Wed 28 Jul 2004, 12:43 Production Resumes At Barplats" Crocodile River M
Barplats  - Production Resumes At Barplats` Crocodile River Mine                
Barplats Investments Limited                                                    
(Incorporated in the Republic of South Africa)                                  
(Registration number 1987/004830/06)                                            
Share Code: BPL                                                                 
ISIN:       ZAE000028692                                                        
(`Barplats` or `the Company`)                                                   
PRODUCTION RESUMES AT BARPLATS` CROCODILE RIVER MINE                            
Production at Barplats Investments Limited`s Crocodile River Mine near Brits in 
South Africa`s North West Province resumed today (Wednesday, 28 July 2004) with 
the ceremonial detonation of the first blast by the company`s new chairman,     
Loucas Pouroulis.                                                               
Pouroulis was the founder of the mine, then known as Lefkochrysos, in 1987 which
was eventually taken over by Rand Mines Limited and subsequently by Impala      
Platinum Holdings (Implats).                                                    
At the beginning of July this year, Pouroulis was lead representative for a     
consortium of institutional investors in the acquisition of Implats` 83.2%      
interest in Barplats for R390 million.                                          
`The extent and quality of Barplats assets, and a new, enthusiastic team give me
every confidence that we will successfully complete what was started 18 years   
ago. The project goal is to return the mine to its rated capacity of 150 000    
tonnes per month over the next three years.`                                    
Managing director David Salter says Barplats` guiding philosophy going forward  
will be to `Build on Basics`, with a focus on safety, grade, recovery and costs.
`The new mining plan will have three phases - start-up, lasting approximately 8 
to 12 months; build-up to full production during the ensuing 28 to 36 months;   
and maintenance of production at the highest economic level thereafter.`        
Initial production will be from the mine`s Maroelabult Section where six panels 
are ready to mine. Production from the Zandfontein Section is expected to begin 
late in 2004 or early in 2005, once re-equipping and repairs have been          
completed. A combination of mechanized mining and conventional stoping will be  
employed at both sections.                                                      
`Currently, the team is evaluating several possible mining plans for the        
Zandfontein Section with the goal of identifying the most cost effective,       
efficient plan for short and long term return of value from the assets,` Salter 
added.                                                                          
Refurbishment of the mine`s 150 000 tonnes per month concentrator and 120 000   
tonnes per month dense medium separation (DMS) plant has begun and the first    
treatment of ore is scheduled for late October 2004.                            
Queries:  David Salter   James Duncan                                           
          +27 11 460 1791 (office) +27 11 880 3924 (office)                     
          +27 83 410 1795 (mobile) +27 82 895 0698 (mobile)                     
          Marion Brower  Zenzele Bam                                            
+27 11 880 3924 (office) +27 11 880 3924 (office)                     
          +27 82 895 0698 (mobile) +27 83 544 1827 (mobile)                     
DISCLAIMER:                                                                     
This announcement may contain certain forward-looking statements concerning     
Barplats` operations, economic performance and financial condition, and plans   
and expectations. These statements, including without limitation, those         
concerning the economic outlook for the platinum group metals (PGM) industry and
market, expectations of PGM prices, production, the commencement and completion 
of certain exploration and production projects, may contain forward-looking     
views. Such views involve both known and unknown risks, assumptions,            
uncertainties and other important factors that could materially influence the   
actual performance of the company. No assurance can be given that these will    
prove to be correct and no representation or warranty, express or implied, is   
given as to the accuracy or completeness of such views or as to any of the other
information in this announcement. Barplats` future results may differ materially
from past or current results, and actual results may differ materially from     
those projected in the forward-looking statements.
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: