Tue 10 Feb 2004, 8:47 MINERAL RESOURCES AND ORE RESERVES AS AT 31 DECEMB
ANGLOGOLD LIMITED - MINERAL RESOURCES AND ORE RESERVES AS AT 31 DECEMBER 2003   
ANGLOGOLD LIMITED                                                               
(Registration number 1944/017354/06)                                            
(Incorporated in the Republic of South Africa)                                  
ISIN : ZAE000043485                                                             
JSE Share Code : ANG                                                            
NYSE Ticker: AU                                                                 
("AngloGold")                                                                   
MINERAL RESOURCES AND ORE RESERVES AS AT 31 DECEMBER 2003                       
Summary And Discussion                                                          
At the time of its formation, AngloGold"s reserve base was associated almost    
entirely with deep-level mining operations in South Africa.  Although the       
company currently has a number of South African organic growth projects in      
development, these deep-level orebodies are finite assets, whose limits, up to a
maximum depth within the bounds of current technology and practice, have largely
been defined. There are limited prospects therefore for growing the South       
African reserve base. Consequently, AngloGold has, since its inception, set     
about seeking to expand its asset and reserve base by acquiring companies and   
exploring for orebodies that will host long-life, high-margin operations. The   
soon-to-be-completed merger with Ashanti Goldfields, which will increase        
AngloGold"s Ore Reserves by some 30%, primarily in the form of the long-life,   
high-margin operations of Obuasi and Geita, is an example of the success of this
strategy.                                                                       
The AngloGold Ore Reserve and Mineral Resource statement as at the end of 2003  
illustrates the continuation of this pattern:                                   
Brownfields exploration generated 3.4Moz of Mineral Resource at a discovery cost
of US$7.79/oz. A further 1.3Moz was added to the Mineral Resource with the      
inclusion of Moab Extension, situated to the south of Kopanang.                 
The conversion of Mineral Resources to Ore Reserves added an additional 1.8Moz  
of Ore Reserve at a cost of US$5.2/oz, with a further 0.8Moz added with the     
inclusion of Moab Extension.                                                    
The total Mineral Resource decreased by 74.9Moz from 287.6Moz in 2002 to        
212.7Moz in 2003. This was primarily due to a revision of the mining depth limit
at Western Ultra Deep Levels (WUDLS) from 5km to 4.5km below datum and an       
increase in the Mineral Resource cut-off grade from 600cmg/t to 750cmg/t,       
resulting in a net loss of 64.8Moz. In addition to this change at WUDLS,        
depletion as a result of mining of Mineral Resources during 2003 reduced the    
total Mineral Resource by 6.6Moz.                                               
The total Ore Reserve decreased by 9.2Moz from 72.3Moz in 2002 to 63.1Moz in    
2003. The key features of thus reduction were:                                  
*    depletion of 6.3Moz;                                                       
*    a reduction of the planned life of mine at Savuka (leading to a reduction  
     of 2.2Moz in the Ore Reserve);                                             
*    a decision to remove the Carbon Leader Reef below the 120 level from the   
     current mine plan at Mponeng (leading to a reduction of 1.7Moz inclusive of
     some Ventersdorp Contact Reef due to a reduction in life); and             
*    the assumption of a lower mine call factor and an update to the geological 
model at Great Noligwa resulting in lower gold values (leading to a        
     reduction of 0.5Moz in the reserve).                                       
These decreases were offset by certain increases in the Ore Reserve, principally
at Sunrise Dam, where new modelling techniques, additional drilling and new     
underground design resulted in an increase of 1Moz in Ore Reserves              
Details of the reconciliation between the 2002 and 2003 Ore Reserve Statements  
are provided in the body of the report.                                         
Detailed Report                                                                 
Introduction                                                                    
The table below sets out AngloGold"s Proved and Probable Ore Reserves as at     
31 December 2003. All information on Proved and Probable Ore Reserves refers to 
AngloGold"s attributable interest. Ore Reserves are reported in accordance with 
the Australasian Code for Reporting of Mineral Resources and Ore Reserves (the  
JORC Code), together with the South African Code for the Reporting of Mineral   
Resources and Mineral Reserves (the SAMREC Code), for the South African         
operations, as well as the requirements of the United States Securities and     
Exchange Commission"s Industry Guide 7. Accordingly, as of the date of          
reporting, all Ore Reserves are planned to be mined out under the life of mine  
plans within the period of AngloGold"s existing rights to mine, or within the   
time period of assured renewal periods of AngloGold"s rights to mine.  In       
addition, as of the date of reporting, with the exception of Geita Ridge 8 and  
Moab Extension where the required permits and government approvals are          
anticipated following the required submissions having been made, all Ore        
Reserves are covered by the required permits and government approvals.          
Assumptions                                                                     
In respect of AngloGold"s South African assets, Ore Reserves were determined    
assuming a gold price of US$350/oz and an exchange rate of ZAR7.00 = US$1. This 
compares with a gold price of US$325/oz and an exchange rate of ZAR10.50 = US$1 
as at 31 December 2002.                                                         
In respect of assets in East and West Africa, Ore Reserves were determined      
assuming a gold price of US$350/oz.                                             
In respect of assets in South America, Ore Reserves were determined assuming a  
gold price of US$350/oz, with the exceptions of Cerro Vanguardia, as well as    
certain parts of Morro Velho, namely Engenho D"Agua and Corrego Do Sitio. The   
Ore Reserves for Cerro Vanguardia, Engenho D"Agua and Corrego Do Sitio were     
determined at US$325/oz.                                                        
Ore Reserves for Cripple Creek & Victor in North America were determined        
assuming a gold price of US$325/oz.                                             
Ore Reserves at AngloGold"s Australian assets were determined assuming a gold   
price of US$234/oz and at an exchange rate of A$1 = US$0.55 for Boddington      
(based upon the gold price and exchange rate assumed for the 2000 feasibility   
study) and at US$350/oz and an exchange rate of A$1 = US$0.63 for Sunrise Dam.  
   The Ore Reserve estimates in this document include Ore Reserves below current
infrastructure in the case of certain South African mines. However, these Ore   
Reserves have been determined based upon completed feasibility studies.         
Ore Reserve Statement                                                           
Mine           Anticipated     Category      Tonnes    Grade    Contained       
               Life of mine    of Ore      (millions)  g/t      gold            
(years)(1)      Reserves                      (million oz)       
South African operations                                                        
WEST WITS                                                                       
Mponeng(3)      15             Proved          2.8      8.74          0.8       
Probable       22.8      9.01          6.6       
                               Total          25.6      8.98          7.4       
Savuka           3             Proved          0.4      6.79          0.1       
                               Probable        1.1      6.76          0.3       
Total           1.5      6.77          0.3       
TauTona(3)      12             Proved          1.6     13.11          0.7       
                               Probable       16.3     11.21          5.9       
                               Total          17.9     11.38          6.5       
Western Ultra                  Proved            -         -            -       
Deep Levels(4)                 Probable          -         -            -       
                               Total             -         -            -       
VAAL RIVER                                                                      
Great Noligwa    9             Proved          4.0      9.46          1.2       
                               Probable       14.9      9.16          4.4       
                               Total          18.8      9.22          5.6       
Kopanang        13             Proved          3.4      6.94          0.8       
Probable       19.8      7.19          4.6       
                               Total          23.2      7.15          5.3       
Moab Khotsong   20             Proved                                   -       
(3)(5)                         Probable       18.8     13.93          8.4       
Total          18.9     13.93          8.4       
Tau Lekoa       13             Proved          7.4      5.05          1.2       
                               Probable       20.6      3.99          2.6       
                               Total          28.0      4.27          3.8       
SURFACE                                                                         
Ergo             1             Proved         29.4      0.38          0.4       
                               Probable          -         -            -       
                               Total          29.4      0.38          0.4       
Vaal River      19             Proved          5.8      0.59          0.1       
Surface                        Probable      153.6      0.56          2.8       
                               Total         159.3      0.56          2.9       
West Wits                      Proved            -         -            -       
Surface                        Probable          -         -            -       
                               Total             -         -            -       
EAST AND WEST AFRICAN OPERATIONS                                                
Geita (50%)(6)  16             Proved         14.2      3.30          1.5       
Probable       21.1      4.17          2.8       
                               Total          35.3      3.82          4.3       
Morila (40%)(6)  9             Proved          4.4      3.55          0.5       
                               Probable        5.9      3.88          0.7       
Total          10.3      3.74          1.2       
Navachab        10             Proved          1.3      1.38          0.1       
                               Probable       10.1      1.81          0.6       
                               Total          11.4      1.76          0.6       
Sadiola(38%)(6) 10             Proved          2.5      1.93          0.2       
                               Probable        7.7      3.53          0.9       
                               Total          10.2      3.14          1.0       
Yatela (40%)(6)  5             Proved          0.9      1.12          0.0       
Probable        3.4      3.84          0.4       
                               Total           4.3      3.25          0.4       
SOUTH AMERICAN OPERATIONS                                                       
Cerro Vanguardia 8             Proved          6.7      7.34          1.6       
(92.5%)(6)                     Probable        0.5     10.16          0.2       
                               Total           7.2      7.56          1.8       
Morro Velho     15             Proved          2.3      7.84          0.6       
                               Probable        5.2      7.01          1.2       
Total           7.5      7.27          1.7       
Serra Grande    11             Proved          1.6      6.17          0.3       
(50%)(6)                       Probable        0.6      7.59          0.1       
                               Total           2.3      6.55          0.5       
NORTH AMERICAN OPERATIONS                                                       
Cripple Creek & 12             Proved         53.9      1.26          2.2       
Victor                         Probable       64.7      0.87          1.8       
                               Total         118.6      1.04          4.0       
AUSTRALIAN OPERATIONS                                                           
Boddington      20 (from       Proved         41.5      0.94          1.3       
(33.33%)(6)(7)      2007)      Probable       88.4      0.84          2.4       
                               Total         129.9      0.87          3.6       
Sunrise Dam     12             Proved          5.4      4.16          0.7       
                               Probable       16.9      4.33          2.3       
                               Total          22.2      4.29          3.1       
Tanami (40%)                   Proved            -         -            -       
(6)(8)                         Probable          -         -            -       
                               Total             -         -            -       
TOTAL                          Proved        189.5      2.31         14.1       
                               Probable      492.4      3.09         49.0       
Total         681.9      2.88         63.1       
   (NB:  Rounding of figures may result in computational discrepancies.)        
Notes:                                                                          
1)   Anticipated Life of Mine is expressed in years from 2004 (or from the year 
of the project"s start-up where this is relevant and indicated as such)    
     based on AngloGold"s current business plan for each operation. These       
     business plans include the mining of Ore Reserves and may include the      
     conversion of Mineral Resources to Ore Reserves. The life of mine is an    
estimate used for business planning purposes and is subject to material    
     change due to future geologic information or economic conditions.          
2)   Ore Reserves include marginally economic and diluting materials delivered  
     for treatment and allow for losses that may occur during mining.           
3)   Probable Ore Reserves include Ore Reserves below current infrastructure,   
     which have been based upon completed feasibility studies.                  
4)   The southerly down-dip extension of Mponeng, Elandsrand (Harmony Gold      
     Mining Company Limited) and Driefontein (Gold Fields Limited), with a      
mining depth limit of 4.5km below surface.                                 
5)   Mine is still in the development stage with stoping only recently having   
     commenced.                                                                 
6)   Ore Reserves attributable to AngloGold"s percentage interest shown in each 
case.                                                                      
7)   The Ore Reserves associated with the Boddington Expansion have been based  
     on the feasibility study completed in 2000 and assume a gold price of      
     US$234 per ounce and an exchange rate of A$1 = US$0.55.                    
8)   No Ore Reserves shown as the mine has been permanently closed.             
Reconciliation                                                                  
The Ore Reserves as at 31 December 2003, show a year-on-year decrease of some   
9.2Moz from 72.3Moz as at 31 December 2002 to 63.1Moz. The reduction in Ore     
Reserves includes a depletion of 6.3Moz (being the ore delivered to             
metallurgical plants and the corresponding reduction in the applicable Ore      
Reserve)                                                                        
The principal changes  in AngloGold"s Ore Reserves for 31 December 2003 relative
to those as published as at  31 December 2002, for reasons other than depletion,
are as follows:                                                                 
*    an increase of 1.0Moz at Sunrise Dam due to new modelling techniques,      
     additional drilling and new underground design;                            
*    a decrease of 1.7Moz at the Mponeng mine due to the exclusion of the Carbon
     Leader below 120 level project. The curtailment of this project  resulted  
     in a shorter life, which reduced some Ore Reserves in the Ventersdorp      
     Contact Reef below 120 Level project. The lower rand per kilogram gold     
price at end 2003 resulted in the Carbon Leader Reef below 120 Level       
     project being no longer feasible and it has now been excluded from Ore     
     Reserves as at 31 December 2003. The project is currently the subject of a 
     revised feasibility study. A weakening of the rand relative to the US      
dollar will also result in these Ore Reserves being included and as a      
     result of the revised feasibility study possibly being further amended;    
*    a decrease of 0.5Moz at the Great Noligwa mine due the assumption of a     
     lower mine call factor and due to updates to the geological model which    
resulted in lower gold values;                                             
*    a decrease of 0.5Moz at the Moab Khotsong mine due to updates to the       
     geological model which resulted in lower gold values;                      
*    an increase of 0.9Moz at the TauTona mine partially as a result of the     
purchase of an area of Gold Fields Limited"s Driefontein Gold Mine;        
*    a decrease of 2.2Moz at the Savuka mine due to updates to the geological   
     model, which resulted in lower gold values, as well as changes in economic 
     factors which has resulted in a considerable proportion of the Mineral     
Resource being considered as no longer feasible to be mined economically;  
*    an increase of 0.3Moz at Tau Lekoa due to the assumption of a higher mine  
     call factor, as well as extensions of the Ore Reserve due to exploration in
     new mining areas;                                                          
*    an increase of 0.6Moz of the Vaal River Surface Ore Reserves, due to the   
     inclusion of the Mizpah plant and the South Tailings facility;             
*    a decrease of 0.2Moz at Cerro Vanguardia due to changes in the pit designs 
     resulting from higher waste mining costs and reduced slope angles;         
*    a decrease of 0.3Moz due to the sale of AngloGold"s interest in the Jerritt
     Canyon Joint Venture in North America during 2003; and                     
*    a decrease of 0.7 Moz due to the sale of Amapari in Brazil during May 2003.
Methodology                                                                     
AngloGold has adopted standard accepted procedures for the estimation of Ore    
Reserves.                                                                       
In the case of its underground mines, the procedure is as follows. Firstly, gold
content and tonnage are estimated for in situ mineralised material at a mining  
operation.  This mineralised material is not necessarily economically viable.   
Exclusions on the grounds of safety (for example, stability pillars, shaft      
pillars) are then defined.  Grade and tonnage curves specific for each of the   
deposits, in conjunction with the cost structure, yield, mine call factor and   
Ore Reserves of the operation and gold price estimates are used to determine an 
optimal mining mix.  This process facilitates the determination of the average  
grade to be mined by each operation.  This grade is then applied to the grade-  
tonnage curves, which in turn facilitates the determination of the cut-off grade
and reserve tonnage for the operation.  A full mine design is carried out on the
blocks of mineralised material, excluding large mining areas that do not meet   
the cut-off grade criterion.  This mining plan is reviewed to ensure that it    
satisfies the economic criterion and practical limitations of access and timing.
If the review process is positive then the mineralised material (with dilution) 
included in the mining plan is declared and published as the ore reserve for    
that operation.                                                                 
In the case of surface, open-pit mines the procedure is as follows: Revenue and 
costs are calculated for each mining block within a three-dimensional model of  
the orebody using assumed values for gold price, operating costs, metallurgical 
recoveries and slope angles. An optimisation process is then applied to         
determine all the blocks combined within the model that make a positive         
contribution under these assumptions. Within this process a cut-off grade is    
applied which determines the ore blocks to be treated and included in Ore       
Reserve. These blocks are scheduled with consideration being given to practical 
mining considerations and limitations. Scheduled ore blocks that are classified 
as Proved or Probable constitute the Ore Reserve.                               
Mineral Resources and Ore Reserves are reported in accordance with the          
Australasian Code for Reporting of Mineral Resources and Ore Reserves (the JORC 
Code) and the South African Code for the Reporting of Mineral Resources and     
Mineral Reserves (the SAMREC Code).                                             
Competent Persons                                                               
Competent Persons, designated in terms of the JORC and SAMREC Codes and taking  
corporate responsibility for the reporting of AngloGold"s Mineral Resources,    
are:                                                                            
V A Chamberlain, MSc (Mining Engineering), BSc (Hons) (Geology), MAusIMM, 18    
years" experience.                                                              
M F O"Brien, M Sc (Engineering), BSc (Hons) (Geology), Pr.Sci.Nat., MAusIMM, 24 
years" experience.                                                              
Designated competent persons taking corporate responsibility for the reporting  
of Ore Reserves are:                                                            
B W Guenther, BSc (Mining Engineering), MAusIMM, 23 years" experience.          
D L Worrall, ACSM, MAusIMM, 23 years" experience.                               
J van Zyl Visser, BSc (Mineral Resource Management), PLATO, 17 years"           
experience.                                                                     
The Competent Persons are employed by AngloGold Limited and have consented to   
the inclusion of the Mineral Resources and Ore Reserves information in this     
document.                                                                       
Johannesburg                                                                    
10 February 2004                                                                
Queries:                                                                        
www.anglogold.com                                                               
South Africa        Tel:                Mobile:         E-mail:                 
Steve Lenahan       +27 11 637 6248     +27 83 308 2200 slenahan@anglogold.com  
Alan Fine           +27 11 637 6383     +27 83 250 0757 afine@anglogold.com     
Shelagh Blackman    +27 11 637 6379     +27 83 308 2471 skblackman@anglogold.com
Europe & Asia                                                                   
Tomasz Nadrowski    +1 917 912 4641                     tnadrowski@anglogold.com
USA                                                                             
Charles Carter      (Toll free) 800 417 9255                                    
                    +1 212 750 7999                     cecarter@anglogold.com  
Australia                                                                       
Andrea Maxey        +61 8 9425 4604     +61 438 001 393 amaxey@anglogold.com.au 
CAUTIONARY STATEMENT CONCERNING FORWARD-LOOKING STATEMENTS                      
Certain statements in this announcement are forward-looking within the meaning  
of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the
Securities Exchange Act of 1934, as amended, including without limitation, those
statements concerning (i) timing, fulfillment of conditions, tax treatment and  
completion of the Merger, (ii) the value of the transaction consideration, (iii)
expectations regarding production and cost savings at the combined group"s      
operations and its operating and financial performance and (iv) synergies and   
other benefits anticipated from the Merger.  Although AngloGold and Ashanti     
believe that the expectations reflected in such forward-looking statements are  
reasonable, no assurance can be given that such expectations will prove to have 
been correct.                                                                   
For a discussion of important terms of the Merger and important factors and     
risks involved in the companies" businesses, which could cause the combined     
group"s actual operating and financial results to differ materially from such   
forward-looking statements, refer to AngloGold"s and Ashanti"s filings with the 
US Securities and Exchange Commission (the "SEC"), including AngloGold"s annual 
report on Form 20-F for the year ended 31 December 2002, filed with the SEC on  
7 April 2003 and Ashanti"s annual report on Form 20-F for the year ended        
31 December 2002, filed with the SEC on 17 June 2003 and any other documents in 
respect of the Merger that are furnished to the SEC by AngloGold or Ashanti     
under cover of Form 6-K.                                                        
Neither AngloGold, Ashanti nor the combined group undertakes any obligation to  
update publicly or release any revisions to publicly update any forward-looking 
statements discussed in this announcement, whether as a result of new           
information, future events or otherwise.                                        
ADDITIONAL INFORMATION                                                          
In connection with the Merger, AngloGold will file with, or otherwise furnish   
to, the SEC a scheme document/prospectus.  Investors and security holders are   
urged to carefully read the scheme document/prospectus regarding the Merger when
it becomes available, because it will contain important information.  Investors 
and security holders may obtain a free copy of the scheme document/prospectus   
(when it is available) and other documents containing information about         
AngloGold and Ashanti, without charge, at the SEC"s website at www.sec.gov.     
Copies of the scheme document/prospectus together with any SEC filings that may 
be incorporated by reference in the scheme document/prospectus may also be      
obtained free of charge by directing a request to:                              
AngloGold Limited,                                                              
11 Diagonal Street, Johannesburg 2001,                                          
PO Box 62117, Marshalltown 2107,                                                
South Africa,                                                                   
Attention:     Chris R. Bull,                                                   
               Company Secretary,                                               
Telephone      +27 11 637 6000,                                                 
fax:           +27 11 637 6624.                                                 
UBS Investment Bank and First Africa Group Holdings (Pty) Limited ("First       
Africa") are acting for AngloGold and no one else in connection with the Merger 
and will not be responsible to anyone other than AngloGold for providing the    
protections afforded to clients of UBS Investment Bank or First Africa or for   
providing advice in relation to the Merger.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: