Fri 2 Apr 2004, 11:54 FIRST QUARTER 2004 - UPDATE ON THE UNDERGROUND
PALABORA MINING COMPANY LIMITED - FIRST QUARTER 2004 - UPDATE ON THE UNDERGROUND
  MINE                                                                            
  PALABORA MINING COMPANY LIMITED                                                 
  (Incorporated in the Republic of South Africa)                                  
  Registration number - 1956/002134/06                                            
  Share Code: PAM   ARC ISIN: ZAE000005245                                        
  ("Palabora" or "the Company")                                                   
  FIRST QUARTER 2004 - UPDATE ON THE UNDERGROUND MINE                             
  Average copper production in the first quarter of 2004 of 153 tonnes per day was
  10% higher than the fourth quarter of 2003.  Although ore hoisted of 20,200     
  tonnes per day was 8% lower than the fourth quarter of 2003, mine rescheduling  
  is resulting in higher copper grades and improved cave management.              
  The undercut has now been completed and 18 out of the planned 20 cross cuts are 
  operational.  Production was disrupted in both February and March by a conveyor 
  belt tear and a water ingress event.   The secondary breaking of drawpoint      
  material continues to be a production bottleneck and, as previously advised,    
  additional secondary breaking units will be delivered over the course of the    
  next couple of months.                                                          
  Improvement steps continue to ensure that production moves toward the previously
  established targets.  Work to achieve this is focussed on improvements to       
  equipment availability and more efficient secondary breaking. As always, the    
  safety of employees and contractors is being given first priority and will not  
  be compromised to achieve production targets.                                   
  A more complete Q1 brief will be published once all Q1 statistics are available.
  More information on the Company"s performance will be available on the website  
  www.palabora.com.                                                               
  The following table summarises recent daily underground production:             
  Final Quarter 2003     22,000 tonnes ore per day average                        
                         140 tons Cu per day average                              
  First Quarter 2004     20,200 tonnes ore per day average                        
                         153 tons Cu per day average                              
  For further information please contact the Managing Director, Keith Marshall, on
  +27 (0) 15 780 2802.                                                            
  Phalaborwa                                                                      
  2 April 2004                                                                    
  Sponsor :                                                                       
  Barnard Jacobs Mellet Corporate Finance (Pty) Limited                           
  Date: 02/04/2004 11:30:07 AM Produced by the JSE SENS Department
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: