Thu 23 Oct 2003, 9:49 Bhp Billiton Quarterly Report On Exploration And D
Bhp Billiton Quarterly Report On Exploration And Development Activities         
BHP Billiton Plc                                                                
Registration number 3196209                                                     
Share code: BIL                                                                 
ISIN: GB0000566504                                                              
Issuer Code: BIBLT                                                              
BHP BILLITON QUARTERLY REPORT ON EXPLORATION AND DEVELOPMENT ACTIVITIES         
July 2003 - September 2003                                                      
This report covers exploration and development activities for the quarter ended 
30 September 2003.  Unless otherwise stated, BHP Billiton"s interest in the     
projects referred to in this report is 100 per cent, and references to quarters 
are based on calendar years.                                                    
Of the 14 projects currently under construction, 12 are currently within Board  
approved expenditure limits and are tracking on or ahead of schedule.  The      
exceptions are Minerva and the ROD Integrated development.                      
PETROLEUM DEVELOPMENT                                                           
Atlantis Development, Gulf of Mexico, USA (BHP Billiton 44%, non-operated)      
BHP Billiton completed full capital allocation for the Atlantis project in      
February 2003.  Our share of total project expenditure is US$1.1 billion.       
During the quarter, fabrication of the facilities topsides continued on all     
three production modules.  Qualification testing of critical subsea components  
was progressed, as was detailed design of the hull.  The project remains on     
budget and on schedule for first production in the third quarter of 2006.       
OHANET Development, Algeria (BHP Billiton 45%, joint operating organisation     
comprising BHP Billiton/SONATRACH)                                              
The OHANET Development consists of the development of four gas-condensate       
reservoirs in the Illizi Basin in southern Algeria. The project will provide a  
gas treatment facility with a capacity of 20 million standard cubic metres per  
day fed by 47 production wells, of which 32 will be new and 15 will be re-      
completions of existing oil producers.  3D seismic data across all reservoirs   
has been processed and incorporated into the reservoir models.  A total of 28   
new wells have been drilled and completed and 15 existing wells re-completed.   
The last four wells have been deferred to allow three to four years of          
production history to be gathered.  Construction is complete and the plant is   
undergoing advanced commissioning and testing, including of the gas and liquids 
export systems. BHP Billiton"s share of capital expenditure is US$464 million.  
Mad Dog Development, Gulf of Mexico, USA  (BHP Billiton 23.9%, non-operated)    
BHP Billiton announced its sanction of the Mad Dog field in February 2002,      
approving up to US$335 million for development of the Gulf of Mexico oil and gas
field. Construction continues on the hull (in Finland) and topsides (in the     
USA), with an estimated 70 per cent of the work complete at the end of September
2003.  The project is within budget (BHP Billiton share US$335 million), and    
first production remains on schedule for the end of calendar year 2004.         
Greater Angostura Development, Trinidad (BHP Billiton 45%, operated)            
In March 2003, BHP Billiton approved US$327 million for the first development   
phase of the Greater Angostura oil and gas field off the northeast coast of     
Trinidad.  During the September 2003 quarter, construction progressed on the    
onshore storage terminal, engineering and fabrication of the offshore facilities
continued, and the first of four wellhead protection platforms was prepared for 
loadout and installation.  Recruitment of the initial group of operations       
personnel was completed, with training commencing in September.  First oil is   
scheduled for the end of calendar year 2004.                                    
North West Shelf expansion, Australia (BHP Billiton 16.67%, non operated)       
Overall progress on the fourth liquefaction processing train is 78 per cent     
complete and remains on schedule to start up in mid 2004.  All major equipment  
is on site and construction is 55 per cent complete.  With the completion of    
pipelay, the second trunkline is progressing as planned at 76 per cent complete.
Tie in of the second trunkline into the existing interfield line has started.   
BHP Billiton"s share of capital expenditure is US$247 million.                  
ROD Integrated Development, Algeria (BHP Billiton 36.04%, joint operating entity
comprising BHP Billiton/SONATRACH)                                              
The ROD Integrated Development consists of the development of six satellite     
oilfields in the Berkine Basin in eastern Algeria. The project will produce     
80,000 barrels of Sahara Blend crude oil per day, with associated gas being     
reinjected into the reservoir together with water to provide pressure support to
the reservoir. 36 development wells will be required, 10 of which will be       
recompletions of already drilled wells. At the end of September 2003, 18 new    
development wells had been completed and the 19th was well advanced.            
Procurement of major equipment is now complete.  Erection of the piperack       
steelwork, tank farm construction, civil works at the Field Gathering Station   
(FGS) and Intermediate Field Manifolds, and the welding and tie in of pipelines 
are all well advanced. Over 2 million manhours have been completed at the       
construction site without a Lost Time Incident.  Overall project progress is    
67.5 per cent complete.  Following a detailed project review, first production  
is now scheduled for the middle of calendar year 2004, resulting from delays in 
procurement of some equipment and materials.  BHP Billiton"s share of capital   
expenditure is US$192 million.                                                  
Minerva (BHP Billiton 90%, operated)                                            
In September 2003, BHP Billiton changed the contractual arrangements relating to
the design and construction of the Minerva development.  The arrangement with   
the original contracting joint venture is no longer in place.  Tendering for a  
new managing contractor to complete the gas plant has been initiated and award  
is scheduled for October 2003.  Work on the offshore and shore crossing         
activities has resumed.  To date, the offshore Minerva 3 and 4 production wells 
have been drilled and completed, and the subsea trees installed.  Construction  
of the offshore flowline is scheduled to start towards the end of October 2003  
and preparations for installation of the shore crossing section of the flowline 
are underway.  The main length of onshore flowline has been installed.  At the  
gas plant site bulk earthworks and foundations are largely complete.  The       
initial target of first production in first quarter of 2004 will not be met, and
in light of the changes to contractual arrangements, the project"s targets are  
under review.                                                                   
Caesar/Cleopatra Transportation Systems, Gulf of Mexico, USA (BHP Billiton      
interest in Caesar pipeline, 25%; interest in Cleopatra pipeline, 22%. Non-     
operated)                                                                       
BHP Billiton acquired a 25 per cent interest in the Caesar oil pipeline and a 22
per cent interest in the Cleopatra gas pipeline which will transport product    
from the Mad Dog and Atlantis fields to pipelines closer to shore.  Installation
of the Cleopatra portion of the line is complete to a third party facility and  
to Mad Dog, with engineering and pipe coating activities continuing on the      
Caesar leg during the September 2003 quarter.  Expenditure of up to US$132      
million has been approved by the Board for this project.  The project is on     
budget and on schedule to commence operation coinciding with first production at
third party facilities, in advance of first hydrocarbon production from Mad Dog 
and Atlantis.                                                                   
MINERALS DEVELOPMENT                                                            
Aluminium                                                                       
Mozal 2 Expansion, Mozambique (BHP Billiton 47.11%)                             
Construction work on the 253,000 tonne per annum Mozal II aluminium smelter     
project was completed on 30 September 2003, seven months ahead of schedule.     
Process commissioning has proceeded well and the plant reached full production  
in August 2003.  The final capital cost of the project was US$665 million (BHP  
Billiton share US$313 million), a saving of US$195 million against the original 
budget of US$860 million.    This project is now fully operational and will no  
longer be included in this report.                                              
Hillside Expansion                                                              
Main construction work on the 130,000 tonne per annum Hillside III aluminium    
smelter project commenced on 1 April 2002, and at the end of September 2003     
overall construction work has reached 94 per cent completion.  The potline      
production facilities have been handed over to operations and first metal       
production occurred on 3 October 2003, some six months ahead of schedule.       
Production will be ramped up progressively with full production expected by the 
first quarter of 2004.  Expenditure to date indicates that the project will     
likely be completed below the budgeted US$449 million.                          
Base Metals                                                                     
Escondida Norte, Chile (BHP Billiton 57.5%)                                     
The development of the Escondida Norte pit, located approximately 5 kilometres  
north of the existing Escondida mining operations, was approved in June 2003, as
part of Escondida"s operating strategy to maintain copper production capacity in
future years.  Pre-mine waste stripping commenced during the quarter with the   
first blast at the new pit area on 30 September.  The pre-mine pioneering       
contract was awarded, the contractor mobilized to site and road/drill platforms 
access development has commenced.  External and internal recruitment activities 
are on schedule and operational planning is on target to meet the project       
milestone of start-up of the first mining shovel in December 2003.  Purchase and
delivery of the major mining equipment to support the pre-mine is on target.    
The construction phase of the project has commenced with the award of the       
Engineering Procurement Construction and Management contract and an immediate   
start on detailed engineering.  Procurement of the crusher unit has progressed  
with an order being placed.  Early construction activities are progressing in   
order to supply initial services to mine operations.  Construction work is      
progressing to schedule with the target date for first ore delivery in the      
fourth quarter of 2005.   Development costs are estimated at US$400 million (BHP
Billiton share US$230 million).                                                 
Carbon Steel Materials                                                          
Products & Capacity Expansion Project (PACE), Australia (BHP Billiton 85%)      
The project provides for the upgrade of the BHP Billiton rail and port          
facilities in a staged process to meet forecast increases in sales of iron ore. 
The estimated capital cost for Stage 1 is US$351 million (BHP Billiton share    
US$299 million).                                                                
Detailed engineering is complete and construction work continues on schedule.   
The project is within budget and is on track to commission ahead of original    
schedule in the first quarter of 2004.                                          
Area C Project, `C Deposit", Australia (BHP Billiton 85%)                       
The project provides for the development of a mine, processing plant, 38        
kilometre rail spur and associated infrastructure for an operation to build up  
to 15 Mtpa at Area C, which is situated approximately 120 kilometres from Newman
in Western Australia"s Pilbara region.                                          
Construction work is complete at both the plant and infrastructure rail and road
sites.  First ore was railed from Area C to the port at Nelson Point on 16      
August 2003, and the first shipment of ore departed Nelson Point on 24 September
2003.  Overall the project was completed within the budget of US$213 million    
(BHP Billiton share US$181 million) and was commissioned ahead of schedule      
during the third quarter of 2003, with production ramp up continuing into the   
fourth quarter of 2003.                                                         
Dendrobium Coal Project, Australia                                              
The Dendrobium Mine will be a low cost underground longwall operation capable of
producing 5.2 Mtpa of raw coal (3.6 Mtpa of clean coal).  The main customer for 
the coking coal is the Port Kembla steelworks, which is located seven kilometres
from the mine site.                                                             
Construction activities associated with the mine surface facilities and         
ventilation shaft are essentially complete.  Commissioning of the coal loading  
facilities (Kemira Valley) is underway with the first trains loaded during      
September 2003.  Construction activities associated with the washery upgrade and
the thermal drier installation are well underway.  The project is approximately 
45 per cent complete with two of the three trunk conveyor belt installations    
being successfully commissioned.                                                
Just over 65 per cent of the project"s capital has been committed to date.  The 
capital forecast remains unchanged at US$170 million.  Forecast longwall        
commencement is tracking ahead of schedule and is expected in the first quarter 
of 2005.                                                                        
Energy Coal                                                                     
Mount Arthur North, Australia                                                   
The Mount Arthur North Mine will be capable of producing up to 12 million tonnes
of saleable thermal coal per annum when full production is achieved in 2006.    
Construction activities associated with the Coal Handling and Preparation Plant 
are complete and in the final stages of commissioning.  During the September    
2003 quarter, product was supplied to both the export and domestic thermal coal 
markets in line with the ramp up plan.                                          
The project is progressing to plan with final capital cost forecast to be below 
the approved budget of US$411 million.                                          
PETROLEUM EXPLORATION                                                           
Exploration and appraisal wells drilled during the quarter or in the process of 
drilling as at 30 June 2003.                                                    
WELL           LOCATION            BHP BILLITON EQUITY  STATUS                  
Bimurraburra-1 Trinidad Block      30% BHP Billiton     Drilling ahead.         
               3(a)                operator                                     
Howler-1       Trinidad Block      64.29% BHP Billiton  Plugged and abandoned   
               2(c)                operator             with hydrocarbon        
shows.                  
Neptune-5      Gulf of Mexico,     35% BHP Billiton     See News Release of 8   
(including 2   Atwater Valley      operator             August 2003.            
side tracks)   Block 57                                                         
Puma-1         Gulf of Mexico,     33.3% BHP Billiton;  Drilling ahead.         
               Green Canyon 823    BP operator                                  
Shenzi-2       Gulf of Mexico,     44% BHP Billiton     Drilling ahead.         
               Green Canyon 653    operator                                     
Tiger-1        Gulf of Mexico,     100% BHP Billiton    Plugged and abandoned.  
               Green Canyon 195    operator                                     
Carteret-1     Western Australia,  16.67% BHP           Plugged and abandoned.  
               North West Shelf    Billiton; Woodside                           
WA-4-L              operator                                     
Crosby-1*      Australia, Exmouth  71.43% BHP Billiton  Oil discovery.          
               Sub-Basin WA-12-RL  operator             Encountered gross oil   
                                                        column of 34.7 metres   
with 29.4 metres of     
                                                        net pay.                
Ravensworth-1  Australia, Exmouth  40% BHP Billiton     See News at BHP         
               Sub-Basin WA-12-RL  operator             Billiton release of 23  
July 2003.              
Van Gogh-1     Australia, Exmouth  40% BHP Billiton     Plugged and abandoned.  
               Sub-Basin WA-155-P  operator             Encountered             
                                                        hydrocarbons.           
* Drilled in December 2003 quarter.                                             
MINERALS EXPLORATION                                                            
The exploration group of BHP Billiton Minerals continued to pursue global       
exploration opportunities for key commodities of interest to the group utilising
both the Junior Alliance Program and in house generative capabilities.          
In August 2003, BHP Billiton sold its 51% interest in the Mt Woods Joint Venture
to its junior alliance partner Minotaur Resources Limited for approximately US$5
million in cash that is payable in two instalments.                             
During the quarter, BHP Billiton spent US$15 million on minerals exploration, of
which US$13 million was expensed.                                               
EXPLORATION EXPENDITURE                                                         
Information related to exploration expenditure will be included in the BHP      
Billiton first quarter results, to be released on 29 October 2003.              
Further information on BHP Billiton can be found on our Internet site:          
http://www.bhpbilliton.com                                                      
Australia                                                                       
Andrew Nairn, Investor Relations                                                
Tel: +61 3 9609 3952  Mobile: +61 408 313 259                                   
email: Andrew.Nairn@bhpbilliton.com                                             
Tania Price, Media Relations                                                    
Tel: +61 3 9609 3815  Mobile: +61 419 152 780                                   
email: Tania.Price@bhpbilliton.com                                              
United Kingdom                                                                  
Mark Lidiard, Investor & Media Relations                                        
Tel: +44 20 7802 4156                                                           
email: Mark.Lidiard@bhpbilliton.com                                             
Ariane Gentil, Media Relations                                                  
Tel: +44 20 7802 4177                                                           
email: Ariane.Gentil@bhpbilliton.com                                            
United States                                                                   
Francis McAllister, Investor Relations                                          
Tel: +1 713 961 8625  Mobile: +1 713 480 3699                                   
email: Francis.R.McAllister@bhpbilliton.com                                     
South Africa                                                                    
Michael Campbell, Investor & Media Relations                                    
Tel: +27 11 376 3360   Mobile: +27 82 458 2587                                  
email: Michael.J.Campbell@bhpbilliton.com                                       
Date: 23/10/2003 08:03:07 AM Supplied by www.sharenet.co.za                     
Produced by the JSE SENS Department
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: