DRDGold Limited - Report On Activities For The Third Quarter Ended 31 March 2006
DRDGOLD LIMITED                                                                 
(Incorporated in the Republic of South Africa)                                  
(Registration number 1895/000926/06)                                            
ARB number 086 277 616                                                          
JSE trading symbol: DRD                                                         
ISIN Code: ZAE000058723                                                         
Issuer code: DUSM                                                               
Nasdaq trading symbol: DROOY                                                    
ASX trading symbol: DRD                                                         
("DRDGOLD" or "The Company")                                                    
REPORT ON ACTIVITIES FOR THE THIRD QUARTER ENDED 31 MARCH 2006                  
OF THE 2006 FINANCIAL YEAR                                                      
GROUP RESULTS (Unaudited)                                                       
KEY FEATURES                                                                    
- Group gold production steady at 129 657 oz                                    
- Australasian production 27% lower due mainly to planned West Wall changes at  
Porgera                                                                         
- Blyvoor"s new mine plan kicks in; early intersection of Alpha Dyke            
- Ministerial approval for Top Star                                             
- High grade exploration results continue at Tolukuma and Vatukoula             
KEY RESULTS SUMMARY                                                             
GROUP                Quarter    Quarter      % 9 Months to   Quarter            
Mar 2006   Dec 2005  Change   Mar 2006  Mar 2005            
Attributable gold production(*)                                                 
Australasian Operations                                                         
                oz    42 979     58 850    (27)   169 749     79 334            
kg     1 337      1 832    (27)     5 282      2 467            
South African Operations                                                        
                oz    86 678     71 407     21    225 795     60 733            
                kg     2 696      2 221     21      7 023      1 889            
Discontinued operations                                                         
                oz         -          -      -          -     47 584            
                kg         -          -      -          -      1 480            
Group           oz   129 657    130 257      -    395 544    187 651            
kg     4 033      4 053      -     12 305      5 836            
Cash operating costs                                                            
Australasian operations                                                         
              US$/oz     514        341    (51)       371        227            
ZAR/kg 102 286     71 782    (42)    76 540     44 169            
South African Operations                                                        
              US$/oz     511        463    (10)       468        418            
              ZAR/kg 103 519     97 532     (6)    96 493     81 002            
Group         US$/oz     512        406    (26)       426        412            
              ZAR/kg 103 156     85 449    (21)    87 825     81 222            
Gold price received                                                             
              US$/oz     561        487     15        502        431            
ZAR/kg 112 633    102 555     10    103 547     83 341            
Capital expenditure                                                             
            US$ million  6.8       12.2     45       24.3        1.3            
            ZAR million 41.2       79.8     48      155.7        7.1            
* Attributable - Including Emperor Mines Limited ("Emperor") 39.52% from 5      
December 2005 (previously 45.33%); Crown Gold Recoveries (Pty) Limited ("CGR")  
and East Rand Proprietary Mines Limited ("ERPM") (100%) from 1 December 2005    
(previously 40%)                                                                
STOCK                                                                           
ISSUED CAPITAL                                                                  
316 292 684 ordinary no par value shares                                        
5 000 000 cumulative preference shares                                          
Total ordinary no par value shares issued and committed: 349 489 303            
STOCK TRADED                     JSE         NASDAQ        FRANKFURT            
Avg. volume for the quarter                                                     
per day (000)                    674          4 311              123            
% of issued stock traded                                                        
(annualised)                      56            356                6            
Price - High                  R12.10        US$2.02        Euro 1.66            
      - Low                   R 7.80        US$1.24        Euro 1.05            
- Close                 R 9.20        US$1.55        Euro 1.26            
SAFETY                                                                          
It is with deep regret that we record the deaths of two employees at the South  
African operations during the quarter under review. Alfonso Magumane died in a  
shaft incident underground at ERPM on 16 February and Castigo Nhuzuane in a fall
of ground at Blyvooruitzicht Gold Mining Company Limited ("Blyvoor") on 21      
March. In the previous quarter, the South African operations were fatality-free.
At Blyvoor, both the Disabling Injury Frequency Rate ("DIFR") and the Reportable
Injury Frequency Rate ("RIFR") improved; the former from 6.37 to 5.1 and the    
latter from 2.29 to 0.74. At ERPM, the DIFR deteriorated from 14.58 to 16.41,   
while the RIFR improved from 9.28 to 4.6. At the CGR surface operation, the DIFR
improved from 5.10 to 3.76 in the quarter under review, but the RIFR            
deteriorated from 2.54 to 3.76.                                                 
The Australasian operations were fatality-free in the quarter under review. At  
Tolukuma Mines Limited ("Tolukuma"), however, both the DIFR and RIFR            
deteriorated from 0 to 3.98. At Emperor, the Lost Time Injury Frequency Rate    
("LTIFR") remained unchanged at 2, while the DIFR improved from 5 to 4.         
PRODUCTION                                                                      
Group gold production was virtually unchanged at 129 657 ounces ("oz"). While   
gold production from the South African operations increased by 21% to 86 678 oz,
that from the Australasian operations declined by 27% to 42 979 oz. In South    
Africa, gold production from ERPM"s underground operation was higher; in        
Australasia, gold production was lower at all three operations but the major    
negative impact arose from planned West Wall changes at Porgera. Production     
movements are discussed in more detail in the operation-by-operation            
commentaries below.                                                             
Australasian operations                                                         
Porgera              Quarter    Quarter       % 9 mnths to   Quarter            
Mar 2006   Dec 2005  Change   Mar 2006  Mar 2005            
(20% of the Joint                                                               
Venture)                                                                        
Ore milled    t"000      241        270    (11)        792       297            
Yield         g/t       3.15       3.83    (18)       3.97      5.07            
Gold produced oz      24 410     33 218    (26)    101 023    48 406            
              kg         760      1 034    (26)      3 144     1 506            
Cash operating costs                                                            
US$/oz     455        288    (58)        318       191            
              ZAR/kg  90 457     60 685    (49)     65 605    37 073            
Capital expenditure                                                             
            US$ million  1.1        6.8     84         9.8       0.9            
ZAR million  5.8       44.4     87        63.0       5.0            
An 11% decline in ore milled to 241 000 tonnes ("t") and a planned 18% drop in  
yield to 3.15 grams per tonne ("g/t") arising from increased treatment of       
stockpile led to a 26% decline in attributable gold production to 24 410 oz.    
Major factors contributing to lower throughput were the continued utilisation of
resources for the removal of slip material from the West Wall failure which is  
now 36% complete; power outages due to vandalism of pylons (7days lost); and the
disruption of fuel supplies arising from damage to a bridge caused by heavy     
rains. This bridge has since been repaired. Six full days and six half days were
also lost due to a strike by the local workforce during the take-over bid of    
Placer Dome by Barrick Gold.                                                    
Cash operating costs were 58% higher at US$455 per ounce as a consequence of    
lower production.                                                               
Tolukuma             Quarter    Quarter       % 9 mnths to   Quarter            
                    Mar 2006   Dec 2005  Change   Mar 2006  Mar 2005            
Ore milled    t"000       47         54      (13)       148       52            
Yield         g/t       7.70       9.52      (19)      8.91    11.27            
Gold produced oz      11 659     16 524      (29)    42 382   18 878            
              kg         362        514      (29)     1 318      586            
Cash operating costs                                                            
US$/oz     637        447      (43)       497      321            
              ZAR/kg 127 122     94 105      (35)   102 624   62 404            
Capital expenditure                                                             
            US$ million  1.3        2.5       48        4.9      0.5            
ZAR million  8.0       16.4       51       31.7      3.2            
Gold production was 29% lower at 11 659 oz, reflecting a 13% decline in ore     
milled to 47 000 t and a 19% drop in yield to 7.70 g/t.                         
Production for the period was severely impacted by the loss of the hydro on two 
separate occasions: the first when a landslide resulting from excessive rain    
severed the headrace pipeline and the second when non ML104 landowners aired an 
unfounded grievance by blocking the intake. These resulted in the loss of 10    
days of production.  Flooding of the main production area, resulting from the   
same rains, forced production to be moved to the upper areas of the mine with   
delays incurred due to ordered pumps arriving late on site. Total development   
increased by 13% quarter on quarter.                                            
The lower production was the main contributor to a 43% increase in cash         
operating costs to US$637 per ounce.                                            
Emperor                                                                         
39.52% attributable from 5 December 2005 (previously 45.33%)                    
                     Quarter    Quarter       % 9 mnths to   Quarter            
Mar 2006   Dec 2005  Change   Mar 2006  Mar 2005            
Ore milled    t"000       36         48     (25)       138        63            
Yield         g/t       5.97       5.92       1       5.94      5.95            
Gold produced oz       6 910      9 108     (24)    26 344    12 050            
kg         215        284     (24)       820       375            
Attributable gold production from the company"s Vatukoula mine was 24% lower,   
reflecting a 25% decline in ore milled to 36 000 t. Lower tonnage resulted from 
restricted access to high-grade areas due to water in-flow, de-watering and     
deteriorating ground conditions. DRDGOLD"s attributable tons and gold were also 
affected by the reduction of the company"s equity holding in Emperor from 45.33%
to 39.52% with effect 5 December 2005. New support standards have been          
introduced to improve conditions while the issue of dewatering will be addressed
through the new capital project plan as part of the accelerated development and 
training programme. Yield increased by 1% to 5.97 g/t.                          
Total development decreased from 3 009 metres to 2 915 metres quarter on        
quarter.                                                                        
Cash operating costs rose by 18% to US$691 per ounce, reflecting lower gold     
production.                                                                     
In line with a change to the mine plan announced in the previous quarter, in    
terms of which production is being re-directed from the lower grade Smith Shaft 
areas to high-grade Philip Shaft sources, work on various infrastructure-related
improvements continued at Philip Shaft during the quarter. Production from Smith
Shaft has now been ceased.                                                      
The implementation of the new "Accelerated development and training plan" is    
designed to introduce flexibility to production areas, to improve infrastructure
and increase the productivity of the workforce.  The plan includes development  
of higher grade areas in the vicinity of Philip Shaft and upgrading of          
associated shaft infrastructure. In addition, the entire workforce will undergo 
a comprehensive assessment, re-skilling and retraining programme.               
Over the next 18-months, Emperor will invest F$27 million in capital            
expenditure.                                                                    
A Workers Relief Fund of F$300 000 has been committed by the Fijian Government  
to assist employees.                                                            
South African operations                                                        
Blyvoor              Quarter    Quarter       % 9 mnths to   Quarter            
                    Mar 2006   Dec 2005  Change   Mar 2006  Mar 2005            
Area mined m2 000         36          33      9         104       36            
Development m           679         579     17       1 987       453            
Face length m         1 413       1 193     18       1 278     1 234            
Stoping width cm        110         106     (4)        108       108            
Ore milled                                                                      
  Underground t"000      171        152     13         496       140            
  Surface     t"000      927        914      1       2 714       780            
  Total       t"000    1 098      1 066      3       3 210       920            
Yield                                                                           
  Underground g/t       4.59       6.18    (26)       5.65      7.36            
  Surface     g/t       0.38       0.32     19        0.34      0.27            
  Total       g/t       1.03       1.15    (10)       1.16      1.35            
Gold produced                                                                   
  Underground oz      25 238     30 190    (16)     90 054    33 115            
              kg         785        939    (16)      2 801     1 030            
  Surface     oz      11 221      9 292     21      29 709     6 880            
kg         349        289     21         924       214            
  Total       oz      36 459     39 482     (8)    119 763    39 995            
              kg       1 134      1 228     (8)      3 725     1 244            
Cash operating costs                                                            
US$/oz     551        454    (21)        459       422            
              ZAR/kg 109 914     95 564    (15)     94 699    81 606            
Capital expenditure                                                             
            US$ million  2.4        2.0    (21)        6.6     (0.1)            
ZAR million 15.1       13.1    (15)       42.5     (0.6)            
Total gold production was 8% lower at 36 459 oz, due to a 16% decrease in gold  
production from underground to 25 238 oz. Surface gold production increased by  
21% to 11 221 oz.                                                               
A 13% increase in underground ore milled to 171 000 t was insufficient to offset
the impact of a 26% decline in underground yield to 4.59 g/t. Both an increase  
in tonnage and a decline in yield were anticipated in terms of the new mine plan
announced at the end of the previous quarter, implementation of which began     
during the quarter under review. However, interception of the Alpha Dyke in the 
No 5 Shaft high grade area earlier than anticipated negatively affected output. 
Drilling to better determine the location and extent of the dyke has begun.     
Seismicity also negatively affected production in the area. Damaged stoping has 
had to be re-opened in order that mining can be resumed. Faulting encountered in
the high-grade S section in the No 5 Shaft area led to a higher than expected   
level of off-reef mining and, consequently, lower yield.                        
In terms of the new mine plan, mining in the seismically active high-grade B5A  
area has been reduced in the interests of employee safety and is being increased
in the No 4 Shaft and lower-grade No 6 Shaft areas. Overall production from     
underground is expected to reach 70 000 t by September 2006.                    
Phase 1 of the No 2 Sub-shaft Project - involving the re-establishment of access
to No 2 Shaft from No 5 Shaft and development and stoping of mining areas en    
route - was completed during the quarter, some three months ahead of schedule.  
Phase 2 of the project - involving the re-equipping of the sub-shaft - is under 
review.                                                                         
While heavy rainfall reduced recoveries from the slimes retreatment project and 
gold production was 2% lower as a consequence, gold production from the         
treatment of rock dump material increased by 90%, resulting in the overall      
increase in gold production from surface sources.                               
Overall cash operating costs increased by 21% to US$551 per ounce, reflecting a 
34% increase in underground cash operating costs to US$692 per ounce due to     
lower underground gold production. Surface cash operating costs decreased by 8% 
to US$233 per ounce.                                                            
Crown                                                                           
100% attributable from 1 Dec 2005(Previously 40%)                               
                     Quarter    Quarter       % 9 mnths to   Quarter            
                    Mar 2006   Dec 2005  Change   Mar 2006  Mar 2005            
Ore milled    t"000    1 946     1 255      55       4 095       841            
Yield         g/t       0.37      0.41     (10)       0.40      0.39            
Gold produced oz      23 213    16 635      40      52 136    10 643            
              kg         722       517      40       1 621       331            
Cash operating costs #                                                          
              US$/oz     502       391     (28)        416       428            
              ZAR/kg  99 841    82 486     (21)     85 809    82 723            
Capital expenditure #                                                           
US$ million  1.3       1.5      13         3.3       0.7            
            ZAR million  7.8      10.0      22        21.0       4.4            
# Represents total operation                                                    
Gold production for the operation as a whole was 18% lower at 23 213 oz,        
reflecting a 7% decline in ore milled to 1 946 000 t. Heavy rainfall during     
January and February 2006 and piping infrastructure failures on the CMR         
reclamation site and on the residue disposal system impacted negatively on      
throughput at the Crown plant in particular. Yield was 12% lower at 0.37 g/t,   
reflecting depletion of higher grade material from the CMR reclamation site and 
an increase in production from the lower grade Robertson Deep reclamation site. 
Replacement of high-risk sections of the CMR pipeline is scheduled for          
completion during the fourth quarter and planning for the replacement of one of 
the two residue pipelines is well advanced. The Minister of Minerals and Energy 
has given consent that an application for a mining license in respect of the Top
Star dump to the south of Johannesburg"s Central Business District be submitted.
This brings to three, the number of approvals considered favourably by the      
Department of Minerals and Energy since DRDGOLD South African Operations (Pty)  
Limited ("DRDSA") concluded its Black Economic Empowerment ("BEE") transaction  
in December 2005.                                                               
Due to lower gold production, cash operating costs increased by 28% to US$502   
per ounce.                                                                      
ERPM                                                                            
100% attributable from 1 Dec 2005(Previously 40%)                               
                     Quarter    Quarter       % 9 mnths to   Quarter            
Mar 2006   Dec 2005  Change   Mar 2006  Mar 2005            
Area mined m2 # 000       16         16       -          50        16           
Development #   m        157       413     (62)        906       253            
Face length #   m        725       723       -         715       694            
Stoping width # cm       135       132      (2)        133       126            
Ore milled                                                                      
 Underground  t"000       72        42      71         148        30            
 Surface      t"000      537       381      41       1 124       197            
Total        t"000      609       423      44       1 272       227            
Yield                                                                           
 Underground  g/t       8.86      7.81      13        8.36      7.61            
 Surface      g/t       0.38      0.38      (1)       0.39      0.42            
Total        g/t       1.38      1.13      23        1.32      1.38            
Gold produced                                                                   
 Underground  oz      20 512    10 545      96      39 776     7 433            
              kg         638       328      96       1 237       231            
Surface      oz       6 494     4 745      37      14 120     2 662            
              kg         202       148      37         440        83            
 Total        oz      27 006    15 290      77      53 896    10 095            
              kg         840       476      77       1 677       314            
Cash operating costs #                                                          
              US$/oz     493       491       -         464       462            
              ZAR/kg  98 045   103 518       5      95 678    89 408            
Capital expenditure #                                                           
US$ million  0.7       0.7       -         1.4         -            
            ZAR million  4.4       4.3      (2)        8.9         -            
# Represents total operation.                                                   
Total gold production was 2% higher at 27 006 oz, reflecting an 11% increase in 
gold production from underground to 20 512 oz.  Production from the Cason       
surface operation was 18% lower at 6 494 oz.                                    
Higher gold production from underground resulted from a 1% increase in ore      
milled to 72 000 t and a 9% increase in yield to 8.86 g/t. Traversing of the 16-
metre, up-throw fault on the eastern side of the mine is now 90% complete; in-  
situ grades continue to be very pleasing and separation of reef and waste       
underground is substantially improving recoveries.                              
Refurbishment of the Far East Vertical ("FEV") Shaft decline conveyor continues 
and is scheduled for completion by the end of the June quarter. The design and  
modification of the conveyor in order to split the belt into two sections, thus 
reducing tension and the incidence of breakdowns, is under consideration. A belt
splicing issue, which resulted in 206 hours of downtime during the quarter, has 
been resolved by a switch from cold- to hot-splicing.                           
Opening up and development above 70 level in order to reduce dependence on      
production via the decline is progressing well and is expected to provide 150   
metres of extra face length. Production from 66 level is scheduled to begin     
during May 2006.                                                                
Planning for the exploration drilling programme of the ERPM extension (Sallies  
lease area) has been completed and the contract has been placed. Exploration    
drilling will begin during May 2006.                                            
Design and costing of the pumping upgrade project - intended to both increase   
water pumping levels and create mud pumping capacity, which will impact         
positively on gold recovery - have been completed. The project will begin once  
funding arrangements are in place.                                              
Phase 2 of the plugging project continues and is scheduled for completion by the
end of June 2007.                                                               
Lower gold production from the Cason surface operation resulted from a 14%      
decrease in throughput to 537 000 t. Yield was unchanged at 0.38 g/t. A mill    
bearing failure in the ERPM plant during the quarter under review, which        
negatively affected throughput, has been repaired. Commissioning of two         
additional mills at the Knights plant during the June quarter is expected to    
significantly improve surface throughput and recovery efficiencies.             
Overall cash operating costs increased slightly to US$493 per ounce with cash   
operating costs from underground 7% lower at US$470 per ounce.                  
Discontinued operations                                                         
North West                                                                      
(Hartebeestfontein and Buffelsfontein mines)                                    
                     Quarter    Quarter       % 9 mnths to   Quarter            
                    Mar 2006   Dec 2005  Change   Mar 2006  Mar 2005            
Ore milled    t"000       -         -        -        -          566            
Yield         g/t         -         -        -        -         2.61            
Gold produced oz          -         -        -        -       47 584            
              kg          -         -        -        -        1 480            
Cash operating costs                                                            
US$/oz      -         -        -        -          665            
              ZAR/kg      -         -        -        -      133 275            
Capital expenditure                                                             
            US$ million   -         -        -        -        (0.1)            
ZAR million   -         -        -        -        (0.7)            
EXPLORATION - TOLUKUMA                                                          
Exploration activities in the quarter have focused on drilling targets          
peripheral to the main mineralised centres at Tolukuma, with drilling and       
surface sampling targeting extensions to the main structures. This focus will   
change in the coming quarter with the availability of three underground drill   
rigs. These rigs will target the highest priority targets within the Tolukuma   
Mine Corridor, being the Tolimi, Tolukuma, Fundoot and Gulbadi structures at    
depth, and the highly prospective Zine structure, which has returned bonanza    
style grades from recent exploration development.                               
Zine Underground Development                                                    
Exploration development along the Zine 1525 south level commenced in late       
February to determine what potential for mineralisation existed at the          
intersection of the Zine and high grade Tinnabar structures. Previous data      
suggested that there may be potential if the correct controls of mineralisation 
could be intersected. This recent development has shown that the Zine structure 
does indeed have significant potential to host bonanza style mineralisation,    
along a significant vertical and strike extent.                                 
Selected results from development channel sampling on the 1525 south level are  
listed below.                                                                   
Channel No.    Width     Grade                                                  
282            1.5 m     13.3 g/t Au and 117 g/t Ag                             
285            1.7 m     21.7 g/t Au and 100 g/t Ag                             
288            1.9 m     49.0 g/t Au and 35 g/t Ag                              
291            1.9 m     50.4 g/t Au and 92 g/t Ag                              
292            2.0 m     84.6 g/t Au and 31 g/t Ag                              
295            1.9 m     25.9 g/t Au and 44 g/t Ag                              
The average value of continuous mineralised drive development completed on this 
structure during the quarter is 32 metres advanced with an average vein width of
1.9m and values of 37.5g/t Au and 97g/t Ag respectively.                        
These bonanza style values have been further supported by recent development    
along the Zine structure, with the tenor and width of the structure continuing  
to provide highly encouraging results from channel sampling. This structure is  
being targeted this coming quarter with a program of drilling to determine the  
resource potential along this structure.                                        
Surface Exploration                                                             
Ridge and Spur sampling ML 104                                                  
As part of the increased understanding on the controls of mineralisation at     
Tolukuma, a program of ridge and spur sampling and creek traversing was         
completed between the Gulbadi and Kunda prospects. This work involved sampling  
across the interpreted extensions of the mine corridor which had not been       
subject to this style of exploration. This data will be used to define the      
location of the multiple vein corridors in the area and generate further targets
for trenching and drilling. Results as yet remain outstanding.                  
Surface Drilling                                                                
Gufinis                                                                         
Seven holes were completed on the Gufinis structure in the period. No           
significant intersections were returned, and it appears that with the current   
knowledge base that little prospectivity remains. No further work is planned for
this area.                                                                      
120 North Structure                                                             
Three holes targeted the 120 North vein below a 150m long zone of strong        
mineralisation delineated by surface trenching. This drilling, whilst           
intersecting encouraging epithermal textures, failed to deliver any significant 
results with values returned all less than 4g/t Au.                             
Tolukuma Footwall                                                               
Thirteen short holes tested the extent of the Tolukuma footwall mineralisation  
for a total of 1,177.9m drilling. Results returned indicate that whilst         
mineralisation does exist i.e. TFW007 1.0m @ 27.2 g/t Au, it does not occur over
either a significant vertical or lateral extent to make it economically viable. 
This area will also be reviewed to determine what potential remains.            
Banana West/Wossa Ridge                                                         
Two holes were drilled into the Wossa Ridge structure below high grade trench   
and grab sample results of up to 580g/t Au. The results returned so far do not  
support the tenor of mineralisation encountered at the surface, and this        
localised enrichment is most likely a product of weathering and mechanical      
enrichment. Further geochemical and textural analysis will be completed on the  
drill core to determine if any prospectivity remains. Importantly the Banana    
West structure continues to the northwest of Tolukuma and the structure is      
interpreted to intersect a large vegetation anomaly similar to the one which    
covered the original Tolukuma mineralisation. This area will be mapped and      
trenched to determine what is the causative factor of this anomaly.             
Kunda                                                                           
Four holes were completed at Kunda over a three hundred metre strike length.    
Results returned were disappointing. Three of the four holes intersected        
encouraging thicknesses of epithermal quartz, with widths up to 6m, however only
low grade gold and silver values were returned with a maximum result returned in
KD016 of 1.3m @ 1.4 g/t Au and 22.9 g/t Ag. Fluid inclusion and petrographical  
analysis will be carried out to determine if any potential remains along this   
structure.                                                                      
Underground Drilling                                                            
Underground drilling in the period was significantly reduced due to rig         
accessibility. This resulted in severely reduced output by the LMA-90 drill rig,
with only two holes being completed.                                            
Gulbadi Red                                                                     
Two holes were drilled in the period to the south of the main zone of           
mineralisation at Gulbadi Red. No significant results were returned. However,   
this may be in part due to the poor core recovery encountered in TU066. Further 
work is planned for this area to follow up the high grade intersections         
encountered in previous drill holes.                                            
Diamond Drilling Summary                                                        
During this quarter a total of 3,923.8m were drilled from 24 drillholes compared
to 4,936.5m in the previous quarter. The reduced meterage was due to a planned  
rebuild being completed on the Longyear 44 drill rig and the inaccessibility,   
due to flooding, of the underground drill rigs. It is expected that during this 
quarter an LM-75 drill rig will be commissioned at Tolukuma. This drill rig will
be used to target the high priority exploration targets which exist at depth and
along strike of the current mineralised centres at Tolukuma.                    
Regional Exploration                                                            
The company continued to maintain eleven Exploration Licences ("EL") covering   
9,114 sq km. Seven tenements are granted, namely EL"s 683, 1297, 1379, 1271,    
1352 and 1366 with four tenements, EL"s 580, 894, 1264, 1327 awaiting renewal.  
Activity for the quarter included maintenance of tenure matters, commencement of
field work in EL"s 1284 and EL 1297, and, completion of a major technical       
exploration review of all tenements.                                            
Exploration Field Work                                                          
EL 1284                                                                         
A field crew consisting of one contract geologist and one field supervisor      
commenced work in mid March 2006 in the Belavista prospect area conducting ridge
and spur soil sampling, trenching and creek mapping as a follow up of an        
intrusive (diorite) float with encouraging gold values, from an inferred        
porphyry source.  The most significant exposure to date is a vegetation anomaly 
(similar to the Tolukuma vegetation anomaly) on a prominent hill. Trenching and 
detailed sampling of this wider area is planned during April. The planned       
program has been hampered by extreme wet weather but is expected to be completed
by the end of April 2006. Details of field work and results will be presented in
the next quarter.                                                               
EL1297                                                                          
A Supervising Geologist, a contract geologist and three field assistants        
commenced work in mid March using Popondetta as a landing and supply base, via  
Lae. Work commenced on ridge and spur soil sampling, creek mapping and trenching
at Ioma, also investigating a porphyry or intrusion related source. Prospecting 
along extensive areas of the Oi and Milton Creeks encountered pervasive alluvial
gold throughout and in perched alluvial banks but failed to realise significant 
zones of hydrothermal alteration to indicate a major primary mineralisation     
source. Forward work includes completion of soil lines and a reconnaissance     
sampling visit to the Gira Circular Structure and to the Green Creek prospect in
EL 1366 to the south and Baranuma Prospect area in EL 1327 to the north west of 
Ioma. This work is expected to be completed by mid May and details of field work
and results will be presented in the next quarter.                              
Exploration Review                                                              
A major technical review of all exploration tenements which commenced in July   
2005 has neared completion. The technical review phase has been completed and   
final edits of eleven EL reports and a Summary Report are being finalised.      
TerraSearch completed validating and uploading all geochemical information      
across all the tenements and the Tolukuma database is now considered to be up to
date. Together with recently acquired Landsat 7 thematic images and a Aster     
(15m) digital terrain model, a comprehensive base now exists for future         
exploration planning on the existing tenements and the immediate regions.       
The tenements contain mineralisation and anomalies at all scales from individual
porphyry stocks (Cu-Au) to the Tolukuma epithermal vein (Au) system. The        
mineralisation is intimately associated with Pliocene volcanic piles and is     
expected to be connected to Miocene-Pliocene intrusions. Important controlling  
structures also occur, similar to those observed at other important deposits in 
PNG.                                                                            
Much of the "modern" exploration from the past (1960"s onward), has been        
sourced, reviewed and synthesised and has greatly assisted in defining          
individual prospects, their potential and the broader regional opportunity.     
These evaluations have highlighted and high-graded in excess of 30 separate     
prospects with several key prospects at an advanced stage requiring major       
drilling and exploration. These prospects exhibit large areas of geochemical and
geophysical anomalism. Detailed geological knowledge of the Tolukuma discovery  
base to current mining, other PNG deposits and knowledge and comparison to other
deposits worldwide has allowed screens to be applied and a ranking of prospects 
undertaken. Priorities for future exploration have been recommended.            
This exploration review establishes the basis for the aggressive A$15 million   
exploration program unveiled by Emperor at the recent Asia Mining Congress held 
in Singapore during March 2006.                                                 
EXPLORATION - EMPEROR                                                           
A$15m Exploration Program                                                       
On 29 March 2006 at the Asia Mining Congress 2006 in Singapore, Emperor unveiled
details of its extensive A$15million, 100 kilometres drilling and exploration   
program over its gold tenements in Fiji and Papua New Guinea. The combination of
the PNG gold projects with Emperor"s existing Fijian tenements makes Emperor one
of the biggest gold exploration tenement holders in both countries. The         
exploration program for PNG could help lift Tolukuma to world class status.     
Speaking at the Congress, CEO Mr Wellesley-Wood said Emperor"s tenement holdings
provided excellent opportunities to increase shareholder value. "We have highly 
prospective tenement holdings in `elephant country" with a diversified and well 
balanced portfolio of projects ranging from mine ready to green fields. We have 
a fully equipped exploration division with six rigs in PNG and 10 in Fiji which 
is supported by an extensive database across PNG and Fiji sourced from 35 years 
of physical data from full airborne and satellite imagery."                     
Also speaking at the conference, Emperor Executive Vice-President, Exploration, 
Richard Johnson, said it was one of the biggest exploration campaigns commenced 
in PNG or Fiji. "This program represents the culmination of many years of       
investigation using new exploration technologies. It is now time to start       
drilling," Mr Johnson said.                                                     
FIJI                                                                            
Vatukoula                                                                       
Drilling focus shifted back to the highly prospective Vatukoula Deeps and Basala
Project areas this quarter, following ongoing dewatering below the 17L workings.
This quarter saw a combined total of 4,789 m drilled at Vatukoula               
At Philip Shaft, recent underground diamond drilling in the vicinity of the     
Philip Shaft has targeted extensions of several flatmake structures within a    
zone of inferred resource, which was previously poorly understood and thought to
be geologically complex. This high priority target is referred to as the        
Brewster 4-Ways Target. The first hole in this programme, PU-18-074, intersected
both the Prince William and Prince flatmakes with encouraging results. The      
second hole, PU-18-075 drilled on the same azimuth but at a steeper angle, has  
intersected both the Prince William and Dolphin structures.  Program results to 
date are as follows:                                                            
Hole No.  Target  From(m) To(m)  Width  True     Grade  Remarks                 
                                        width(m) (g/t)                          
PU-18-074 PW      181.28  181.67 0.39   0.25     37.82  0.12 @ 77.25            
PU-18-074 PW      202.34  202.74 0.40   0.23     23.54  0.10 @ 55.75            
PU-18-075 PW       76.30   77.10 0.80   0.27     113.84                         
PU-18-075 Dolphin 177.33  177.94 0.61   0.35     13.87                          
Elsewhere in the Philip section, exploration focus expanded to include the      
Basala project where previously untested flatmakes are interpreted to occur     
within the footwall of Prince William flatmake.  Drill testing commenced late in
the quarter and initial results from 16L returning the following intersection:  
Hole No.  Target  From(m) To(m)  Width  True     Grade  Remarks                 
                                        width(m) (g/t)                          
PU-16-099 PW FW1   48.06   48.28 0.22   0.18     16.73                          
Fiji Regional                                                                   
There was no exploration elsewhere in Fiji.  An aggressive regional programme   
for Tuvatu and Vanua Levu is under review.                                      
SENIOR MANAGEMENT CHANGES                                                       
South Africa                                                                    
Dr Paseka Ncholo resigned as Executive Chairman of DRDSA with effect from       
January 2006. Dr Ncholo remains as a Non-Executive Director of DRDSA            
representing the interest of Khumo Gold SPV (Pty) Limited ("KBH"). Mr Niel      
Pretorius has been appointed as Acting Chief Executive Officer of DRDSA.        
Australasia                                                                     
On 18 January 2006, Mr Clyde Moore was appointed as Chief Financial Officer of  
Emperor.                                                                        
Mr Mike Marriott resigned as Chief Operating Officer of DRD Australasia and     
Director of Emperor. Mr Sean O"Connor resigned as General Manager of Vatukoula  
Gold Mine. Mr Andre Labuschagne has been appointed Acting Chief Operating       
Officer of Emperor and Mr Greg Shay appointed as Acting General Manager         
Vatukoula Gold Mine - all effective 31 March 2006.                              
On 24 April 2006, Mr Brad Gordon was appointed Chief Executive Officer of       
Emperor. Mr Gordon is a former Senior Executive of Placer Dome having also held 
the position of General Manager Porgera Joint Venture as well as country head of
Placer Dome Australasian region.                                                
Mr Mark Wellesley-Wood remains Chief Executive Officer of DRDGOLD and a Director
of Emperor. This means that executive responsibility for Emperor will pass to Mr
Brad Gordon in due course while Mr Wellesley-Wood will represent DRDGOLD on the 
Emperor board.                                                                  
MARK WELLESLEY-WOOD                                                             
Chief Executive Officer                                                         
28 April 2006                                                                   
INVESTOR INFORMATION                                                            
DIRECTORS - (*British)(**Australian)(***American)                               
Executives:                                                                     
MM Wellesley-Wood (Chief Executive Officer)*                                    
JWC Sayers (Chief Financial Officer)                                            
Non-executives:                                                                 
J Turk ***                                                                      
Independent non-executives:                                                     
DJM Blackmur**                                                                  
GC Campbell* (Non-Executive Chairman)                                           
RP Hume                                                                         
Company Secretary:                                                              
TJ Gwebu                                                                        
INVESTOR RELATIONS                                                              
For further information, contact Ilja Graulich at:                              
Tel: (+27-11) 219-8700, Fax: (+27-11) 476-2637,                                 
e-mail: ilja.graulich@za.drdgold.com,                                           
website: http://www.drdgold.com                                                 
Ebsco House 4,                                                                  
299 Pendoring Avenue,                                                           
Blackheath,                                                                     
Randburg,                                                                       
South Africa.                                                                   
PO Box 390,                                                                     
Maraisburg, 1700,                                                               
South Africa.                                                                   
Date: 28/04/2006 08:00:35 AM Produced by the JSE SENS Department                
                                                                                
                                                                                
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: