Fri 28 Oct 2005, 8:27 Aquarius - Quarter ended 30 September 2005
Aquarius Platinum Limited - Quarter ended 30 September 2005                     
Aquarius Platinum Limited                                                       
(Incorporated in Bermuda)                                                       
Registration number: EC26290                                                    
Share code on JSE: AQP        ISIN: BMG0440M1029                                
Share code on ASX: AQP.AXISIN: BMG0440M1029                                     
ROBUST PRODUCTION PROFILE, COUPLED WITH RISING PGM PRICES DELIVERS              
STRONG PROFIT RESULTS                                                           
  Quarterly cash profit climbs strongly to $17.7 million, resulting in a net    
   profit of $9.9 million                                                       
  Record group attributable production: 103,869 PGM ounces, marginally up from  
the last quarter                                                             
  Expansion projects on track                                                   
  Cold commissioning commenced at the new Everest Mine                          
  New senior debt facility in place                                             
Highlights of the Quarter                                                       
Kroondal (PSA1)                                                                 
  Expanded operation produced 115,362 PGM ounces (Aquarius attributable 57,681  
   PGM ounces)                                                                  
Underground operations produced a record 1.59 million tons                    
  New No. 4 decline on schedule                                                 
  Underground production ramp up on schedule to 540,000 tons per month by       
   December 2005                                                                
Marikana                                                                        
  Production increased marginally to 27,322 PGM ounces                          
  Operating cash margin of 8% for the quarter, Mine reports a net profit in     
   September month                                                              
Trial underground mining continues, reporting favourable mining conditions    
  Marikana P&SA2 (signed with Anglo Platinum in July 2005) approvals in         
   process                                                                      
Mimosa                                                                          
Production increased to a record 36,368 PGM ounces (Aquarius attributable     
   18,184 PGM ounces)                                                           
  Wedza Phase IV upgrade commenced                                              
  Cash costs decreased 7% to $361 per PGM ounce and to $106 per PGM ounce       
after by-product credits                                                     
  Currency devaluation restores margins, new monetary policy issued in October  
Everest                                                                         
  Construction activities proceed on schedule and within budget                 
Ore stockpile at 220,000 tons                                                 
  Cold commissioning of the plant has commenced                                 
  Hot commissioning in December 2005, ahead of schedule                         
CTRP                                                                            
Production disappoints due to problems feeding dump material into circuits,   
   with lower than anticipated recoveries on certain feeds                      
  Alternative process equipment to be fitted during the second quarter to       
   improve throughput and recovery                                              
Commenting on the results, Stuart Murray, CEO of Aquarius Platinum said,        
"Aquarius has worked hard, and I am encouraged to see that our efforts to       
expand production and enhance efficiencies at all our operations are finally    
resulting in significant improvements to the bottom line. The results of this   
quarter are set to continue going forward, and I am confident this will be a    
good year for shareholders."                                                    
Production by Mine                                                              
PGMs (4E)                           Quarter Ended                               
Dec 2004     Mar 2005         Jun 2005    Sept 2005         
Kroondal              71,523       69,051          116,669      115,362         
Marikana              24,019       26,509           26,940       27,322         
Mimosa                30,386       33,529           35,644       36,368         
CTRP                       -          644            1,473        1,363         
Total                125,928      129,733          180,726      180,415         
Production by Mine Attributable to Aquarius                                     
PGMs (4E)                           Quarter Ended                               
Dec 2004     Mar 2005         Jun 2005     Sep 2005         
Kroondal              35,761       34,526           58,335       57,681         
Marikana              24,019       26,509           26,940       27,322         
Mimosa                15,193       16,765           17,822       18,184         
CTRP                       -          322              737          682         
Total                 74,973       78,122          103,834      103,869         
Aquarius announces consolidated earnings for the quarter to 30 September 2005   
of $9.9 million (US 11.9 cents per share) as the Group"s expansion program      
continues to deliver increased profits.Cash earnings (before depreciation and   
amortisation) were $17.7 million.                                               
Aquarius Attributable Production and Net Profit Summary                         
                                   Qtr Mar     Qtr June    Qtr Sept             
2005         2005        2005             
PGM Production (attributable                                                    
ounces)                             78,122      103,834     103,869             
Net Profit After Tax & Outside                                                  
Equity Interests                    $6.0 m       $8.9 m      $9.9 m             
Production of PGMs attributable to shareholders of Aquarius was 103,869 PGM     
ounces, up slightly from the previous quarter ended June 2005, with all mines   
achieving consistent performance.                                               
Revenue for the quarter, net of currency adjustments, was $78.7 million. Net    
finance charges for the quarter were $0.6 million comprising interest expense   
of $1.6 million, offset by interest income of $1.0 million.                     
Depreciation was higher at $5.8 million due to capital expenditure on the       
developments and expansions at Kroondal and Marikana.Amortisation arising from  
the fair value uplift of mineral rights at $2.0 million reflects increased      
production.                                                                     
Aquarius Group cash balances at 30 September 2005 were $102.6 million, an       
increase of $27.3 million. Material items other than mine operations that       
affected cash balances during the quarter included a redraw from the debt       
facility of $25.3 million and capital expenditure of $32.1 million.             
Over the quarter, the US Dollar was on average 3% stronger against the Rand at  
an average exchange rate of R6.52 to the US Dollar.This coupled with increased  
production and higher US dollar PGM basket prices achieved during the quarter   
all contributed to the improved quarterly profit performance.                   
Kroondal"s mining cash costs, excluding development costs for the quarter       
increased marginally. Costs per ROM ton increased 5.1% to R155. Costs per PGM   
ounce increased 3.1% to R2,012. Reported cash costs, however, on a per ROM ton  
basis increased by 11% to R181 compared to the previous quarter and cash cost   
per PGM ounce increased by 13% to R2,489 per PGM ounce. The increase is         
attributed to a 73% increase in development cost to ensure the production       
build-up to 540,000 tons/month, and higher than normal escalation charges,      
impacted by higher fuel prices and annual wage increases.                       
Marikana returned a gross margin of 8% despite cash costs being impacted by     
some "one-off" costs. These "one-off" costs involved additional stripping due   
to the unanticipated change in location of Pit A reef sub-outcrop as well as    
the removal of clay layers found in Pit A as a contingency against heavy        
rainfall. Cash costs were R280 per ROM and R4,268 per PGM ounce.                
Operating costs at the Mimosa Mine decreased 7% to $358 per PGM ounce, and $106 
per PGM ounce after by-product credits. This decrease in cash costs is          
predominantly attributed to a devaluation of the Zimbabwean currency to         
Z$26,002 to the Dollar.                                                         
Foreign Exchange                                                                
Rand                                                                            
Over the quarter, despite the Rand weakening on average, the spot rates for the 
Rand strengthened marginally to close the quarter at R6.36 to the Dollar,       
having started the quarter at R6.52 to the Dollar.                              
Zimbabwe Dollar                                                                 
The Zimbabwean dollar devalued to Z$26,002 to the Dollar during the quarter.    
This largely compensated for the abolition of the FOB export credit and cost    
inflation.                                                                      
Metals Prices                                                                   
The value of the basket continued to rise during the quarter to close at R5,721 
per PGM ounce. This represents a 40% increase since January 2005 when the       
basket price was below R4,000 per PGM ounce.Encouragingly, this upward move has 
continued into the current quarter, having at one point already broken through  
R 6,000 per PGM ounce.                                                          
The platinum price closed for the quarter at a twenty-five year high of $929    
per ounce, having risen 14% since January 2005. The rhodium price was           
particularly strong, increasing by 43% to $2,740 per from $1,920 per ounce in   
the previous quarter. Palladium also demonstrated positive gains, increasing 7% 
to $194 per PGM ounce from $181 per PGM ounce.                                  
The basket price for the operations in South Africa improved from R4,716 ($746) 
to R5,262 ($807) at AQPSA, due to a strong rise in the rhodium price.           
Significantly the South African basket price broke through R6,000 per PGM ounce 
near the quarter"s end.                                                         
The basket price for the operations in Zimbabwe improved from $603 to $614, due 
to the improvement in the platinum price. Mimosa mine in Zimbabwe produces      
significant nickel/copper as a by-product, contributing approximately 30% of    
Mimosa"s revenue. Base metal prices remained strong during the quarter, with    
nickel falling back lightly from recent highs to $6.92 per pound and copper     
continuing to advance, increasing 3% to $1.50 per pound, since the previous     
quarter.                                                                        
Aquarius Platinum Limited                                                       
Consolidated Income Statement                                                   
Quarter ended 30 September 2005                                                 
US$"000                                                                         
                                                                  Financial     
Quarter      Quarter          year     
                                          ended*        ended         ended     
                                        30/09/05     30/09/04      30/06/05     
Aquarius PGM Production                                                         
103,869       67,486       327,669     
(attributable ounces)                                                           
                               Note                                             
Revenue                         (i)       80,992       45,591       222,327     
Forex sales adjustments        (ii)      (2,325)        (363)         2,797     
Total revenue                             78,667       45,228       225,124     
Cost of sales                 (iii)     (55,859)     (42,749)     (174,936)     
Gross profit                              22,808        2,479        50,188     
Amortisation of fair value                                                      
uplift                                                                          
of mineral properties                    (1,958)        (941)       (6,745)     
Gross profit after                                                              
amortisation                                                                    
of fair value uplift                      20,850        1,538        43,443     
Admin & other costs                      (1,144)      (1,173)       (5,976)     
Finance costs                  (iv)      (1,644)      (2,113)           484     
FX movements                    (v)        (480)        1,963       (9,889)     
Profit before tax                         17,582          215        28,062     
Income tax expense                       (3,940)      (1,306)       (3,446)     
Profit after tax                          13,642      (1,091)        24,616     
Minority interest              (vi)      (3,780)        1,136       (3,666)     
Net profit for the period                  9,862           45        20,950     
Earnings per share (basic -                                                     
cents)                                      11.9         0.05          25.3     
* Unaudited                                                                    
Notes on the Consolidated Income Statement                                      
(i)   Revenue is up 78% from the previous corresponding quarter due to          
      increased production and higher PGM prices                                
(ii)  Reflects effects of adjusting revenue recorded at time of production to   
      cash received at the end of the four month pipeline                       
(iii) Cost of sales on a per PGM ounce basis are lower from the previous        
      corresponding quarter due to increased level of low cost ounces from      
Kroondal production                                                       
(iv)  Finance costs reflect interest expense on Group interest bearing          
      borrowings                                                                
(v)   Reflects foreign exchange movements on translation of net monetary assets 
(vi)  Minority interests reflects 29.5% and 20% outside equity interest of      
      Savannah Consortium and Impala Platinum Holdings Limited (Implats) in     
      AQPSA                                                                     
Aquarius Platinum Limited                                                       
Consolidated Cash Flow Statement                                                
Quarter ended 30 September 2005                                                 
US$"000                                                                         
                                                Quarter      Financial          
ended *     year ended          
                                               30/09/05       30/06/05          
                                       Note                                     
Net operating cash inflow              (i)       31,264         31,458          
Net investing cash outflow             (ii)    (32,103)       (88,152)          
Net financing cash inflow              (iii)     25,923         54,921          
Net increase (decrease) in cash held             25,084        (1,773)          
Opening cash balance                             75,251         77,942          
Exchange rate movement on cash                    2,297          (918)          
Closing cash balance                            102,632         75,251          
* Unaudited                                                                     
 Notes on the Consolidated Cash Flow Statement                                  
(i)   Net operating cash flow includes $31.1 million net inflow from            
      operations, $0.9 million net finance costs and $0.9 million income tax    
      payments                                                                  
(ii)  Reflects payments for mine construction costs of $32.1 million, relating  
mainly to the new Everest operation                                       
(iii) Reflects proceeds from redraw of finance facilities of $25.3 million,     
      conversion of options $0.4 million and repayment of share plan loans $0.1 
      million                                                                   
Aquarius Platinum Limited                                                       
Consolidated Balance Sheet                                                      
at 30 September 2005                                                            
US$"000                                                                         
Quarter     Financial year     
                                                 ended *              ended     
                                       Note     30/09/05           30/06/05     
Assets                                                                          
Cash assets                             (i)      102,632             75,251     
Current receivables                    (ii)       42,548             44,695     
Other current assets                  (iii)       19,732             16,312     
Non-current receivables                (iv)        2,735              2,928     
Mining assets                           (v)      444,645            408,765     
Other non-current assets                           1,106                541     
Total Assets                                     613,398            548,492     
Liabilities                                                                     
Current liabilities                    (vi)       39,615             35,480     
Non-current payables                  (vii)      157,738            150,735     
Non-current interest-bearing                                                    
liabilities                          (viii)       45,028             16,037     
Other non-current liabilities          (ix)       82,353             78,315     
Total Liabilities                                324,734            280,567     
Net Assets                                       288,664            267,925     
Equity                                                                          
Parent entity interest                           250,479            235,352     
Minority interest                                 38,185             32,573     
Total Equity                                     288,664            267,925     
* Unaudited                                                                     
Notes on the Consolidated Balance Sheet                                         
(i)   Cash balance is up due to redraw on finance facilities,                   
      $25 million during the quarter                                            
(ii)  Reflects debtors receivable on PGM concentrate sales                      
(iii) Increase reflects stockpile build up to accommodate the P&SA expansion.   
(iv)  Reflects employee share plan loans                                        
(v)   Increase in mining assets mainly relates to Everest construction          
(vi)  Includes tax payable ($12 million) and creditors ($28 million)            
(vii) Reflects deferred income from BEE transaction ($10.6 million) and         
      portion of Implats and Savcon non interest bearing shareholder loans      
      ($148.5 million)                                                          
(viii)Reflects non-current portion of Investec debt and Savcon interest         
bearing shareholder loan                                                  
(ix)  Reflects deferred tax liabilities $56 million, provision for closure      
      costs $26 million                                                         
AQUARIUS PLATINUM (SOUTH AFRICA) (PTY) LTD (Aquarius Platinum 50.5%)            
Kroondal Platinum Mine                                                          
Safety                                                                          
The DIIR for the quarter was unchanged from the previous quarter at 0.65.The 12 
month rolling DIIR has improved to 0.67, reflecting the improved longer-term    
safety performance.                                                             
Mining                                                                          
  P&SA expansion nears completion, underground operations produced a record     
   1.59 million tons                                                            
New No. 4 decline is on schedule                                              
  Underground production is on schedule for ramping up to 540,000 tons per      
   month by December 2005                                                       
Kroondal: Metal in concentrate produced (PGM ounces)                            
Quarter        Pt         Pd         Rh      Au        PGMs          PGMs (4E)  
ended                                                  (4E)    attributable to  
                                                                      Aquarius  
Sep-05     69,129     33,420     12,250     563     115,362             57,681  
Jun 05     69,875     33,728     12,499     567     116,669             58,335  
Mar 05     41,366     19,971      7,408     306      69,051             34,526  
Dec 04     42,659     20,815      7,723     326      71,523             35,761  
Processing                                                                      
DMS feed increased by 1.0% to 1.59 million tons                               
  Production decreased by 1.1% to 115,362 PGM ounces                            
  Overall recovery increased by 1.3% to 78.3%                                   
Operations                                                                      
Operations produced 1,583,000 tons from underground and 125,000 tons from       
opencast mining.                                                                
Development and equipping of additional underground mining areas continued at   
the Central, East and No. 3 decline shafts. In addition, underground mining at  
the new No. 4 decline shaft continues on schedule.In total, 1,265 metres of     
development were completed during the quarter.                                  
The increase in mining area as a result of down-dip development as part of the  
P&SA project has had a marked positive effect on production, with an average of 
2.2km of dip face length mined every month.                                     
Surface stockpiles were depleted due to the early completion of the K2          
concentrator and the rapid tonnage build-up during the ramp-up phase.           
The head grade to the plant reduced marginally to 2.88g/t from 2.99g/t in the   
previous quarter.This was due to development material from underground and a    
lower in-situ grade of the surface stockpile material.                          
PGM Production decreased slightly by 1.1% to 115,362 4PGE ounces for the        
quarter (Aquarius attributable 57,681 PGM ounces, largely as a result of the    
lower than expected head grades at number 3 shaft and significant development   
tonnages.                                                                       
It is anticipated that total underground mining production will reach           
sustainable steady state production of 540,000 tons per month by December 2005. 
Remaining work on the P&SA expansion, notably the surface and underground       
infrastructure at the No 4 decline shaft, is scheduled for completion by        
December 2005.                                                                  
Both plants (K1 and K2) continued to perform well, with recoveries improving by 
1.3% overall. The plants processed 1,590,000 tons during the quarter at 77% and 
79% recovery respectively for K1 and K2 concentrators. Recoveries, though       
better by 1.3 % than the previous quarter, were affected by reduced head grade  
and the processing of open cast tons.                                           
K1 plant continued to perform above design capacity of 250,000 tons per         
monthand strong improvements in grind were achieved following a complete reline 
of the ball mill during July 2005.                                              
The K2 plant continued to perform at above designed tonnage capacity with       
recoveries improving from 76% during commissioning to 79% during the quarter.   
This improvement is attributed to optimisation of the DMS plant, fines handling 
circuit, and primary mill grinding. The K2 spiral plant has also been           
commissioned and is producing on-specification chrome.                          
Mining cash costs, excluding development costs for the quarter increased        
marginally by 5.1% to R155 per ROM ton and by 3.1% to R2,012 per PGM ounce.     
Reported cash costs, however, on a per ROM ton basis increased by 11% to R181   
compared to the previous quarter and cash cost per PGM ounce increased by 13%   
to R2,489 per PGM ounce. The high cost increases can be attributed to a 73%     
increase in development cost to ensure the production build-up to 540,000 tpm   
is achieved, and higher escalation charges, impacted by annual wage increases   
and high fuel prices The PGM basket price increased quarter on quarter by 9%    
from $745 per PGM oz to $813 PGM oz at an average ZAR / US$ exchange rate of    
R6.52.                                                                          
P&SA1 PROJECT                                                                   
The P&SA expansion works continued well and are nearing completion. All         
conveyor installations are complete, with electrical installations nearing      
completion. At the new No.4 Shaft, the materials handling system (silo, silo    
truck load-out facility, silo feed belt, transfer station, decline belt and     
underground decline tip) was completed to schedule. .                           
The final capital cost is expected well below budget. The figures presented     
below include mining, plant and infrastructure portions of the project. The     
estimated final cost is R689.2 million (100% basis), R132.5 million below the   
escalated budget largely due to deferment into future ongoing capital. R587.2   
million has been paid to date.                                                  
Environmental Management                                                        
Environmental management at Kroondal continues to be a fundamental element of   
the day to day operations.                                                      
Minimising dust pollution from tailings dams is a considerable challenge for    
all mining operations in the region.Following numerous trials on different      
methods of dust suppression on the K1 tailings dam, an overhead water spraying  
system was installed.The system was commissioned on 1 September 2005 with       
excellent results, and will now be rolled out to the remaining two tailings     
dams. This is an industry first that third parties, including government are    
observing with interest.                                                        
During the quarter, specific attention was also given to:                       
Environmental management of all contractors at Kroondal                       
  Community/Stakeholder liaison in terms of dust management and rehabilitation  
  Water management                                                              
Marikana Platinum Mine                                                          
Safety                                                                          
  Two lost time injuries were reported for the quarter. The 12 month rolling    
   DIIR reduced slightly from 0.81 to 0.80 for the current quarter. The FY06    
   DIIR rate stands at 0.57 for the quarter.                                    
Mining                                                                          
  Both opencast mining contractors delivered against revised mining schedules.  
  Stockpiles at the end of the quarter totalled 66,000 ROM tons.                
  Trial underground mining has extended some 60m down dip of the portals.       
Processing                                                                      
  417,043 ROM tons were processed during the period, an increase of 3% on the   
   previous quarter.                                                            
  Concentrator plant recoveries for the period were 62% overall and in line     
with expectations despite high variability in the feed.                      
  A record 27,322 PGM ounces were produced.                                     
  End of quarter ROM stockpiles contain an estimated recoverable 2,900 PGM      
   ounces.                                                                      
Operations                                                                      
PGM production increased quarter-on-quarter by 1.4% to a new record of 27,322   
PGM ounces.                                                                     
Marikana made a modest 8% cash margin for the quarter, and realized a modest    
net operating profit in September 2005 for the first time since commencement of 
operations.                                                                     
Cash cost for the quarter was R280 per ROM ton and R4,268 per PGM ounce.        
Increases on the previous quarter are 17% and 19% respectively.                 
The increase in cash costs is largely attributed to the two new pits, pit "A"   
and "SW"; currently being opened up to sustain production. These had a negative 
impact on mining rates and costs. Oxidized reef from Pit A extended an          
approximate 15m deeper than expected. Hence the ratio of oxidized to fresh reef 
ratio was higher than planned which impacted negatively on recovery, but more   
importantly, on planned plant throughput. Due to the clay- like nature of the   
oxidized reef, this reef can only be processed effectively and efficiently when 
blended with more competent reef at ratios in the order of 5% - 10%. The effect 
of this is, however, reflected by stockpiles of approximately 66,000 ROM tons   
with an estimated recoverable 2,900 ounces locked up within them, available at  
the end of the quarter.                                                         
Approximately 50% of the cash cost increase was due to an authorized increase   
in strip ratio during July 2005 to allow for additional stripping due to the    
unanticipated change in location of Pit A reef sub-outcrop, as well as the      
removal of clay layers found in Pit A as a contingency against heavy rainfall.  
These costs are deemed as one-off and not on-going.                             
The PGM basket price increased quarter-on-quarter by 10.5% from R4,722 per PGM  
ounce to R5,216 per PGM ounce at an average R/$ exchange rate of R6.52.         
Marikana: Metal in concentrate produced (PGM ounces)                            
Quarter ended       Pt      Pd      Rh    Au  PGMs(4E)                          
Sep-05          17,244   7,409   2,466   203    27,322                          
Jun 05          16,893   7,402   2,428   217    26,940                          
Mar 05          17,230   6,759   2,324   196    26,509                          
Dec 04          15,808   6,214   1,800   197    24,019                          
Marikana Pool & Share Agreement (P&SA2)                                         
On 13 July 2005, AQPSA announced a second Pooling and Sharing Agreement with    
Anglo Platinum. In terms of this agreement the Marikana ore-body and            
concentrator plant will be pooled with Rustenburg Platinum Mines (RPM)          
underground UG2 ore reserves on the farm Brakspruit. At the Marikana            
concentrator a dense media separation plant (DMS) will be added allowing an     
increase in throughput to 250,000 tpm.                                          
The P&SA2 will see Kroondal P&SA reserves associated with No 4 Shaft move to    
Marikana, while these reserves are replaced with reserves from RPM"s Townlands  
property. This leaves the Kroondal P&SA ounce neutral. Once the P&SA2 is        
effective this exchange of reserves will have little or no impact on Kroondal   
P&SA production.                                                                
The P&SA2 is subject to a number of conditions precedent and regulatory         
approvals. With good progress made during the quarter, it is expected that all  
outstanding requirements will be met during the second quarter.                 
The finalisation of the agreement will result in a revised Business Plan for    
Marikana. Underground mining production from No.4 shaft and Marikana, will      
gradually replace opencast mining production at Marikana at significantly lower 
operating costs.                                                                
Trial Underground Mining                                                        
Poor ground conditions were experienced within 15m into the high wall in both   
portals which necessitated the installation of steel sets and concrete to       
stabilise the area. This delayed sinking of the declines by a month. Conditions 
underground to date are favourable and the outlook is positive for achieving    
future planned tonnage build up                                                 
Contractor dispute with Moolman Mining                                          
Aquarius Platinum (South Africa) (Proprietary) Limited ("AQPSA"), is currently  
engaged in arbitration proceedings instituted against AQPSA by Moolman Mining,  
a division of Grinaker LTA Limited ("Moolman Mining"), relating to the          
application of a "rise and fall formula" provided for in the opencast mining    
contract concluded between Moolman Mining and AQPSA for AQPSA"s Marikana Mine.  
At the request of Moolman Mining, AQPSA agreed to postpone the arbitration      
proceedings indefinitely to adhere to a request from Moolman Mining to audit    
the weightings in the rise and fall formula by KPMG, who would also investigate 
the basis for the original weightings inserted in the mining contract at the    
request of Moolman Mining.                                                      
A leading forensic auditor, Professor Harvey Wainer, was appointed by AQPSA to  
monitor the auditing process and to investigate the conduct of Moolman Mining   
when the mining contract was concluded.                                         
In AQPSA"s view, KPMG has inferred that the weightings inserted in the mining   
contract by Moolman Mining were materially defective and significantly, KPMG    
disclaimed any view on Moolman Mining"s explanation for the gross "error" in    
their calculations in the following words -                                     
"Basis for disclaimer of conclusion                                             
We obtained a schedule detailing the various categories of expenses per the     
original tender of R799 million, as well as a schedule allocating the various   
expense categories to the cost elements (as per appendix B), however we were    
not able to obtain sufficient appropriate evidence to substantiate the basis    
on which Moolman Mining allocated the expenses included in the tender to        
the cost elements of "fuel", "local" and "foreign".                             
Disclaimer of conclusion                                                        
Because of the significance of the matter described in the preceding paragraph, 
we do not express an opinion on the calculation and determination of the        
original weightings for "fuel", "local" and "foreign" as reflected in the       
agreement."                                                                     
AQPSA views the matter in a very serious light. The disclaimer in the KPMG      
report, suggests that there may have been a material misrepresentation of the   
facts by Moolman Mining at the time when the mining contract was concluded,     
which induced AQPSA to agree to the terms proposed by Moolman Mining. AQPSA is, 
however, awaiting the report from its advisors, before a final decision is      
taken on the matter.                                                            
AQPSA has received a "pro forma" invoice from Moolman Mining for escalation,    
based on a proposed revision of the original contractual weightings. Moolman    
Mining relied on the KPMG audit in compiling this pro forma invoice. The        
validity of this pro forma invoice is under investigation by AQPSA"s advisors,  
as part of the enquiry into the apparent misrepresentation of facts by Moolman  
Mining at a time when they caused the original weightings to be inserted into   
the mining contract.                                                            
Everest Platinum Mine                                                           
Safety                                                                          
The DIIR for the quarter rose to 0.41 from 0.39 in the previous quarter as a    
result of three lost time injuries.                                             
Highlights                                                                      
  Construction activities are on schedule and within budget                     
  Opencast mining and underground mining activities on programme, with          
   220,000 tons on stockpile                                                    
Plant commissioning is set for December 2005                                  
Mining                                                                          
Opencast mining progressed well during the period, with opencast production     
from both the North and South pits. Opencast mining is ahead of programme, with 
a total of 145,720 opencast ROM tons produced during the quarter.               
The decline development in the footwall was completed during the period, with   
reef intersection on programme. Underground services have been fully            
commissioned and 18,000 tons of underground ROM tons were produced. Combined    
opencast and underground mining have yielded a stockpile of 220,000 ROM tons,   
approximately 10,000 ROM tons more than planned.                                
Everest Mine Development (end September 2005)                                   
Progress                                                                        
The Everest construction programme is proceeding as planned.                    
Earthworks, civil construction and erection of steel structures are complete,   
with piping, electrical and instrumentation and tailings dam construction       
continuing during the period.Engineering, design and procurement activities are 
proceeding in parallel and project execution is on track for hot commissioning  
during December 2005.                                                           
Everest will mine and process 250,000 tons per month of UG2 ore to produce      
225,000 ounces of PGMs per annum at steady state, with full production to be    
attained by the end of 2006.                                                    
The implementation of Social Upliftment and Sustainable Livelihood projects is  
ongoing. Contractor recruitment of local labour is proving beneficial with 523  
local people employed during the period.                                        
The Everest capital budget is R819 million including a R33 million allowance    
for escalation. The Everest project capital expenditure commitments were R622   
million at the end of the quarter with capital expenditure paid to date of R413 
million.                                                                        
MIMOSA INVESTMENTS                                                              
Mimosa Mine (Aquarius 50%)                                                      
Safety                                                                          
Safety performance improved by 65% achieving a DIIR of 0.12 for the quarter     
compared to a DIIR of 0.34 for the previous quarter.The rolling 12 months DIIR  
closed at 0.22 down from 0.31 as at the end of June 2005.                       
Production                                                                      
Satisfactory results were achieved in all operations with ROM and PGM           
production increasing 10% and 2% respectively compared to the previous          
quarter.ROM production at 433,000 dry metric tons achieved during the quarter   
was in line with the increase in lashing capacity following the delivery of     
additional underground vehicles. The PGM feed grade improved was constant at    
3.75g/t. A 1% improvement in the recovery rate to 78% resulted in an increase   
in the total PGM ounces produced to a record 36,368 (previous quarter 35,644).  
Mimosa: PGMs in concentrate produced (ounces)                                   
                                                                  PGMs (4E)     
Quarter        Pt         Pd        Rh        Au       PGMs    attributable     
ended                                                  (4E)     to Aquarius     
Sep-05     18,548     13,915     1,407     2,498     36,368          18,184     
Jun 05     18,269     13,518     1,406     2,451     35,644          17,822     
Mar 05     17,189     12,665     1,343     2,332     33,529          16,765     
Dec 04     15,557     11,514     1,198     2,117     30,386          15,193     
Mimosa: Base metals in concentrate produced (tons)                              
                                  Mine Production   Attributable to Aquarius    
Quarter                                                                         
ended                              Ni      Cu     Co      Ni      Cu     Co     
Sep-05                            512     422     15     256     211      8     
Jun 05                            514     420     15     257     210      8     
Mar 05                            491     407     14     245     203      7     
Dec 04                            444     374     13     222     187      6     
Revenue                                                                         
The gross revenue realized for the quarter was up by 20% to US$27.6 million     
compared to US$23.0 million for the previous quarter. The increase is directly  
attributable to 2% increase in both the PGM basket price and PGM ounce produced 
to US$614 per ounce and 36,368 respectively.                                    
Operating Costs                                                                 
Cash costs per PGM ounce for the quarter decreased by 7% to US$361 compared to  
US$389 for the quarter ending 30 June 2005. After by- product credits cash      
costs per ounce were 36% lower at US$105 compared to US$164 in the previous     
quarter. The reduction in the cash costs was attributable to a 49% devaluation  
of Zimbabwean dollar during the quarter from Z$17,500 to US$1.00 down to        
Z$26,002 to US$1.00. However the full benefits of this devaluation were partly  
eroded by a cost push inflation of local costs and the scrapping of 25% Export  
Incentive Scheme by the Reserve Bank of Zimbabwe.                               
Wedza Phase IV Upgrade                                                          
The mine embarked on the Wedza Phase IV upgrade project to increase production  
by 25% to 170,000 PGM ounces (86,000 platinum ounces). The project follows      
finalization of the Account Management Agreement with the Reserve Bank of       
Zimbabwe (RBZ) in terms of the Enhanced Platinum Sector Regime (EPSR), the      
granting of a project status by the Ministry of Finance and the conclusion of a 
US Dollar based loan facility with the Merchant Bank of Central Africa (MBCA).  
The project is due for completion by June 2006.                                 
Foreign exchange                                                                
Post the closure of the quarter ended September; the Reserve Bank of Zimbabwe   
(RBZ) issued its 2005 3rd Quarter Momentary Policy Statement on 20 October      
2005. The policy relaxed controls on foreign exchange management by introducing 
a new Tradable Foreign Currency Balances System (TFCBS) to replace the highly   
regulated Foreign Exchange Auction Floor System. The new regime together with   
the Enhanced Platinum Sector Regime allows platinum exporters to retain foreign 
currency in FCA"s for 45 days. Any balance not utilised in the 45 days is       
exchanged at the ruling inter bank market rate. The new regime is favourable to 
exporters and should assist mine profitability going forward.                   
AQUARIUS PLATINUM (SA) CORPORATE SERVICES (PTY) LTD                             
Chromite Tailings Retreatment Plant (CTRP) (Aquarius 50%)                       
Safety                                                                          
No lost time injuries occurred during the quarter.                              
Processing                                                                      
  Throughput during the quarter remained low due to problems in feeding         
certain dump material into the process. The installation of cyclones to      
   remove excess water from the Xstrata feed helped to raise throughput during  
   September.                                                                   
  Production was lower than the previous quarter due to a decrease in PGM       
recovery. The drop off in recovery is a result of excessive water in the     
   circuit, which has been rectified by the installation of the cyclones.       
   Recovery of the dump material is still below expectation and negatively      
   affecting overall plant recovery.                                            
Operations                                                                      
Cash costs per PGM ounce for the quarter were $448. Costs are above plan        
estimates and are expected to reduce once steady state production is achieved.  
Despite current high production costs, the operation is cash positive and       
returns a small profit.Optimisation of the flotation circuit continued during   
September.During the second quarter additional process equipment will be tested 
with the aim of solving the feed problems, improving density control and        
increasing recoveries. Significant improvements in production are expected from 
the third quarter.                                                              
CORPORATE MATTERS                                                               
New debt facility                                                               
AQPSA has entered into a new debt facility with Rand Merchant Bank to refinance 
its existing debt facilities on significantly improved terms. The new facility  
of R700 million will provide AQPSA with the requisite funding for any future    
growth opportunities and for balance sheet optimisation. It reflects the        
substantially improved operational profile of AQPSA in comparison to that in    
existence when the facility was originally entered into in 2002.                
The facility has been structured as a 6 year amortising senior loan and         
provides AQPSA with a large degree of flexibility in managing its funding cost  
and financial risk. The facility can be denominated in either Rands or US       
Dollars at AQPSA"s election and AQPSA is entitled at any time during the        
facility term to repay and or redraw principle amounts subject to the           
amortising facility limit not being breached.                                   
The margin payable on the new facility will be 190 basis points above both      
JIBAR and LIBOR.                                                                
Existing debt facility                                                          
R175 million ($25.3 million) was redrawn against the existing debt facility for 
providing assurances of funding capacity as the Company enters into P&SA2. This 
debt will be repaid and cancelled by drawing on the RMB facility.               
Statistical Information: Kroondal P&SA1: (Aquarius 50%)                         
Data reflects 100% of                                                           
mine                                                                            
operations                                                                      
operations                                                                      
                                  Unit     Current     Previous           %     
                                                                     Change     
Quarter      Quarter     Quarter     
                                              Sept         June          on     
                                              2005         2005     Quarter     
Safety                                                                          
Rate/200,000                                          
                                   man                                          
DIIR                             hours        0.65         0.65           -     
Revenue                                                                         
Gross Revenue                       RM         573          466          23     
PGM basket Price                  $/oz         813          745           9     
Gross cash margin                    %          50           45          11     
Nickel Price                      5/tb        6.60         7.44        (11)     
Copper Price                    USc/lb         170          154          10     
Ave R"S rate                                  6.52         6.33           3     
Cash Costs                                                                      
Per ROM ton                      R"ton         181          163          11     
S/ton          28           26           7     
Per PGM oz                        R"oz       2,489        2,208          13     
                                  $/oz         382          349           9     
Per PGM oz after by-                                                            
product credit                    R"oz       2,362        2,070          14     
                                  $/oz         362          327          11     
Capex                                                                           
Current                         R"000s      16,522       18,453        (10)     
$"000s       2,534     2,915.00        (13)     
Expansion                       R"000s      32,635       67,198        (51)     
                                $"000s       5,005       10,616        (53)     
Mining Processed                                                                
Underground               ROM Ton "000       1,465        1,519         (4)     
Open Pit                  ROM Ton `000         125           59         112     
Total                     ROM Ton `000       1,590        1,578           1     
Grade                                                                           
Plant Head                         g/t        2.88         2.99         (4)     
Recoveries                           %          78           77           1     
PGM Production                                                                  
Platinum                           Ozs      69,129       69,875         (1)     
Palladium                          Ozs      33,420       33,728         (1)     
Rhodium                            Ozs      12,250       12,499         (2)     
Gold                               Ozs         563          567         (1)     
Total                              Ozs     115.362      116,669         (1)     
Base Metals                                                                     
Production                                                                      
Nickel                          Tonnes         110          119         (8)     
Copper                          Tonnes          48           53         (9)     
Chromite (000)            Tonnes (000)         275          261           5     
Data reflects 100% of                                                           
mine                                                                            
operations                                                                      
operations                                                                      
                              Current     Previous       +/- %          YTD     
                             3 months     3 months                 3 months     
                                   to           to     Year on           to     
Sept 05       Sept04        Year         Sept     
                                                                       2005     
Safety                                                                          
DIIR                             0.65         0.94        (31)         0.65     
Revenue                                                                         
Gross Revenue                     573          257         123          573     
PGM basket Price                  813          672          21          813     
Gross cash margin                  50           36          39           50     
Nickel Price                     6.60         6.00          10         6.60     
Copper Price                   170.00          129          32          170     
Ave R"S rate                     6.52         6.34           3         6.52     
Cash Costs                                                                      
Per ROM ton                       181          189         (4)          181     
                                   28           30         (7)           28     
Per PGM oz                      2,489         2436           2        2,489     
                                  382          384         (1)          382     
Per PGM oz after by-                                                            
product credit                  2,362        2,333           1        2,362     
                                  362          368         (2)          362     
Capex                                                                           
Current                        16,522        1,455       1,036       16,522     
                                2,534          229       1,007        2,534     
Expansion                      32,635      115,420           -       32,635     
                                5.005       18,199           -        5,005     
Mining Processed                                                                
Underground                     1,465          803          82        1,465     
Open Pit                          125           65          92          125     
Total                           1,590          868          83        1,590     
Grade                                                                           
Plant Head                       2.88         3.02         (5)         2.88     
Recoveries                         78           80         (3)           78     
PGM Production                                                                  
Platinum                       69,129       40,389          71       69,129     
Palladium                      33,420       19,471          72       33,420     
Rhodium                        12,250        7,285          68       12,250     
Gold                              563          342          65          563     
Total                         115,362        67487          71      115,362     
Base Metals                                                                     
Production                                                                      
Nickel                            110           63          75          110     
Copper                             48           27          78           48     
Chromite (000)                    275           50         450          275     
Statistical Information: Marikana: (Aquarius 100%)                              
                                           Current     Previous           %     
Change     
Data reflects                                                                   
100% of nine                     Unit                                           
operations                                 Quarter      Quarter     Quarter     
Sept         June          on     
                                              2005         2005     Quarter     
Safety                                                                          
                         Rate/200,000                                           
DIIR                        man hours         0.80         0.81         (1)     
Revenue                                                                         
Gross Revenue                      RM          127          105          21     
PGM basket Price                 $!oz          800          746           7     
Gross cash                                                                      
margin                              %            8            8           -     
Nickel Price                     5/lb         6.60         7.44        (11)     
Copper Price                   USc/lb          170          154          10     
Ave R/$ rate                                  6.52         6.33           3     
Cash Costs                                                                      
Per ROM ton                     R/ton          280          239          17     
5/ton                              43           38          (5)          43     
Per PGM oz                       R/oz         4268        3,578          19     
$/oz                              655          565           16         655     
Per PGM ounce                                                                   
after by product                 R"oz        4,051        3,342          21     
credit                                                                          
$/oz                              621          528           18         621     
Capital                                                                         
expenditure                                                                     
Current                         R000s        3,434        6,053        (43)     
                               $`000s          527          956        (45)     
Expansion                       R000s            -            -                 
                               $`000s            -            -           -     
Processed                                                                       
                                  ROM                                           
Underground                   Ton"000            8            -           8     
                                  ROM                                           
Open Pit                      Ton"000          409          403           1     
                                  ROM                                           
Total                         Ton"000          417          403           3     
Grade                                                                           
Plant Head                        g/t         3.26         3.20           2     
Recoveries                          %           62           65         (5)     
PGM Production                                                                  
Platinum                          Ozs       17,244       16,893           2     
Palladium                         Ozs        7,409        7,402           0     
Rhodium                           Ozs        2,466        2,428           2     
Gold                              Ozs          203          217         (6)     
Total                             Ozs       27,322       26,940           1     
Base Metals                                                                     
Production                                                                      
Nickel                         Tonnes           40           45        (II)     
Copper                          Tomes           24           27        (11)     
Chromite (000)           Tonnes (000)           60           66         (9)     
                                  YTD     Previous     Previous         YTD     
Data reflects                                                                   
100% of nine                                                                    
operations                    3months     3 months      Year on     Quarter     
                                   to           to      Year to        Sept     
                               Sept05       Sept04       Sept05        2005     
Safety                                                                          
DIIR                             0.80         0.80            -        0.80     
Revenue                                                                         
Gross Revenue                     127           82           55         127     
PGM basket Price                  800          685           17         803     
Gross cash                                                                      
margin                              8       (37.8)          n/a           8     
Nickel Price                     6.60         6.35            4        6.60     
Copper Price                      170          129           32         170     
Ave R/$ rate                      652         6.34            3        6.52     
Cash Costs                                                                      
Per ROM ton                       280          282          (1)         280     
5/ton                              44          (3)           43                 
Per PGM oz                      4,268        5,198         (18)       4,268     
$/oz                              820         (20)          655                 
Per PGM ounce                                                                   
after by product                4,051        5,100         (21)       4,051     
credit                                                                          
$/oz                              804         (23)          621                 
Capital                                                                         
expenditure                                                                     
Current                         3,434        5,100         (33)       3,434     
                                  527          804         (34)         527     
Expansion                           -            -                        -     
Processed                           -            -            -           -     
Underground                         -                                     8     
Open Pit                          409          400            2         409     
Total                             417          400            4         417     
Grade
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: