Mon 17 Jul 2006, 10:11 Palabora - Second quarter 2006 - operations overvi
PAM
 PAM                                                                             
Palabora - Second quarter 2006 - operations overview and production             
           statistics                                                           
Palabora Mining Company Limited                                                 
(Incorporated in the Republic of South Africa)                                  
Registration number - 1956/002134/06                                            
JSE Code: PAM        ISIN: ZAE000005245                                         
("Palabora" or "the Company")                                                   
SECOND QUARTER 2006 - OPERATIONS OVERVIEW AND PRODUCTION STATISTICS             
                      2Q         3Q     4Q     1Q       2Q      1H      1H      
                     2005       2005   2005   2006     2006    2005    2006     
 Palabora mine                                                                  
Tonnes hoisted (`000                          2,743    2,672           5,415   
tonnes)               2,620      2,677  2,400                 4,955             
 Ore treated ("000    2,459      2,572  2,349  2,646    2,633   4,615   5,279   
tonnes)                                                                         
Average ore grade:   0.71       0.71   0.72   0.71     0.70    0.71    0.70    
copper (%)                                                                      
 Copper concentrates  48.4       52.9   47.8   51.5     43.0    96.4    94.5    
produced                                                                        
("000 tonnes)                                                                   
 Average concentrate  32.2       31.3   31.2   29.9     30.5    30.8    30.1    
grade:                                                                          
copper (%)                                                                      
Copper in             15.6       16.6   14.9   15.4     13.1    29.7    28.5    
concentrates                                                                    
("000 tonnes)                                                                   
Palabora                                                                        
smelter/refinery                                                                
New concentrate       71.7       75.2   82.2   42.0     83.3    147.0   125.3   
smelted on site                                                                 
("000 tonnes)                                                                   
New copper anodes     19.4       22.7   22.4   10.0     24.0    39.3    34.0    
produced                                                                        
("000 tonnes)                                                                   
Refined new copper    19.0       22.1   20.6   14.3     21.9    37.7    36.2    
produced                                                                        
("000 tonnes)                                                                   
By-products:                                                                    
Magnetite concentrate 189        267    231    251      296     390     547     
("000 tonnes)                                                                   
Refined nickel        57         37     57     35       28      91      63      
sulphate (tonnes)                                                               
Vermiculite plant                                                               
Vermiculite produced  54         53     55     48       48      102     95      
("000 tonnes)                                                                   
Palabora, situated in the Ba-Phalaborwa area of Limpopo, operates South         
Africa"s largest copper mine. After 40 years of mining from a large, open-pit   
operation, the ore is now extracted in an underground operation located         
immediately below the open pit. Overall copper production is supplemented by    
imported copper concentrates from Zambia.                                       
Daily production from the underground mine was affected by two four day         
stoppages in the production hoists but still averaged 29,392 tonnes. This was   
4% lower than the prior quarter and 2% higher than the corresponding period     
in 2005. The tonnes hoisted for the first half of 2006 were 8% higher than      
the corresponding period in 2005. In total, 2,674,660 tonnes of ore were        
hoisted in the quarter with a copper grade of 0.70%, slightly lower than the    
previous quarter. New monthly and daily average records of 1,016,383 and        
33,946 tonnes were achieved in the period respectively. A record of monthly     
copper units of 8,616 tonnes was also achieved during the month of June.        
Total mill throughput remained in line with the previous quarter.  Mill head    
grade for the quarter was slightly below the average of the first quarter,      
however the overall trend for the second quarter was steadier and higher than   
the average for January and February. The bulk of the concentrate variance      
was due to inefficiencies in the concentrate drying facility resulting in a     
build up of inventories in the thickeners and drying paddocks. The drying       
paddocks are currently used as a temporary measure whilst working on a long-    
term solution for implementation by end of the first quarter of 2007. The       
increase in the inventory of copper thickeners and paddocks accounted for 93%   
of the variance for copper in concentrate delivered to the smelter.             
Concentrate smelted and anodes produced in the first half of 2006 were lower    
compared with the first half of 2005 as a result of the 35 day smelter          
shutdown in February/March 2006. Smelting rates and copper produced during      
the second quarter of 2006 increased following the shutdown to higher levels    
compared with the same period in 2005.                                          
Refined copper production was in line with anode supply from the Smelter. New   
refined copper during the first half of the year was higher than new anode      
produced due to the Smelter shutdown during the first quarter 2006.             
Vermiculite Operations                                                          
Vermiculite production during the quarter was in line with plan and 13% below   
the corresponding quarter for 2005.  The main contributing factor for the       
lower production during the same period for 2005 was due to the fact that the   
plant feed grade had declined from 24.85% to 22%. Overall plant recovery for    
the quarter remained at 69%, which was above plan. The strong market demand     
for the coarser grades continues to exceed production in all market segments.   
Magnetite                                                                       
Higher magnetite production in the quarter was a result of an increase in       
sales volumes for both coal washery and export grades.                          
Phalaborwa                                                                      
17 July 2006                                                                    
Sponsor:                                                                        
Barnard Jacobs Mellet Corporate Finance (Pty) Limited                           
Date: 17/07/2006 10:11:53 AM Produced by the JSE SENS Department                
                                                                                
                                                                                
Profile Group (Pty) Ltd. has taken care in preparing all information on this website, but does not accept any liability for errors or out-of-date information.
Other Profile Group sites: FundsData Online (unit trust data)  |  Profile Group corporate site
[  Terms of Use |  Privacy Policy |  PAIA manual |  FAQs/Help |  Site Map |  © Copyright Reserved 2026  ]
  


Powered by ProfileData

Profile Mobile App Google Play Store Apple App Store


Follow us on: