Anglo Platinum - Expansion Projects Review and Rus
Anglo Platinum - Expansion Projects Review and Rustenburg Platinum Mines
Tailings Retreatment Project
Anglo American Platinum Corporation Limited
(Incorporated in the Republic of South Africa)
Registration number 1946/022452/06
ISIN: ZAE000013181
JSE Code: AMS
("Anglo Platinum")
MEDIA RELEASE
Expansion Projects Review and
Rustenburg Platinum Mines Tailings Retreatment Project
On 13 August 2002, Anglo Platinum advised shareholders that it was re-examining
the optimum mix of projects required to raise the annual production rate to 3,5
million ounces of refined platinum by the end of 2006.
Anglo Platinum is pleased to announce that in pursuit of the target of 3,5
million ounces of refined platinum it is implementing a suite of projects
capable of meeting this target by the end of 2006. In line with previous
practice, full details of each project in this suite will be announced upon
Board approval. The suite includes joint ventures with Empowerment groupings,
which will satisfy the requirements of the Mineral and Petroleum Resources
Development Act. To produce at a rate of 3,5 million platinum ounces by the end
of 2006 and to allow for expansion beyond this should market conditions warrant,
the capital amount yet to be spent is R15,3 billion, of which R12,9 billion is
Anglo Platinum`s portion with the balance contributed by joint venture partners.
Capital expenditure to maintain the annual base production level will grow in
line with higher output. Capital expenditure for 2003 will total some R7,7
billion, comprising R3,6 billion to maintain and R4,1 billion to expand
operations. All these capital expenditures are in 2003 money terms. The
production forecast for 2002 remains at 2,25 million platinum ounces, rising to
2,4 million ounces in 2003.
Anglo Platinum is pleased to announce that it will be proceeding with the
development of a tailings retreatment project at its Rustenburg Platinum Mines
complex near Rustenburg in the North West province.
The tailings plant will be situated near the Brakspruit shaft and will draw
feedstock from a number of tailings dams in the Klipfontein and Waterval areas.
Capital expenditure is estimated at R1,6 billion in 2003 money terms. The plant
is expected to commence operations in 2004, reaching full production in 2006 at
an average rate of 120 000 ounces of refined platinum and 38 000 ounces of
palladium per annum. At the planned production rate, the project`s resource base
is sufficient to sustain production for some 15 years.
For further information please consult the Company`s website
(www.angloplatinum.com)
or contact Mike Mtakati
011 373 6865
083 455 7887
28 November 2002
Date: 28/11/2002 02:03:36 PM Produced by the JSE SENS Department
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.