Fri 17 Feb 2023, 15:01 ACSION LIMITED - Construction Contract Constituting a Small Related Party Transaction
Construction Contract Constituting a Small Related Party Transaction

ACSION LIMITED
Incorporated in the Republic of South Africa
(Registration number 2014/182931/06)
Share code: ACS  ISIN: ZAE000198289
(“Acsion” or “the Company” or “the Group”)


CONSTRUCTION CONTRACT CONSTITUTING A SMALL RELATED PARTY TRANSACTION


1. Introduction

   Shareholders are advised that on 16 February 2023, Nabuvax Proprietary Limited (“Nabuvax”), a
   wholly owned subsidiary of Acsion and the owner of the Mall@55, concluded a construction contract
   with K. Anastasi Projects Proprietary Limited (“KAP”) appointing KAP as its principal contractor to
   build an extension of approximately 9,571m2 to the Mall@55 for a cash amount of R99 575 515,
   inclusive of a contingency allowance, as set out in paragraph 3.1 below (“Construction Contract”).

   KAP, which trades in the construction sector, is beneficially owned by the chief executive officer of
   Acsion, Mr Kiriakos Anastasiadis, and his family through a trust structure and therefore the
   Construction Contract is deemed a small related party transaction in terms of the Listings
   Requirements of the JSE Limited (“JSE”).

2. Rationale

   Mall@55 is a convenience shopping centre located in Monavoni, Gauteng with direct access from the
   R55 which connects Sandton and Pretoria. Anchored by seven national retailers, Mall@55 provides a
   convenience retail offering including groceries, homeware and lifestyle, a medical centre, gym and
   other services.

   The expansion of Mall@55 aligns with the Group’s long-term strategic objective of delivering Net
   Asset Value through the execution of its long-term expansion and development plans.

   KAP was appointed as principal contractor on the basis of a market related price for the works, its
   long-standing reputation in the construction industry and track record of successfully executing
   projects of a similar size and nature.

   Pursuant to the Construction Contract, as principal contractor on the project KAP will be responsible
   for planning, leading and executing the general building works as well as overseeing and managing
   other direct contractors/subcontractors of the project.

3. Construction Contract

   3.1   Contract Value and settlement

         The value of the Construction Contract, of R99 575 515, including the contingency allowance
         (“Contract Value”), will be settled by way of cash payments by Nabuvax of such amounts as
         certified in the monthly interim payment certificates issued by the professional quantity
         surveying firm which has been appointed as the principal agent in terms of the Construction
         Contract, within 14 calendar days of the date of presentation thereof.

   3.2   Fairness Opinion

         In terms of paragraph 10.7 of the Listings Requirements, the Construction Contract is deemed
         a small related party transaction and accordingly, the board of directors of the Company
         (“Board”) is required to provide the JSE with written confirmation prepared in accordance with
         Schedule 5 thereof (“Fairness Opinion”), obtained from an independent professional expert
         acceptable to the JSE, confirming that the terms of the Construction Contract are fair insofar as
         shareholders are concerned.

         In compliance with paragraph 10.7(b) of the Listings Requirements, Merchantec Proprietary
         Limited has been appointed as the independent professional expert to provide it with the
         Fairness Opinion.
         As the JSE may, in accordance with Schedule 5, waive the requirement for a valuation in
         relation to related party agreements (other than disposals and acquisitions) on the basis that
         the subject matter of such agreement cannot be valued, the independent professional expert
         will discuss the basis of the Fairness Opinion with the JSE to determine whether a valuation is
         indeed required.

         The Fairness Opinion will be submitted to the JSE for review, whereafter it will lie for inspection
         at Acsion’s registered office, Anaprop Offices, Mall@Reds Cnr Hendrik Verwoerd Drive and
         Rooihuiskraal Drive, Centurion, 0157, and will be made available on request from the Company
         Secretary by emailing michael@mwrk.co.za, for a period of 28 days from the date of issue.

         Shareholders will be kept informed in this regard.


Johannesburg
17 February 2023

Sponsor
Merchantec Capital

Date: 17-02-2023 03:01:00
Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE'). 
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
 the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct, 
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
 information disseminated through SENS.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData


Follow us on: