Thu 4 Dec 2003, 8:42 ANGLO PLATINUM EXPANSION REVIEW
ANGLO AMERICAN PLATINUM CORPORATION LIMITED -       
Anglo American Platinum Corporation Limited                                     
(Incorporated in the Republic of South Africa)                                  
Registration No. 1946/022452/06                                                 
JSE share code: AMS                                                             
ISIN: ZAE000013181                                                              
ANGLO PLATINUM EXPANSION REVIEW AND TRADING UPDATE                              
Background                                                                      
On 16 May 2000 Anglo Platinum announced a major expansion programme to increase 
mining production from the 1999 base of some 2 million ounces to 3,5 million    
ounces of refined platinum by the end of calendar year 2006. In that year some  
3,4 million ounces of platinum were expected to be produced. In November 2002   
more details regarding specific projects and capital expenditure to reach this  
target were announced.                                                          
At the half year results presentation on 30 July 2003, shareholders were advised
that the much stronger than anticipated rand and lower US dollar prices for the 
basket of metals sold, had severely affected operating cashflows. Moreover, if  
such prices and exchange rates were to persist, project returns and funding     
requirements would be further impacted.                                         
Consequently, the Group has reviewed all aspects of its strategy and expansion  
programme against a backdrop of:                                                
*    The impact of a 26 percent increase in South African producer price        
inflation on mining costs over the past three years.                       
*    Over the same period, despite an increase in the platinum price, a net     
     decrease of 14 percent in the US dollar value of the basket of metals      
     produced by the Group.                                                     
*    A 50 percent appreciation in the value of the rand from its low of over R13
     to the US dollar in December 2001.                                         
Supply / Demand                                                                 
The review confirmed that current and future demand for platinum remain robust. 
Anglo Platinum remains firmly committed to expanding its production base.       
However, as a result of the factors discussed above, in particular because of   
the uncertainty of the rand"s future movements, Anglo Platinum intends to slow  
down the rate of implementation of its expansion projects. The effect of this   
slowdown on the expected ongoing platinum supply deficit is likely to be        
lessened by an increase in palladium usage in autocatalysts and a softening of  
platinum jewellery offtake.  Anglo Platinum"s long-term strategy to grow markets
for platinum group metals, expand production to meet the increased demand and   
optimise operations remains in place.                                           
Project Progress In 2003                                                        
During 2003 significant progress has been made with the expansion programme.    
The Polokwane smelter, designed to process concentrate from Eastern Limb        
operations, was successfully commissioned in March.  The slag-cleaning furnace  
at Rustenburg was commissioned. The ACP converter plant was brought on stream   
and continues to increase throughput in line with its commissioning schedule.   
Phase 1 of the Rustenburg tailings project is being commissioned ahead of       
schedule.  Agreement was reached with Aquarius Platinum to jointly mine         
contiguous properties in the Kroondal area from which revenue benefits are      
expected in 2004. The Bafokeng-Rasimone and Modikwa projects have continued to  
increase production levels.                                                     
Impact Of The Review                                                            
The impact of the review on Anglo Platinum"s project suite is to slow down the  
implementation of a number of mining projects by between one and three years.   
Ore treatment, smelting and refining projects will continue to be expanded to   
meet the requirements of the build up in the mining profile.  In addition,      
rationalisation of existing operations will be undertaken to improve operating  
margins.                                                                        
Consultations with stakeholders have commenced regarding the implementation of  
operational interventions and the project slowdown.  Anglo Platinum will        
endeavour to soften the impact of actions taken and every effort will be made to
minimise job losses.                                                            
The Group is budgeting to increase production of refined platinum from 2,3      
million ounces in 2003 to approximately 2,45 million ounces in 2004. This       
represents a 2,0 % decline from the previously targeted production level for    
2004 and is based on a rand / US dollar exchange rate of R7,0 to the US dollar. 
The production targets may be revised from time to time, as they remain         
dependent on the rand / US dollar exchange rate and the prices of the metals    
produced and sold by Anglo Platinum.  Should the outlook improve, Anglo Platinum
has the flexibility to accelerate project implementation. The production of     
refined platinum is now planned to increase to approximately 2,9 million ounces 
in 2006 compared to the 3,4 million ounce level originally envisaged.           
In terms of announced projects, the Bafokeng-Rasimone and Modikwa ramp-up       
operations are unaffected. The Twickenham and Der Brochen projects will be      
slowed down.  Anglo Platinum remains in discussion with its black economic      
empowerment partners on the Paschaskraal and Booysensdal projects and will      
complete bankable feasibility studies in due course, following which a joint    
announcement on each project will be made. The Pandora JV implementation may be 
slowed down in agreement with our partners.  The UG2 project at Rustenburg,     
which sources ore from new declines and existing shafts, will be optimised to   
include more of the higher platinum content Merensky ore than originally        
envisaged in the short term.  The second phase of the Rustenburg tailings       
project will be slowed down.  The Kroondal venture will continue as originally  
planned.                                                                        
Capital Expenditure                                                             
Total capital expenditure in 2004 is now expected to be R6,2bn, comprising      
R2,3bn for ongoing capital expenditure, R1,8bn for production replacement       
projects, R1,8bn for expansion projects and R0,3bn for capitalised interest.  In
terms of the revised implementation programme expansion capital expenditure over
the period 2003 to 2006 will reduce from R15,3bn to R11,0 bn.  All capital      
expenditure figures are stated in 2003 money terms.                             
Funding                                                                         
Anglo Platinum is evaluating all financing options to fund the expansion        
programme and expects to finalise proposals by the end of the first quarter of  
2004.  Anglo American has indicated that it remains supportive of Anglo         
Platinum"s expansion plans.                                                     
Black Economic Empowerment                                                      
Anglo Platinum has established significant joint ventures with historically     
disadvantaged South African groupings.  The Group is pleased with the progress  
it has made regarding black economic empowerment.  This progress includes       
facilitating the purchase of 22,5% of Northam Platinum by Mvelaphanda Platinum, 
a 50:50 joint venture with African Rainbow Minerals in respect of the Modikwa   
platinum mine and, subject to the fulfilment of certain suspensive conditions,  
the 50:50 Bafokeng-Rasimone joint venture with the Royal Bafokeng Nation        
incorporating the Styldrift project area. Anglo Platinum remains in discussions 
with the Pelawan and Khumama consortia on the Paschaskraal and Booysensdal joint
venture projects respectively.  The revised project scheduling will not in any  
way affect Anglo Platinum"s black economic empowerment commitments or ability to
comply with the requirements of the Mining Charter.                             
Trading Statement                                                               
Anglo Platinum advised shareholders on 30 July 2003 that it expected earnings   
for the year ending December 2003 to be significantly below those for the year  
ended December 2002 as a result of the stronger rand / US dollar exchange rate. 
As a result of the continued strengthening of the rand and in compliance with   
the revised listings requirements (Section 3.4 (b)) of the JSE Securities       
Exchange South Africa ("JSE"), which became effective on 1 September 2003, the  
Company wishes to advise shareholders that headline earnings for the year ending
December 2003 are expected to be substantially lower than those for the year    
ended December 2002.                                                            
Furthermore the Company has observed that the market consensus of forecast      
headline earnings for the year ending December 2003 is materially higher than   
the Group"s current forecast.                                                   
The difference appears to be mainly as a result of the market assuming a weaker 
average rand / US dollar exchange rate for the year to December 2003 than the   
company expects to achieve when rates are matched to the fluctuating metal sales
profile for the year. Should the rand remain at current levels, the Company     
expects the effective average rand US / dollar exchange rate to be around R 7,4 
to the US dollar for the year.                                                  
In addition, and as a result of the steady strengthening of the rand over the   
year, the Company expects foreign exchange losses to be materially higher in the
second half of the year when compared to the first half, assuming R6,6 to the US
dollar on 31 December 2003. These losses arise due to the difference in exchange
rate between the date of sale of metals in US dollars and the date of conversion
to rand when those revenues are repatriated.                                    
Anglo Platinum has submitted an accountant"s report in relation to this trading 
statement to the JSE in accordance with the listings requirements of the JSE.   
The accountant"s report is available for inspection at Anglo Platinum"s offices 
at 55 Marshall Street, Johannesburg.                                            
The forecast in this trading statement has been prepared using accounting       
policies consistent with those applied at 31 December 2002 except for the change
in the inventory accounting policy as advised to shareholders on 30 July 2003.  
For further information please consult the Company"s website                    
(www.angloplatinum.com)                                                         
or contact Mike Mtakati                                                         
011 373 6865                                                                    
083 455 7887                                                                    
4 December 2003                                                                 
Sponsor                                                                         
Merrill Lynch South Africa (Pty) Limited                                        
Date: 04/12/2003 08:00:08 AM Supplied by www.sharenet.co.za                     
Produced by the JSE SENS Department
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: