Tue 20 Sep 2005, 14:57 Anglo Platinum Corporation Limited - Polokwane Sme
Anglo Platinum Corporation Limited - Polokwane Smelter Shutdown Update          
Anglo Platinum Corporation Limited                                              
Incorporated in the Republic of South Africa                                    
Registration No.: 1946/022452/06                                                
JSE Ordinary Share Code: AMS                                                    
ISIN: ZAE000013181                                                              
JSE Preference Share Code: AMSP                                                 
ISIN: ZAE000054474                                                              
(`Anglo Platinum`)                                                              
POLOKWANE SMELTER SHUTDOWN UPDATE                                               
Anglo Platinum announces that the detailed technical examination referred to in 
its announcement on 8 September 2005 has been completed. The findings show that 
the failure of a single waffle cooler led to water ingress into the furnace.    
The examination also revealed a concerning general level of corrosion across all
the waffle coolers and it is considered necessary to replace the complete waffle
cooler installation. In addition, following the corrosion disruption in         
September 2004, it was decided to modify the waffle cooler design by introducing
a split cooler system. The modification will allow easier corrosion             
identification and cooler replacement in future. The modification was originally
scheduled to be installed in early 2006 and has been brought forward as part of 
this repair.  It is expected that the work will be complete by the end of       
November and normal smelting operations will resume in mid-December 2005.       
Anglo Platinum is implementing contingency arrangements to minimise the effect  
of the smelter shutdown on metal flow and annual production and will utilise    
excess industry smelting capacity where possible.                               
Anglo Platinum`s forecast production volume for 2005 is likely to be affected   
and unit costs will be higher due to transport and possible toll treatment      
costs.  The impact on production, on the assumption that excess industry        
capacity cannot be economically accessed, would be to reduce planned refined    
platinum production from 2,6 million to approximately 2,45 million ounces for   
2005. Metal in concentrate not smelted and refined would be released in the     
first half of 2006. The impact of contingency arrangements on production and    
unit costs will be announced once finalised.                                    
For further information, please contact                                         
Trevor Raymond                                                                  
(011) 373-6462                                                                  
082 654 8467                                                                    
Date: 20/09/2005 02:20:08 PM        
Produced by the JSE SENS Department
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: