Thu 28 Apr 2005, 9:25 QUARTERLY REPORT ON EXPLORATION AND DEVELOPMENT
Bhp billiton plc - BHP Billiton quarterly report on exploration and development 
activities January 2005 - March 2005                                            
Bhp billiton plc                                                                
Share code     BIL                                                              
Isin:          GB0000566504                                                     
28 April 2005                                                                   
Ref: 19/05                                                                      
BHP BILLITON QUARTERLY REPORT ON EXPLORATION AND DEVELOPMENT ACTIVITIES         
 January 2005 - March 2005                                                      
This report covers exploration and development activities for the quarter ended 
31 March 2005.  Unless otherwise stated, BHP Billiton`s interest in the projects
referred to in this report is 100 per cent, and references to quarters are based
on calendar years.                                                              
The industry is currently operating in an environment where the services and    
supplies necessary to execute its projects are in great demand, and as a result,
delivery of projects to budget and schedule is becoming more challenging.  A    
weakening US dollar combined with the demand for raw materials and hence        
significant levels of project activity are leading to labour shortages and      
rising input costs (such as steel, heavy machinery, fuel and other commodities).
BHP Billiton continues to work with its suppliers, contractors and other        
stakeholders to mitigate the effect of these cost pressures where possible.  We 
have been successful to date.  However, whilst all of our projects are currently
tracking in line or ahead of schedule, some will run over original Board        
approved budgets.                                                               
PETROLEUM DEVELOPMENT                                                           
Atlantis South Development, Gulf of Mexico, USA (BHP Billiton 44%, non-operated)
In February 2005, BHP Billiton approved a revised budget of US$1.1 billion for  
the development of the Atlantis South oil and gas reserves.  The Atlantis South 
development will have a gross nameplate daily capacity of 200,000 barrels of oil
and 180 million cubic feet of natural gas.  During the quarter the production   
platform`s hull left the shipyard in South Korea and installation of suction    
piles has commenced on site.  The project remains on schedule for first         
production in the third quarter of 2006.                                        
MINERALS DEVELOPMENT                                                            
Aluminium                                                                       
Worsley Development Capital Projects (DCP), Australia (BHP Billiton 86%)        
The Worsley Alumina Development Capital Projects were approved in May 2004 with 
a budget of US$192 million (US$165 million BHP Billiton share).  The projects   
will increase alumina capacity by 250,000 tonnes per annum (215,000 tonnes per  
annum BHP Billiton share) to 3.5 million tonnes per annum (3.01 million tonnes  
per annum BHP Billiton share).  Overall the projects are greater than 40 per    
cent complete.  Engineering and procurement activities are nearing completion   
and site activities have increased with a number of major contractors mobilised 
to undertake mechanical and electrical construction work.  Commissioning of the 
DCP is scheduled for the first quarter of 2006.                                 
Base Metals                                                                     
Escondida Norte, Chile (BHP Billiton 57.5%)                                     
The development of the Escondida Norte pit, located approximately 5 kilometres  
north of the existing Escondida mining operations, was approved in June 2003 as 
part of Escondida`s operating strategy to maintain copper production capacity in
future years.  Pre-mine waste stripping continued during the quarter with total 
material movement to the end of March 2005 equalling 166 million tonnes.  During
the period, work on the crushing station and both silo structures continued and 
installation of the overland conveyor belt commenced.  Commissioning of the     
electrical power distribution system is well advanced and control systems       
integration of the Escondida Norte ore into the existing mineral distribution   
system has commenced. Overall project progress is on schedule at approximately  
79 per cent complete with pre-mine development, design and construction         
activities on track to meet first ore delivery to the crusher in the fourth     
quarter of 2005. Development costs are estimated at US$400 million (BHP Billiton
share US$230 million).                                                          
Escondida Sulphide Leach, Chile (BHP Billiton 57.5%)                            
The Escondida Sulphide Leach project was approved in April 2004.  The project   
will produce 180,000 tonnes (103,500 tonnes BHP Billiton share) of copper       
cathode per annum, utilizing a bacterially assisted leaching process on low-    
grade run-of-mine ore from both the Escondida and Escondida Norte pits.  The    
resulting solutions will then be treated in conventional solvent extraction and 
electrowinning plants.  Detailed engineering and procurement activities are     
substantially complete.  Construction underway includes the leach pad base      
preparation, the sea water desalination facilities and the solvent extraction   
and electrowinning civil foundations.  Development costs are estimated at US$870
million (US$500 million BHP Billiton share) and production is scheduled to begin
during the second half of 2006.                                                 
Spence, Chile                                                                   
The Spence Project, approved in October 2004, will be a new open cut mine with  
associated plant facilities capable of producing 200,000 tonnes per annum of    
copper cathode through a combination of chemical and bacterial leaching.  All   
major equipment is being fabricated with some equipment now starting to arrive  
on site. The road relocation is complete and construction of initial camp and   
office facilities continues.  The power line and main substation along with mine
support facilities are also under construction.  The major earthworks contracts 
have been awarded and hiring of personnel for mine operations is nearing        
completion.  Development costs are estimated at US$990 million and production is
scheduled to begin during the last quarter of 2006.                             
Carbon Steel Materials                                                          
Dendrobium Coal Project, Australia                                              
The Dendrobium Mine will be a low cost underground longwall operation capable of
producing 5.2 million tonnes per annum of raw coal (3.6 million tonnes per annum
of clean coal).  Longwall production commenced on 3 April 2005, eight weeks     
ahead of schedule.  Production commissioning was completed on 19 April 2005 and 
the ramp up of longwall operations is now underway. Outstanding project works   
include the completion of the coal fines dryer and installation of a sizer for  
run of mine coal.  Development costs, revised in October 2004, are estimated at 
US$200 million.   As the project has now been successfully commissioned, it will
no longer be included in this report.                                           
Rapid Growth Project 2, Australia (BHP Billiton 85%)                            
The Rapid Growth Project 2 (RGP2) was approved in October 2004. The project     
comprises increases in mine, rail and port capacity through the development of  
Ore Body 18, purchases of additional rolling stock and a new car dumper at      
Finucane Island. Engineering activities are well advanced, tendering procurement
processes are underway and initial site activities have commenced. The project  
will increase installed capacity at Western Australian Iron Ore to 118 million  
tonnes per annum by the second half of 2006.  Development costs are estimated at
US$575 million (BHP Billiton share US$489 million).                             
Diamonds and Specialty Products                                                 
Panda Underground Project, EKATI Diamond Mine, Canada (BHP Billiton 80%)        
The Panda Underground Project, approved in May 2004, will be a 2,600 tonnes per 
day sub-level retreat mine that will deliver approximately 4.6 million tonnes of
ore and 4.7 million carats of high value Panda diamonds to the EKATI process    
plant over a 6 year production life. Underground mine development is progressing
to schedule while construction activities associated with the mine surface      
facilities are nearing completion. All four ventilation shafts have been        
completed. First ore production was successfully achieved to schedule on 26     
April 2005, with full production expected in early 2006.  Development costs are 
estimated at US$182 million (BHP Billiton share US$146 million).                
Stainless Steel Materials                                                       
Ravensthorpe Nickel Project, Australia                                          
The Ravensthorpe Nickel Project was approved in March 2004. The project includes
the development of a mine, treatment plant and associated infrastructure near   
Ravensthorpe in Western Australia.                                              
The Ravensthorpe processing plant will produce a mixed nickel-cobalt hydroxide  
intermediate product (MHP).  Engineering and procurement activities are         
proceeding to schedule.  On site, the major concrete pours to date have been    
completed, access roads are open to traffic, all the construction camp          
accommodation modules are in place, and bulk earthworks progress is enabling the
mobilisation of oncoming contractors.  Development costs are estimated at       
US$1.05 billion, with the first shipment of MHP expected by the second quarter  
of 2007.                                                                        
Yabulu Extension Project, Australia                                             
The Yabulu Extension Project was approved in March 2004. The metal refining     
section of the QNI Yabulu refinery near Townsville in Queensland is being       
expanded to process up to 220,000 tonnes of MHP. This additional processing     
capacity will increase refinery production to 76,000 tonnes of nickel and 3,500 
tonnes of cobalt. Engineering and procurement activities are proceeding to      
schedule. The site infrastructure, site-wide piling, concrete and first tank    
contracts have been awarded. Site work commenced during the period, with        
activity on infrastructure and tankage underway. Development costs are estimated
at US$350 million, with first nickel metal production from the expanded Yabulu  
refinery expected by late 2007.                                                 
PETROLEUM EXPLORATION                                                           
Exploration and appraisal wells drilled during the quarter or in the process of 
drilling as at 31 March 2005.                                                   
WELL              LOCATION      BHP BILLITON      STATUS                        
EQUITY                                          
Scarborough-3, 4a Australia,    50% BHP Billiton  Plugged and abandoned.        
& 5               Exmouth       and operator(1)1  Hydrocarbons                  
                  Plateau                         encountered.                  
West Moonfish-1   Australia,    50% BHP           Plugged and abandoned.        
                  Gippsland     Billiton; Esso    Hydrocarbons                  
                  Basin         operator          encountered.                  
Mad Dog Southwest Gulf of       23.9% BHP         Hydrocarbons                  
Ridge &           Mexico,       Billiton;         encountered. See              
Sidetracks 1 & 2  Green Canyon  BP operator       NewsatBHPBilliton dated       
                  825                             23 March 2005.                
Joseph-1          Gulf of       20% BHP           Drilling ahead.               
Mexico,       Billiton;                                       
                  High Island   Shell operator                                  
                  Block 10L                                                     
Blackbeard West-1 Gulf of       5% BHP Billiton;  Drilling ahead.               
Mexico,       Exxon operator                                  
                  South                                                         
                  Timbalier                                                     
                  Block 168                                                     
Mustang           Gulf of       43.66% BHP        Drilling ahead.               
                  Mexico,       Billiton and                                    
                  West Cameron  operator                                        
                  77 OCS-G-                                                     
9387 #2                                                       
Shenzi-4          Gulf of       44% BHP Billiton  Plugged and abandoned.        
                  Mexico,       and operator      Hydrocarbons                  
                  Green Canyon                    encountered.                  
653                                                           
Knotty Head-1     Gulf of       25% BHP           Drilling ahead.               
                  Mexico,       Billiton;                                       
                  Green Canyon  Unocal operator                                 
512                                                           
Makalu-1          Gulf of       30% BHP           Temporarily plugged and       
                  Mexico,       Billiton;         abandoned.                    
                  Mississippi   Chevron Texaco                                  
Canyon Block  operator                                        
                  937                                                           
BHP Billiton operated and funded 100% of the activity.                          
MINERALS EXPLORATION                                                            
The Minerals Exploration group of BHP Billiton continued to pursue global       
exploration opportunities for key commodities of interest utilising both in-    
house capabilities and the Junior Alliance Programme.                           
Exploration drilling continued on diamond targets in Botswana, Namibia and      
Angola; on porphyry copper targets in Chile and Peru; and on nickel targets in  
Canada. Exploration for iron ore, coal and bauxite was undertaken in a number of
regions including Australia, India, Brazil and West Africa.                     
EXPLORATION EXPENDITURE                                                         
During the quarter, BHP Billiton spent US$31 million on minerals exploration,   
all of which was expensed (US$93 million gross and US$92 million expensed year  
to date), and US$106 million on petroleum exploration, of which US$77 million   
was expensed (US$243 million gross and US$132 million expensed year to date).   
Further information on BHP Billiton can be found on our Internet site:          
http://www.bhpbilliton.com                                                      
Australia                                                                       
Jane Belcher, Investor Relations                                                
Tel: +61 3 9609 3952  Mobile: +61 417 031 653                                   
email: Jane.H.Belcher@bhpbilliton.com                                           
Tania Price, Media Relations                                                    
Tel: +61 3 9609 3815  Mobile: +61 419 152 780                                   
email: Tania.Price@bhpbilliton.com                                              
United Kingdom                                                                  
Mark Lidiard, Investor & Media Relations                                        
Tel: +44 20 7802 4156  Mobile: +44 7769 934 942                                 
email: Mark.Lidiard@bhpbilliton.com                                             
Ariane Gentil, Media Relations                                                  
Tel: +44 20 7802 4177  Mobile: +44 78 81 51 8715                                
email: Ariane.Gentil@bhpbilliton.com                                            
United States                                                                   
Tel: +1 713 599 6100  Mobile: +44 20 7802 4031                                  
email: Mark.Lidiard@bhpbilliton.com                                             
South Africa                                                                    
Michael Campbell, Investor & Media Relations                                    
Tel: +27 11 376 3360  Mobile: +27 82 458 2587                                   
email: Michael.J.Campbell@bhpbilliton.com                                       
_______________________________                                                 
1 BHP Billiton operated and funded 100% of the activity.                        
Date: 28/04/2005 08:53:39 AM           
Produced by the JSE SENS Department
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: