available at Phase 2.  The top three levels (175 metres, 250 metres and  
325 metres) will be mined via the declines, with reef being trucked up to       
surface for processing in the plant.  The portion of the ore body between 400   
metre level and 700 metre level will be accessed via a vertical shaft to 700    
metres, the sinking of which will begin in Year 5 and will be operational by    
Year 7.  The shaft will then be deepened in Years 14 and 15 in order to access  
the remainder of the resource between 700 and 1 000 metres.  The project        
reserves, those above 1 000 metres, are depleted in project Year 25. Potential  
exists however, to extend the project life beyond this date, by considering     
resources below this level.                                                     
The plant has been designed as a two-stage milling and flotation (MF2) type     
plant capable of treating 120 000 tonnes of ore per month at a UG2: Merensky    
feed ratio of 65:35.  A single flotation will be produced as a filter cake and  
will be transported by road for smelting and refining. The average life of mine 
head feed grade is 4.42 grams per tonne 5PGM+Au resulting in an average plant   
recovery of 84 percent. Concentrate production will be approximately 2 400      
tonnes per month, based on a mass pull of 2 percent.                            
Subject to the securing of the necessary government permits and the conclusion  
of financing, the Company plans to commence development of the Messina Phase 2  
in January 2003. It is expected that the mine will be in full production by mid 
2005.                                                                           
FOR FURTHER INFORMATION PLEASE CONTACT:                                         
Messina Limited                                                                 
Patrick C. Evans, CEO; or                                                       
Mike Kritzinger, Secretary                                                      
Telephone: (011) 442-6923                                                       
Fax: (011) 442-6993                                                             
Date: 27/08/2002 04:30:00 PM Produced by the JSE SENS Department                


Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: