Mon 28 Jun 2004, 8:33 SUCCESSFUL COMPLETION OF SCOPING STUDIES
SUB NIGEL - SUCCESSFUL COMPLETION OF SCOPING STUDIES AND WITHDRAWAL OF          
            CAUTIONARY ANNOUNCEMENTS                                            
Sub Nigel Gold Mining Company Limited                                           
(Incorporated in the Republic of South Africa)                                  
(Registration number 1984/006179/06)                                            
JSE Share code: SBN                                                             
ISIN: ZAE000006391                                                              
(`Sub Nigel` or `the company`)                                                  
SUCCESSFUL COMPLETION OF SCOPING STUDIES AND WITHDRAWAL OF CAUTIONARY           
ANNOUNCEMENTS                                                                   
1.   Shareholders are referred to the cautionary announcement dated 8 April 2004
relating to the company completing a scoping study on both its Ventersburg 
     and Spaarwater projects and are advised that the board of directors of Sub 
     Nigel has completed these studies.                                         
2.   The Sub Nigel board is pleased to announce that the scoping studies for    
both the Spaarwater project on the East Rand, South Africa and the         
     Ventersburg project in the Free State, South Africa have now been finalised
     and signed off by Metallurgical Design Management (Proprietary) Limited    
     (`MDM`).                                                                   
3.   The scoping study for the Spaarwater project indicates that at the current 
     gold price, the project is robust, and the recommendations put forward by  
     MDM to the Sub Nigel board are as follows:                                 
     3.1  The company should commence with a 3-month pre Bankable Feasibility   
Study (pre-BFS) on the project to verify the grade and tonnage used in
          the scoping study as well as to verify the state of the underground   
          conditions.                                                           
     3.2  The project should ultimately be developed as a 40,000 ton per month  
operation, from two existing shafts on the property and should include
          the construction of a 40,000-ton per month carbon in leach (`CIL`)    
          processing facility to treat this ore.                                
4.   The project is currently estimated to cost R126 million, which includes R70
million for a CIL processing facility. The company previously reported that
     it expected the project to cost R 50 million, however, this assumed that   
     the company would toll treat its ore at a suitable processing facility in  
     the region.                                                                
5.   The company has completed its first phase of drilling on the northern most 
     area of the Spaarwater property. 1 primary intersection and 4 deflections  
     intersected a mineralised Nigel reef at an approximate depth of 453 metres.
     The grades ranged from 1.4 g/t to 3.8 g/t over an average thickness of 0.89
metres and illustrated the potential for significant pay shoot development.
     The recommendation by the consultants is for a secondary drilling programme
     over the area at close spacing to be completed.                            
6.   The scoping study for the Ventersburg project indicates that at the current
gold price, the project is robust, and the recommendations put forward by  
     MDM to the Sub Nigel board are as follows:                                 
     6.1  The company should continue with a drilling programme on the project  
          area to confirm the historical drilling results in the area, to       
increase the resource base to the North and South of the current      
          project area and thirdly to do in-fill drilling on the project area.  
          The company recently announced that it had begun drilling on the      
          Ventersburg project area to confirm an extension of the resource.     
6.2  The project should be developed as a 90,000 ton per month operation   
          and include the construction of a 90,000 ton per month CIL processing 
          facility to treat this ore                                            
          The project is estimated to cost R241 million. The company previously 
reported that it expected the project to cost R800 million to         
          complete, but this assumed a 200,000-ton per month mining operation.  
7.   Shareholders are therefore no longer required to exercise caution when     
     dealing in their Sub Nigel shares in this regard.                          
8.   Shareholders are further referred to the cautionary announcement dated 4   
     May 2004 and are advised that the negotiations referred to therein have    
     been terminated.                                                           
Johannesburg                                                                    
28 June 2004                                                                    
Sponsor                                                                         
Sasfin Corporate Finance                                                        
A division of Sasfin Bank Limited                                               
Date: 28/06/2004 08:19:07 AM                 
Produced by the JSE SENS Department
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: