Tue 19 Apr 2005, 17:33 Palabora -First Quarter 2005 - Operations overview
Palabora - First Quarter 2005 - Operations overview and production statistics   
PALABORA MINING COMPANY LIMITED                                                 
(Incorporated in the Republic of South Africa)                                  
Registration number - 1956/002134/06                                            
Share Code: PAM        ISIN: ZAE000005245                                       
(`Palabora` or `the Company`)                                                   
FIRST QUARTER 2005 - OPERATIONS OVERVIEW AND PRODUCTION STATISTICS              
1Q     2Q     3Q    4Q    1Q   YEAR
                                            2004   2004   2004  2004  2005  2004
 Palabora mine                                                                  
 Tonnes hoisted (`000 tonnes)              1,833   1,910 2,405 2,464 2,335 8,612
Ore treated (`000 tonnes)                 2,101   1,897 2,345 2,314 2,156 8,657
 Average ore grade: copper (%)              0.76    0.74  0.75  0.73  0.72  0.74
 Copper concentrates produced (`000         35.9    35.4  64.2  52.2  48.0 187.7
tonnes)                                                                         
Average concentrate grade: copper (%)      29.7    28.3  27.7  30.6  29.3  29.0
 Copper in concentrates (`000 tonnes)       10.7    10.0  17.8  16.0  14.1  54.4
 Palabora smelter/refinery                                                      
 New concentrate smelted on site (`000      59.4    68.0  59.0  67.0  75.2 253.4
tonnes)                                                                         
 New copper anodes produced (`000 tonnes)   15.8    19.7  14.4  17.3  20.0  67.2
 Refined new copper produced (`000 tonnes)  17.9    17.2  16.2  16.2  18.7  67.5
 By-products:                                                                   
Magnetite concentrate (`000 tonnes)         105     160   144   165   201   574
 Refined nickel sulphate (tonnes)             53      37    36    41    34   167
 Vermiculite plant                                                              
 Vermiculite produced (`000 tonnes)         38.4    51.5  52.7  50.8  48.1 193.4
The underground mining operation hoisted 2,335,700 tonnes during the quarter and
represented a 5% decline compared to the previous quarter. The main issue       
affecting production was a planned shutdown (18 days) on the North winder to    
replace a failing bearing in the last two months of the quarter. Average daily  
production was 25,952 tonnes, and represented a 3.1% decline over the previous  
quarter. A new daily production record of 38,585 tonnes was achieved during the 
period. The copper grade averaged 0,72%, slightly below the previous quarter.   
Copper recoveries in the concentrator declined slightly to 87.3% from 88% in the
previous quarter. Dolerite content from drawpoints was higher at 13.3% and 13.9%
in February and March, after reduced levels in the fourth quarter of 2004. Lower
bornite content in the first two months of the quarter led to lower grades      
relative to the fourth quarter of 2004 to preserve recovery.                    
Smelter throughput was higher during the quarter following unplanned maintenance
on the Power Plant in the previous quarter. Improved operating practices were   
implemented during the fourth quarter and improving the daily smelting rates.   
The new copper in anodes is higher due to the increase in concentrate smelted.  
Total concentrate smelted was 75,230 tonnes of which 20,960 tonnes (28%) were   
purchased.                                                                      
Refined copper production was in line with anode supply from the Smelter.       
Average number of operating sections increased from 12 to 13 in the first       
quarter of 2005.                                                                
Vermiculite Operations                                                          
Vermiculite production was in line with the plan for the quarter and 25%  higher
than  the  corresponding quarter for 2004.  A decline in coarseness of ore  body
particle  size distribution in the lower benches affected the plant  and  mine`s
capability  to respond to the high demand of Medium and Fine grade. Consequently
in  March the mine decided to review the mining sequence and access new areas to
enhance  the  production  recovery  of coarser  grades.  Overall,  the  improved
recoveries  achieved  across  the plant following  the  initiatives  implemented
earlier in the year continued and will in turn be the target for 2005.          
Magnetite                                                                       
Magnetite production outstripped increased demand during the period, leading  to
an extended maintenance shutdown towards the end of the quarter.                
For further information please contact the Managing Director, Keith Marshall, on
+27 (0) 15 780 2802.                                                            
Phalaborwa                                                                      
19 April 2005                                                                   
Sponsor:                                                                        
Barnard Jacobs Mellet Corporate Finance (Pty) Limited                           
Date: 19/04/2005 05:26:11 PM
Produced by the JSE SENS Department                                             
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site