PRODUCTION DIFFICULTIES EXACERBATE TOUGH TRADING CONDITIONS FOR WESTERN AREAS   
Keeping company with the big four gold mining houses that have announced their  
first quarter results, Western Areas Limited has reported a profit decline of   
almost 200% for the three months to March 2005.                                 
The company reported a loss of R186,8 million compared to a R189,9 million      
profit for the quarter ended December 2004. A negative fair value adjustment of 
R126,9 million (compared to a positive R187,9 million fair value adjustment in  
the previous quarter) contributed to the loss of 158,2 cents a share (compared  
to a positive 161,1 cents a share previously).                                  
However, CEO Brett Kebble, said the major cause of the reversal this quarter was
a 452 kilogram decline in gold production from the 1891 kilograms for the       
previous quarter (based on the company`s 50% interest in the South Deep Mine),  
and the fair value adjustments.                                                 
This was mainly due to pump and water column failures in the old South Shaft    
system that interrupted services for both the South Shaft and Twin Shaft        
complexes for 10 days. Production problems were compounded by the loss of       
working time during the January start-up and the Easter holidays.               
Underground ore production for the quarter was supplemented by treating 112 000 
tonnes of low-grade ore from surface stockpile material, but there was          
nonetheless a reduction of 27 000 tonnes to 265 000 tonnes of ore milled.       
Kebble indicated that the loss of production for the quarter would partially be 
recovered by re-arranging working rosters of conventional stoping crews in      
addition to the recovery of `lock-up` material from a clean-up of the old       
processing plant.                                                               
`Although gross costs were contained, cash costs per kilogram increased from R71
513/kg in the December quarter to R87 278/kg, mainly due to the production      
problems,` he said.                                                             
The average dollar spot gold price achieved (before hedging) decreased from     
$435/oz in the December quarter to $427/oz. The benefit of a historically strong
US $ gold price was offset by a strong Rand which averaged R6.02/$ for the      
quarter.                                                                        
The average Rand price of gold thus declined only slightly from R83 976/kg for  
the December quarter to R83 345/kg.                                             
`Taking into account our hedge obligations, principally `out of the money` sold 
call options, we realised an average gold price of only R58 193 /kg.`           
`The encouraging news is that the commissioning of the Twin Shaft in the last   
quarter of 2004 and the development on 100 Level has started to open up high-   
grade VCR reserves and to provide access to the Elsburg Massives to the east of 
the Upper Elsburg.`                                                             
Kebble said that South Deep management was on track to finalise a 25-year long- 
term mine plan by July 2005. He was of the view that the plan could well        
motivate accelerated development on 100, 105 and 110 Levels in support of an    
increase in production to approximately 320 000 tons per month by 2010.         
South Deep had stopped pumping water from the Randfontein Estates No. 4 Shaft   
owned by Harmony.                                                               
`Independent experts have confirmed the integrity of the boundary plugs and     
pillars separating No. 4 shaft from South Deep. The Department of Minerals and  
Energy (DME) is currently evaluating the water barrier and have instructed      
Harmony to continue pumping at the shaft until such time as a closure           
certificate has been issued.`                                                   
Kebble says the Placer Dome Western Areas Joint Venture partners are confident  
that South Deep has no obligation to dewater the neighbouring shaft but that    
discussions continue with Harmony regarding the interim cost of pumping.        
Discussions with underwriters were also under way regarding the insurance claim 
arising from a fall of ground in the SV1 shaft in January 2004. Placer Dome Inc,
which administers the mine`s insurance, was optimistic that there would be a    
`fair negotiated settlement`.                                                   
Discussions are progressing with the hedge banks to restructure the derivative  
structure to `more appropriately match the South Deep production profile.`      
Meanwhile Western Areas will proceed with a R800 million rights issue to finance
the capital expenditure needed to ramp-up production at South Deep and service  
its hedge obligations.                                                          
Taking into consideration that the life of mine plan for South Deep is scheduled
to be completed by the end of 2005, refinancing of the Option Premium Payable   
and the possible conversion of this obligation into a Rand denominated          
obligation will be undertaken `as soon as practically possible` says Kebble.    
Statement issued on behalf of Western Areas Limited by Brian Gibson Issue       
Management (Contact Brian Gibson on 011 880 1510 or 083 253 5988)               
12 May 2005                                                                     
About Western Areas Limited                                                     
Western Areas is focused on investment in the African gold mining industry. The 
Company`s principal asset is its 50% interest in the South Deep Joint Venture.  
South Deep is a joint venture between Western Areas and Placer Dome SA (Pty)    
Ltd, a subsidiary of Placer Dome Inc.                                           
About the PDWA JV                                                               
The Placer Dome Western Areas Joint Venture (PDWA JV) was established on 31     
March 1999. It is jointly controlled by Western Areas and Placer Dome SA. The   
PDWA JV is administered and governed by a PDWA JV board in terms of a joint     
venture agreement (JVA).                                                        
Western Areas and Placer Dome are each entitled to appoint three directors to   
the JV board. The Placer Dome entitlement to appoint the chairman is dependent  
on Placer Dome maintaining an interest in excess of 40% in the PDWA JV.  The    
chairman has the casting vote, except on a wide range of defined issues where   
board decisions could have a material impact on the business, in which case the 
decision must be unanimous.                                                     
About South Deep                                                                
South Deep is a joint venture between Western Areas and Placer Dome SA (Pty)    
Ltd, a subsidiary of Placer Dome Inc.                                           
Situated in the magisterial districts of Westonaria and Vanderbijlpark, some 45 
kilometers south west of Johannesburg, the mine encompasses one of the world`s  
largest gold mineral reserves, with an estimated 56.6 million ounces of gold in 
the Proved and Probable Mineral Reserve categories.  At its deepest, the mine   
will be more than 3 300 metres below surface.                                   
The South Deep Twin Shaft complex, built at a cost of some R4 billion, was      
officially opened by the Deputy President of South Africa, Mr Jacob Zuma, on 4  
February 2005.                                                                  
Date: 12/05/2005 05:02:09 PM Supplied by www.sharenet.co.za                     
Produced by the JSE SENS Department                                             
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: