WESTERN AREAS SECURES SHORT TERM BANKING FACILITY                               
Western Areas announced today that it had secured a short term banking facility 
agreement with The Standard Bank of South Africa ("the facility") for the period
through to January 2007.  The facility has been arranged such that the Company  
can:                                                                            
-    Meet its obligations in respect of any cash calls in terms of the Joint    
     Venture Agreement with Barrick Gold South Africa (Pty) Limited;            
-    Fund its obligations in terms of the payment of the deferred premium       
     pertaining to the Company"s derivative structure;                          
-    Comply with its obligations under and in terms of the derivative structure;
-    Fund any general operational and administrative expenses incurred by the   
Company in the day to day conduct of its business.                         
The facility has been arranged following the Twin Shaft Incident ("the          
Incident") on 04 May 2006, which has resulted in the mine"s underground ore flow
having to be redirected through the South Shaft Complex, with a consequential   
reduction in throughput to an estimated 80 000 tpm (which excludes the planned  
30 000 tpm from a surface low-grade waste dump).                                
Mine and contract personnel have continued to perform above expectations as     
regards the rehabilitation of the Main Shaft of the Twin Shaft Complex, with the
re-commissioning of the Shaft being expected in early 2007 at a cost of some R80
million.                                                                        
Investigations into the cause of the Incident are still underway, and a final   
report is expected in due course.  Considerable work continues as regards the   
insurance process to determine the nature and extent of a potential claim under 
the policy, and every effort is being made to finalise the matter expeditiously.
Johannesburg                                                                    
4 July 2006                                                                     
E-mail:  info@wal.co.za                                                         
Date: 04/07/2006 11:02:05 AM Produced by the JSE SENS Department                
                                                                                
                                                                                
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: