Not logged in
  Home   Markets   Shares   Funds   Portfolio   Toolbox   Charting   Alerts   Directory   
 Admin   

Wed 13 Aug 2003, 14:43 Progress reports, advice of a liquidation applicat
Diamond Core -                                                            
DIAMOND CORE RESOURCES LIMITED                                                  
(Formerly Mazal Mining and Exploration Limited)                                 
(Incorporated in the Republic of South Africa)                                  
(Registration number 1998/013468/06)                                            
Share code: DMR     ISIN Number: ZAE000045688                                   
("Diamond Core" or "the Company")                                               
Progress reports, advice of a liquidation application and further cautionary    
1.   Progress report on the Paardeberg East project and the Skeyfontein joint   
venture                                                                         
Paardeberg East project                                                         
After Hopkinton Capital Limited ("Hopkinton") acquired control of the Company on
28 February 2003, Geoventures (Pty) Ltd ("Geoventures") was contracted to act as
the independent geologist to the Company at the Paardeberg East project ("the   
property").                                                                     
The exploration program at the property currently involves drilling at two      
locations.  Core drilling is in progress for the purpose of quantifying the     
volume of kimberlite beneath the existing pit known as P1.  Computerised        
modelling is currently being conducted and volumes and tonnages determined.     
Core drilling and the computerised model should be completed towards the end of 
August 2003.                                                                    
Percussion drilling over the area of the property known as P3 has revealed the  
presence of kimberlite over an area 600 meters in length and approximately 30   
meters in width.  A program of core drilling has commenced to investigate this  
occurrence.  The first inclined drill hole intercepted kimberlite over a        
corrected width of 26 meters.  A further 7 holes are scheduled to be drilled    
over the P3 occurrence before the end of August 2003.                           
Geophysical and geological investigations are in progress over target areas P4  
and P5 on the property.  Thus far 8 drill holes have been drilled at P4 but no  
kimberlite intrusion has been found.                                            
Once the drilling program in respect of the property has been completed,        
Geoventures shall prepare a report, whereafter the Company will decide whether  
bulk sampling is warranted or not.                                              
Insufficient information is as yet to hand to enable Hopkinton to comment on the
possibility of it investing a further R10 million in exchange for 126 million   
Diamond Core shares in terms of the option approved by shareholders and issued  
to Hopkinton in February 2003 ("the option").  The option is exercisable at any 
time within a period of 2 months from the completion of a bankable feasibility  
document acceptable to Hopkinton.                                               
Skeyfontein joint venture                                                       
On 30 May 2003, the Company entered into a Memorandum of Understanding to       
conclude a joint venture with the Skeyfontein Communal Property Association     
("CPA") to prospect and, if viable, to embark upon full scale mining on the farm
Skeyfontein.                                                                    
Agreements have been drafted encapsulating the terms and conditions of the      
Memorandum of Understanding and the Company is currently awaiting comments and  
input on these agreements from the CPA and its advisors.                        
The Company hopes to conclude these agreements by mid-August 2003, whereafter a 
prospecting permit shall be issued.                                             
2.   Impairment of assets                                                       
The Board of Diamond Core ("the Board") hereby advises shareholders that,       
subsequent to Hopkinton acquiring control of the Company, Hopkinton commissioned
an inspection of its plant and earthmoving equipment ("the equipment").  The    
equipment has been found to be materially impaired.  It is the Board"s view that
this is a direct result of the manner and fashion in which the equipment was    
purchased, constructed, managed and maintained by previous mine management.  The
equipment was valued in the Company"s accounts at R13 million and the extent of 
the impairment is currently being evaluated by the Board.                       
3.   Progress on the release of the annual report and interim results           
The Board has recently appointed advisors to provide input and guidance on      
several strategic matters relating to the Company"s future activities and its   
capital structure.  The current delay in releasing the annual report for the    
year ended 30 June 2002 is a result of the Board awaiting clarity on these      
matters and agreeing on a route forward.  This is expected to be achieved by mid
August at which time both the annual report for the year ended 30 June 2002 and 
the interim report for the six months ended 31 December 2002 will be sent to    
shareholders.  The Company will then apply to the JSE Securities Exchange South 
Africa ("JSE") to lift the suspension of trading in Diamond Core"s shares.      
4.   Liquidation application                                                    
Leynys Services Limited ("Leynys") has brought an application ("the liquidation 
application") to liquidate Diamond Core Mining & Exploration (Pty) Ltd, a wholly
owned subsidiary of Diamond Core which holds the mineral and surface rights at  
Paardeberg East.  Leynys claims that in excess of R3 million is owing to it.    
The Company has always denied being indebted to Leynys in this amount and is    
defending the liquidation application accordingly.  Shareholders will be kept   
appraised of progress in this matter.                                           
5.   Further cautionary announcement                                            
Shareholders are referred to the cautionary announcement published on SENS on 7 
May 2003.  Although the listing of the Company"s shares on the JSE is currently 
suspended, shareholders are advised to take cognisance of all the matters set   
out above and to continue to exercise caution when dealing over the counter in  
the Company"s shares, or when trading in the Company"s shares when the          
suspension is lifted, until a further announcement is made.                     
Hyde Park                                                                       
13 August 2003                                                                  
Corporate adviser                                                               
QuestCo Investments (Pty) Limited                                               
Sponsor                                                                         
Sasfin Corporate Finance                                                        
A division of Sasfin Bank Limited                                               
Date: 13/08/2003 02:37:09 PM Supplied by www.sharenet.co.za                     
Produced by the JSE SENS Department
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: