Tue 2 Sep 2003, 8:38 PALABORA UNDERGROUND PRODUCTION PROGRESS
PALABORA UNDERGROUND PRODUCTION PROGRESS                                        
PALABORA MINING COMPANY LIMITED                                                 
(incorporated in the Republic of South Africa)                                  
Registration number - 1956/002134/06                                            
Share Code: PAM   ARC ISIN: ZAE000005245                                        
("Palabora" or "the Company")                                                   
PALABORA UNDERGROUND PRODUCTION PROGRESS                                        
Palabora announced today further progress achieved with the ramp up of its      
underground mine to design production levels of 30 000 tons of ore per day.     
As previously announced, production ramp up has been constrained by operating   
difficulties, including the inability to clear drawpoints efficiently that have 
been blocked with poorly fragmented, large rocks.  The company is implementing  
an integrated improvement action plan to address these difficulties.  As a      
consequence of this action plan, production volumes have improved to an average 
of 16 900 tons of ore per day during July and 18 900 tons of ore per day in     
August.  The underground mine achieved a record weekly production rate of 20 800
tons of ore per day during the final week of August, including a record daily   
production rate of 30 038 tons in one day.  Further work is ongoing in order to 
reach the target level of 30 000 tons per day on a consistent basis by the end  
of 2003.                                                                        
As previously announced, the Company cautions that the aggregate impact of the  
limited production from the underground mine, the strength of the Rand against  
the US Dollar and the commencement of depreciation of the underground mine      
capital costs, partly offset by the cost saving actions taken by the Company,   
will impact negatively on the earnings of the Company in 2003.                  
For further information please contact the Managing Director, David Sadler, on  
015 780 2802                                                                    
Phalaborwa                                                                      
1 September 2003                                                                
Sponsor:                                                                        
Barnard Jacobs Mellet Corporate Finance                                         
(Pty) Limited                                                                   
Date: 02/09/2003 07:05:11 AM                    
Produced by the JSE SENS Department                                             
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: